Quality control

Inspections you can witness, records you can hand to your inspector

We agree an Inspection and Test Plan with you before production. At every hold and witness point you can visit, send a third-party or special inspector, or watch live by video, and every result lands in your project records.

Inspection reportMember R-21

Inspection and Test Plan
Signed by both parties
Mill test reports
Matched by heat number
WPS, PQR, welder records
Current for this job
Fit-up and dimensions
Checked to shop drawing
Welds
Visual on every weld; NDT per your spec
Coating
Profile, DFT and adhesion recorded

Example layout. Real reports carry your project, the inspector and the date.

Eight checkpoints

Where your steel gets checked

The Inspection and Test Plan lists every check, its method, its acceptance criteria and whether it is a hold, witness or review point. The marks below are typical; yours are agreed with you before production.

Inspection and Test Plan

Signed before fabrication: the checks, the methods, the acceptance criteria and the hold and witness points.
Hold
How we check it

Incoming material

Plate, coil and sections are matched to mill test reports and logged by heat number for full traceability.
Review
How we check it

Welding qualification

WPS, PQR and welder qualifications are in place to AWS D1.1, and to AWS D1.8 for seismic frames, before production welding.
Review
How we check it

Fit-up

Assemblies are checked for fit-up, dimensions and joint preparation before welds are completed.
Witness
How we check it

Weld inspection and NDT

Every weld is visually inspected; ultrasonic, magnetic particle or dye penetrant testing follows your specification.
Hold
How we check it

Dimensional check

Lengths, hole locations and end plates are verified so connections bolt up in the field without reaming.
Witness
How we check it

Surface prep and coating

Blast cleanliness, profile, dry film thickness and adhesion are measured and recorded per coating system.
Witness
How we check it

Final release

A member is released for packing only after it has passed every earlier step.
Hold
How we check it

See a real sample

Sample Inspection and Test Plan (ITP), PEB warehouse

Free download: a sample of the ITP World Steel issues with a quotation: every check from shop drawings to packing, with hold, witness and review points for each party.

PDF · 129 KB · 5 pages · English and Vietnamese

Witness

Three ways to see it yourself

Visit the plant

Come to our plant at Hai Son Industrial Park, Tay Ninh Province, Vietnam, for a witness point or a supplier audit.

Send an inspector

Appoint a third-party agency or your special inspector; hold and witness points are notified in advance.

Watch by video

Join inspections over Zoom or Microsoft Teams from your office in the US and receive the video record afterward.

Quality inspector taking dimensions on a finished steel member Photo
Dimensional check by QC in Vietnam before a member goes on to blasting and paint.
Welder looking over the stiffeners and end plate of a heavy column Photo
Column stiffeners and end plate under inspection at World Steel, Vietnam.
Inspector walking a line of painted built-up members on the shop floor Photo
Final look at coated members before they are released to packing, World Steel plant in Vietnam.

For your building official

IAS AC472 and special inspection

The IBC calls for special inspection of structural steel fabrication, and section 1704.2.5 lets the building official accept a fabricator approved under a recognized program in place of in-plant special inspection. IAS AC472 is the accreditation program for metal building systems. World Steel holds AC472 accreditation for fabrication (Part A) and design (Part C).

Many US jurisdictions recognize IAS-accredited fabricators, but the building official decides on your project, and field inspections still apply. What the accreditation proves is that the process on this page is audited by an independent body.

IAS AC472 Center

IAS AC472, Parts A and C

Fabrication and design of metal building systems, accredited since 2019 and audited twice a year with IAS experts. The first and only accredited plant in Vietnam.

ISO 3834-2

Fusion welding quality certified by Bureau Veritas at the comprehensive level.

AWS D1.8-qualified welding

Qualified procedures and welders for seismic force-resisting frames.

Certified coating work

UL-certified coating products, applied by painters trained and certified by the paint manufacturer.

Records

Your Manufacturing Data Record

  • Mill test reports tied to heat numbers (EN 10204 3.1, Charpy V-notch on request)
  • WPS, PQR and welder qualification records
  • Your Inspection and Test Plan, signed by both parties
  • NDT results wherever the specification calls for testing
  • Dimensional inspection reports
  • Coating inspection records
  • Nonconformance reports with their closure

PEB Studio shows every record as it is created, and the full set is handed over at closeout.

Nonconformance

When a part fails inspection

A failed part cannot be packed until it is repaired or remade, inspected again and recorded. You see the report and its closure in your records instead of finding the problem with a crane on site.

  1. Tagged
  2. Quarantined
  3. Repaired or remade
  4. Re-inspected
  5. Recorded
  6. Released

Asked by US contractors

Questions on quality control

Can my special inspector witness fabrication?

Yes. Your special inspector or a third-party agency can attend hold and witness points at the plant or join by video call.

Does AC472 mean no in-plant special inspection?

It can, but only if your building official accepts it. Many US jurisdictions recognize IAS-accredited fabricators, and the decision is always theirs.

How much welding gets NDT?

All welds are visually inspected. Ultrasonic, magnetic particle or penetrant testing follows your specification and the code, and is written into the ITP.

Do I receive the quality records?

Yes. Your Manufacturing Data Record collects mill test reports, procedures and inspection reports, and PEB Studio shows them as they are created.

Is there a sample ITP I can review?

Yes. A sample Inspection and Test Plan is free in our download center. Inspection items and rates are agreed by both parties for each project.

Who checks the coating?

Our QC measures blast cleanliness, profile, dry film thickness and adhesion. Our painters are trained and certified by the paint manufacturer, and the products carry UL certification.

Keep reading

Next in how we work

World Steel designs, fabricates and supplies the steel structure. You, the US contractor and our customer, erect it, and with your Engineer of Record approve the drawings and handle the PE seal and the permit.

Agree the inspection plan up front

Send your specification. We draft the Inspection and Test Plan with hold and witness points, and you choose how to attend each one.