Timeline
What happens once the contract is signed
Phases overlap on purpose: drawings for later sequences are still in approval while the first sequence is in the shop. Your project manager keeps every thread visible.
Kickoff call
Scope, exclusions, contacts, Incoterm, importer of record and the baseline schedule are confirmed on video. Your PEB Studio access is created.
Design and submittals
Each drawing issued and each approval due is tracked, so a slow review is flagged before it delays the shop.
Material purchasing
Plate and coil are ordered against the approved design and logged by heat number on arrival.
Fabrication
Production is tracked member by member and sequence by sequence, with photos and status in PEB Studio.
Inspection
Hold and witness points are announced ahead, so you or your inspector can attend in person or by video.
Packing and booking
Bundles are packed in erection sequence. Booking details, export documents and loading photos are shared before departure.
US arrival and site support
Your broker and trucker take the cargo to site; your crew checks it against the packing list, and our engineers answer questions against the model.
Closeout
As-built drawings and quality records are handed over, and every open item is closed in writing.
Bars show how phases overlap, not durations. Your schedule is set at kickoff for your job.
Communication
How you stay in the loop
Six channels, each with a clear rhythm. You never have to chase a status, because the record is already in PEB Studio and the next call is already booked.
A named project manager
One accountable person for schedule, documents and questions.
Progress reports
Status against schedule, shop photos, open issues and the next milestones.
PEB Studio access
Production, inspection records and packing lists as they are created.
Video meetings
Zoom or Microsoft Teams calls for reviews and witness inspections.
Revision control
Your team, erector and inspector work from the same set.
Issue log
RFIs, changes and nonconformances, each with an owner and a due date.
Scope
Who handles what on a US job
Each contract defines the split. This is the typical arrangement: World Steel designs, fabricates and supplies the steel structure; you, the US contractor and our customer, own the site.
| Item | World Steel | You, your EOR or your erector |
|---|---|---|
| Steel structure design | Calculations, drawings, submittal package | Review and approve through your Engineer of Record, who seals |
| Foundations | Anchor rod plan and base reactions | Design and pour |
| Building permit | Documents for the submittal and answers to plan review comments | Apply to the local building department |
| Fabrication, QC, packing | Yes, in our own plant in Vietnam | Witness inspections if you choose |
| Ocean freight, customs, duties, trucking | Per the Incoterm and importer of record named on the quote | Customs broker, any US duties and inland trucking unless included |
| Erection | Erection drawings and remote support from the engineers who detailed the steel | Your crew or the erector you hire builds the structure |
When something goes wrong
Issues get an owner and a closing date
No steel job is free of problems. The test is how fast they surface and get fixed. A defect found in our shop becomes a nonconformance report: the piece is held, repaired and re-inspected before it can be packed. A short or damaged item at your site is photographed, logged by piece mark and resolved by your project manager.
PEB Studio records the bundle and container of every member, so a missing purlin is traced from data rather than memory.
RFI-014Confirm door opening on gridline CYour EORBefore approval rev CAnsweredNCR-006End plate hole offset on one rafterWorld Steel QCBefore packingRepaired, re-inspectedCHG-003Add solar collateral load to roofProject managerPrice and schedule in writingApprovedSITE-002One purlin bundle strap damagedProject managerNext shipmentReplacement bookedAsked by US contractors
Questions on project management
Do you have a US office or erection crew?
World Steel has a US office in Westminster, California, but no erection crew. Projects are managed from our engineering office and plant in Vietnam by a named project manager, with video meetings and PEB Studio access. Your crew or the erector you hire builds the structure.
How often do I get updates?
Your project manager sends progress reports on the rhythm agreed at kickoff, and PEB Studio shows live status in between.
Who pays US import duties?
Imported steel can be subject to US duties. Each quote states the Incoterm and who acts as importer of record, and that party handles customs entry and any duties.
What if a piece arrives damaged or short?
Photograph it during unloading and send it to your project manager. Each item is traced by piece mark, bundle and container, and the replacement is tracked to closure.
When are calls held across the time difference?
Meetings are booked at the start or end of your US business day, and the issue log keeps moving overnight while you sleep.
Can the schedule change after kickoff?
Yes. A change to sequence or delivery dates is logged, its effect on fabrication and shipping is sent to you in writing, and the shop re-sequences once you agree.
Keep reading
Next in how we work
World Steel designs, fabricates and supplies the steel structure. You, the US contractor and our customer, erect it, and with your Engineer of Record approve the drawings and handle the PE seal and the permit.
Meet the project manager before you sign
Send your package and target site date. A project manager walks you through the baseline schedule, the reporting rhythm and the scope split for your job.