Engineering & standards · Submittals

One current revision for your designers, our plant and your jobsite

Your design team is in the US, our fabrication floor is in Vietnam and the erection crew is on your site, so a superseded drawing can do real damage. That is why our steel submittals run under document control: numbered sheets, tracked revisions, a written reply to every comment, and no steel cut until the drawings are approved.

Hard rule
Nothing is fabricated until its governing drawings are approved
Source
One Tekla model, so no drawing can disagree with another
Revisions
Clouded and numbered, with a running change log
Closeout
PEB Studio freezes the as-built set and every released document

Your reviewer's stamp sets the next step

Three stamps, three outcomes, one current revision

Use your normal review stamp. Each outcome triggers a fixed response on our side, logged against the sheet and revision, so no superseded drawing ever reaches the shop floor or your site.

Approved

The sheet is released to the plant. Materials are cut and fabrication starts for that release.

Approved as noted

Notes are taken into the model, the sheet is reissued with the notes clouded, and fabrication proceeds on the noted revision.

Revise and resubmit

Nothing is fabricated. We answer every comment on a response sheet, revise the model and resubmit the sheet under the next revision.

How a sheet's revisions read

  1. AIssued for approval
  2. BRevised per review comments
  3. 0Released for fabrication
  4. 1As-built, record set

11 answers from our engineers

Shop drawings questions and answers

How submittals actually run between your design team in the US, our engineers and plant in Vietnam and your jobsite: what is submitted, how reviews are answered, how revisions are controlled and what you receive at the end.

Not answered here?Send your Shop drawings question with the drawings. An engineer replies in writing.

What gets submitted 4 answers

How should our reviewer mark up the drawings?

Use your normal stamp; approved, approved as noted and revise-and-resubmit all work for us. The plant receives a release only for sheets marked approved.

What is the difference between approval drawings and shop drawings?

Approval drawings show the building as a whole, frames, bracing, anchor rods and reactions, for your Engineer of Record and plan reviewer. Shop drawings show every assembly and part with its welds, holes and coatings, for fabrication and inspection.

Are shop drawings extra?

No. Shop drawings come with every World Steel project at no extra charge, along with approval and erection drawings.

Will our architect get the steel in 3D?

Yes, as an IFC file that ships with the approval set for their coordination model.

Reviews and RFIs 4 answers

How fast do you answer review comments?

Every comment gets a written reply on a response sheet, and the revised sheets follow. Timing depends on the scope of the comments; the response sheet and revised set come back as one package so your reviewer checks once.

What is an RFI, and when do you send one?

A Request for Information: a numbered question on the contract documents when something is missing, unclear or conflicting. We send one rather than guess, and log the answer so it can be traced later.

Can we review drawings in PEB Studio instead of by email?

Yes. Released drawings, comment logs and RFIs are available in PEB Studio, and every revision stays on file. Email submittals work too if your team prefers them.

Who has to approve before fabrication starts?

The US contractor's Engineer of Record, and anyone else your contract names, such as the architect. We never fabricate from unapproved drawings.

Revisions and closeout 3 answers

How do you stop an old drawing reaching the shop floor?

Only released revisions are issued to the plant, and each new release withdraws the previous one. Drawings come from one Tekla model, so a change updates every sheet that depends on it.

How are revisions marked?

Changes are clouded on the sheet, the revision table gets a new line with date and description, and the change log records why. Your reviewer can see exactly what changed since the last look.

What do we receive at closeout?

The as-built drawing set, the IFC model, the Manufacturing Data Record and the full revision and RFI history, locked in PEB Studio so what you received is what stays on file.

More answers on every US code we design to: search all standards questions.

Submittal set

What goes out for review and why

SubmittalReviewed byPurpose
Design criteria sheetEngineer of RecordAgree the rules of the game: code edition, loads, assumptions
Approval drawings and calculationsEngineer of Record, architect, building departmentVerify the structure works and fits
Anchor rod plan and reactionsFoundation engineerDesign the footings and place the rods
Shop drawings (every project, included at no extra charge)Engineer of Record or special inspectorReview details before fabrication
Erection drawingsGeneral contractor and erectorPut the building together in sequence
As-built recordOwnerUpkeep and future changes

Revision control

Keeping every party on the latest drawing

Comment log

Every review comment gets a written reply on a response sheet and is closed out in the following revision.

Numbered RFIs

Questions on the contract documents go out as numbered RFIs, so each answer can be traced later.

Released only

You see released documents; internal working notes and pricing are kept internal.

Locked at closeout

At closeout PEB Studio locks the record, so what you received is what stays on file.

Who does what with the drawings

One drawing set, three sets of hands

Shop drawings come with every World Steel project at no extra charge. The approval loop around them works like this.

World Steel

  • Details every piece in Tekla from the approved design
  • Issues approval, shop and erection drawings under revision control
  • Fabricates only from drawings that are approved

US contractor and Engineer of Record

  • Review the drawings and return them approved, approved as noted or revise and resubmit
  • Coordinate openings, embeds and other trades against the drawings
  • Erect from the latest erection drawings

Other trades

  • Check door, duct and equipment openings against the frames
  • Send their changes before approval, not after cutting
  • Work from the same revision posted in PEB Studio

What reviewers ask

Four questions about the drawing set

The answers are part of how the set is issued.

Revision control

Is this the current revision?

Revisions are clouded and numbered, with a change log, and PEB Studio shows the current set.

Design report

Do the shop drawings match the design?

Both come from the same model, and the member sizes match the calculations.

Erection drawings

Where are the field connections shown?

Erection drawings show every field joint, with bolts and joint types.

Change control

What happens to a comment after approval?

A change after approval is a new revision, issued for approval again before it is cut.

In your submittal file

Four drawing records from approval to handover

Each one is issued in PEB Studio, and the set is frozen at closeout.

  1. Approval drawings

    Anchor bolt plan, frame elevations and bracing, for your approval.

    Sample approval drawings
  2. Shop drawings

    Every piece with its plates, welds, holes and piece mark.

    BIM and Tekla
  3. Design report

    The calculations the drawings come from.

    How the design report reads
  4. As-built set

    The final drawings in the handover data book.

    Handover documents

Real photos from World Steel

From approved drawing to packed bundle

Photographed in our own plant in Tay Ninh Province, Vietnam, and on World Steel jobs. Not stock images.

Shop crew in safety gear among rows of painted steel members Photo
Members coated and staged inside a World Steel fabrication hall, Vietnam.
Coated members drying in rows on stands in the paint hall Photo
Members drying in the World Steel paint hall in Vietnam after coating.
Painted members strapped into bundles and stacked for the voyage Photo
Bundles made up for an export shipment at the Vietnam plant.
Rows of labeled steel bundles ready to leave the plant Photo
Labeled bundles lined up for dispatch from World Steel in Vietnam.

Shop drawings never works alone

The standards and guides it works with

Each link opens the full page, with its own questions and answers.

Who does what

World Steel designs, fabricates and supplies the steel structure from its own plant in Vietnam. The US contractor, our customer, erects it, has the drawings approved and sealed by their Engineer of Record and pulls the permit.

Verified Edition: As your project specifies

Source record: https://worldsteelgroup.com/capabilities/

Last checked: November 8, 2026. Editions change on a cycle, so your Engineer of Record confirms which one your jurisdiction enforces.