Moment frames in high seismic states: AISC 358 from California and the Pacific Northwest to Alaska, Nevada and Utah

Most special moment frames in the United States are built in six western states. They share the same AISC 358 connections, but local codes, review agencies, climate, labor and ports change how a project chooses and builds them. Here is a state-by-state view of moment frames in high seismic states.

· 6 min read · World Steel USA engineering team

If you plotted every special moment frame built in the United States on a map, most of the points would sit in six western states: California, Washington, Oregon, Alaska, Nevada and Utah. These are the states where plate boundaries, subduction zones and active crustal faults put most urban sites in Seismic Design Category D or higher, so AISC 341 applies and every special or intermediate moment frame connection must be prequalified under AISC 358 or tested. The connections are the same everywhere. What changes from state to state is the code adoption, the review agencies, the climate, the labor market and the route the steel travels. This article looks at moment frames in high seismic states region by region. The seismic regions guide shows the underlying hazard.

What all six states share

  • ASCE 7 ground motions high enough that most sites reach SDC D, and many near faults reach E.
  • IBC adoption with state amendments, which brings in AISC 341 and AISC 358. Editions vary by state and city, so the design basis names them.
  • Special inspection of seismic steel under IBC Chapter 17, including fabrication, unless the fabricator is approved by the building official.
  • A large stock of steel moment frames in offices, hospitals, schools, labs, parking structures and data centers.

California

California carries the highest hazard and the most moment frames. The San Andreas, Hayward, San Jacinto and many smaller faults put most of the Bay Area and Southern California in high categories. The California seismic design page covers the state view.

  • Code: the California Building Code, based on the IBC with state amendments, adopted on a three-year cycle. Cities such as Los Angeles and San Francisco add local amendments.
  • Review agencies: public schools go through the Division of the State Architect and hospitals through the state's health facilities agency, under CBC chapters with added requirements for steel, testing and inspection. Expect closer review of connection calculations and more inspection.
  • Connections: RBS and WUF-W are common in high-rise and mid-rise frames; proprietary systems are well established; bolted connections are chosen where schedule or field labor drives.
  • Fabricator approval: some jurisdictions run their own fabricator approval programs; confirm early how an overseas plant is accepted, by its accreditation or by inspection at the plant.

Our page on California multi-story seismic steel buildings shows how we approach mid-rise frames there.

Washington and Oregon

The Cascadia subduction zone runs offshore of both states, capable of a very large, long-duration earthquake, and shallow crustal faults such as the Seattle fault sit under the cities. Long-duration shaking matters for moment frames: connections see more cycles.

  • Washington: Seattle, Tacoma and the Puget Sound cities are in high categories, with local amendments in Seattle. See Washington seismic steel structures.
  • Oregon: Portland and the Willamette Valley sit on soft soils with Cascadia and crustal hazard; the state code follows the IBC with amendments. See Oregon Cascadia seismic design.
  • Climate and labor: wet winters make field welding slower and require protection, which helps end plate, BFP and double-tee connections, and column trees.
  • Ports: Seattle, Tacoma and Portland put steel from Asia close to the job.

Alaska

Alaska has the highest seismic activity in the country. The 1964 Great Alaska Earthquake was the largest recorded in North America, and Anchorage was shaken hard again in 2018. See Alaska earthquake design.

  • Cold: low service temperatures may lead the Engineer of Record to specify higher Charpy toughness for plate and weld metal. Vietnamese plate mills can supply EN 10204 3.1 certificates with Charpy results on request.
  • Short season: field welding in winter needs enclosures and heat, so bolted connections and shop-welded column trees save time.
  • Snow: heavy roof snow raises the gravity shear in the AISC 358 hinge calculation; the IBC uses 0.7S where the roof does not shed snow.
  • Logistics: steel moves through the Port of Anchorage or via Tacoma, so piece size and shipping sequence matter.

Nevada and Utah

The Intermountain Seismic Belt runs through both states. The Wasatch fault follows the Salt Lake City, Ogden and Provo corridor, where most of Utah builds, and Basin and Range faulting and the Walker Lane keep Reno and western Nevada in elevated categories. Las Vegas is lower, but many sites still need seismic detailing.

  • Utah: a fast-growing market for offices, data centers, distribution and advanced manufacturing along the Wasatch Front, much of it in SDC D. See Utah Wasatch fault seismic.
  • Nevada: Reno and the Tahoe-Reno industrial corridor host large industrial and data center projects; see Nevada northern seismic design.
  • Field work: long distances from fabrication centers and a tight labor market for certified welders make bolted connections attractive.
  • Snow and elevation: mountain sites add snow load to the hinge shear.

How the region changes the connection choice

Region Common drivers Connections that often fit
California high hazard, agency review, tall frames RBS, WUF-W, proprietary systems, end plates on low-rise
Washington, Oregon long-duration shaking, wet climate RBS, end plates, BFP, column trees
Alaska cold, short season, remote sites end plates, BFP, double-tee, column trees
Nevada, Utah growth, data centers, distance RBS for long spans, end plates and BFP for speed

The Engineer of Record decides. The table only shows patterns we see when contractors bring us West Coast and Intermountain packages.

A partner for western contractors

We work for US contractors, not against them: World Steel supplies the steel structure, and the US contractor, our customer, keeps the client, the erection and the site. For western contractors bidding seismic work, that means a second fabrication source with 2,500 t of monthly capacity, which can carry a large moment frame package when local shops are booked. Our contractor partnership program sets out how we share drawings, schedules and quality records on repeat work.

The record behind that offer includes field-bolted packages of 5,000 t for the Sunpro Steel mill and 2,000 t for the Long Son petrochemical complex, heavy box columns built in our plant, and the multi-storey FPI Barracks in Guam. Our partner Smith Emery, a US testing and inspection firm, supports projects that need independent inspection. Inspection items and rates are agreed in a project inspection and test plan, so the special inspector and the building official know in advance what will be checked at the plant and what will be checked on site.

Planning checklist for a western moment frame

  • Confirm the code edition, the review agency and any local amendments in the design basis.
  • Confirm how the building official accepts the fabricator: accreditation, plant inspection, or both.
  • Choose the connection with field labor, climate and schedule in mind, not only steel weight.
  • Agree inspection hold points at the plant and on site before shop drawings are released.

Supplying a western moment frame from Vietnam

A moment frame package from our plant in Vietnam reaches the West Coast ports of Los Angeles, Long Beach, Oakland, Seattle, Tacoma and Portland; our shipping simulator shows typical voyage times. Because AISC 358 frames depend on documented quality, we plan the quality record with the shipping schedule:

  • the plant is accredited under IAS AC472, the first and only in Vietnam, audited twice a year since 2019, which building officials can review when deciding on fabricator approval;
  • the owner's inspector can visit or inspect remotely at agreed hold points, with protected zone marking available on request;
  • demand-critical shop welds follow our AWS D1.8 procedures, with UT reports per connection mark;
  • material certificates trace every moment-frame member by heat number;
  • Tekla shop drawings show every limit, protected zone and bracing point, at no extra cost.

Our work in high seismic regions includes the FPI Barracks in Guam, a US territory, and our sample Design Report shows how we document US-code steel design for review. Erection is the US contractor's scope; the Engineer of Record's design governs, and the US contractor, our customer, approves the drawings. For the seismic provisions read the AISC 341 landing. The next article covers the New Madrid zone.

Quick answers

Which US states use the most special moment frames?

California first, then Washington, Oregon, Alaska, Utah and Nevada, where most urban sites fall in Seismic Design Category D or higher and AISC 341 with AISC 358 connections applies to moment frames.

Do California schools and hospitals follow extra rules?

Yes. Public schools are reviewed by the Division of the State Architect and hospitals by the state health facilities agency, under California Building Code chapters with added structural and inspection requirements.

Can a fabricator outside the US supply a seismic moment frame?

Yes, when the building official accepts its fabricator approval, such as IAS AC472 accreditation, or when special inspection is performed at the plant. Confirm with the jurisdiction at the start of the project.

Does cold weather change moment frame fabrication for Alaska?

It can. Engineers may specify higher Charpy toughness for low service temperatures, and field welding and bolting in winter need protection and preheat, which favors shop-welded, field-bolted connections.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AISC 358-22 prequalified connections series

Twenty in-depth articles on the 2022 standard for prequalified moment connections: the design rules every connection shares, the welding and bolting chapters, each connection family a US moment frame uses, and how the choice plays out in the high-seismic West and the New Madrid zone.

Chapters 1–2Scope and design rules

What prequalification means, what changed in 2022, member limits and the moment at the column face.

Chapters 3–4Welding, bolting and QA

Backing, weld tabs, continuity plate clips, pretensioned bolts, holes and the inspection record.

Chapters 5 and 8Welded connections

The reduced beam section and the welded unreinforced flange, welded web.

Chapters 6, 7 and 13Bolted connections

Extended end plates, bolted flange plates and the double-tee.

Chapters 9–15Brackets, slots and proprietary systems

Cast bolted brackets, the slotted web, and the patented connections in the standard.

Where it appliesUS projects

Choosing a connection, and AISC 358 in the West Coast, Intermountain and New Madrid markets.