Jobsite delivery · Check-in

Steel that checks itself in at your gate

Every member and every bundle leaves our plant in Vietnam with a QR label tied to a packing list that locked when the container was sealed. Your crew scans, counts and reports from the truck, and the record runs back to the shop that made the piece.

At the gate

A delivery your crew checks against a record, not a memory

Every World Steel delivery is checked against a record that already exists: the packing list frozen when the container was sealed. Your crew is not counting steel against memory or a fax. It scans labels, and anything that does not match is reported by piece mark while the truck is still there.

  • A QR label on every member and every bundle
  • A packing list that froze when the container was sealed
  • Receiving status your team and ours see in PEB Studio
SAMPLE
Container 4 of 11Sequence 2 · gridlines C–F
  1. SealISO 17712 number matches the list Matched
  2. Bundles12 of 12 counted Matched
  3. Bundle labels12 of 12 scanned Matched
  4. Members186 of 186 matched Matched
  5. Coating scrapeRafter R2-14, 3 photos logged Reported
Report sent by piece mark, bundle and container. Synthetic data.

Before arrival

Six records in your hands before the first truck

The gate check only works if the list is there first. These reach your project team and your broker while the steel is still at sea.

19packing-list languages to pick from for your receiving crew

  • Locked packing listContainer by container and bundle by bundle, in the language your receiving crew reads. It cannot be edited after the seal.
  • Bundle list by erection sequenceWhich sequence and gridlines each bundle serves, so you know which trucks to unload first.
  • Loading photos and videoHow each container was blocked and strapped, so damage in transit is easy to tell from damage at the plant.
  • Seal number and verified gross massThe ISO 17712 seal number to check at the gate and the weight your trucker and crane plan need.
  • Erection drawings with piece marksThe same marks that are on the labels, so a member found in the yard goes straight to its place on the drawing.
  • Documents for your brokerCommercial invoice, packing list and bill of lading data, so clearance does not hold the delivery.

How the plant builds these records as it packs and loads: export packing and shipping. What your broker files at the border: US import regulations.

Check-in

Four checks between the gate and a member ready to set

Each check is a scan or a count against the locked list. Every scan updates the receiving status for your project in PEB Studio, so the office knows what is on site without calling the yard.

  1. Check the seal

    Compare the seal on the doors with the number on the packing list and photograph the container before it is opened.

    Seal matched or reported
  2. Count the bundles

    Count bundles against the list for that container. Each bundle label names its sequence and gridlines.

    Bundle count by container
  3. Scan the bundle labels

    One scan shows every member packed in that bundle and the weight to plan the lift.

    Bundle received
  4. Open in sequence and scan members

    Open bundles when their sequence is due and scan the member labels as pieces come out.

    Member received, ready to set

Short or damaged

When a piece is missing, bent or will not fit

Three different problems, three different paths. In each one your crew records the facts on the day and our team answers from the shop and loading records for that piece.

A piece looks short

Your crew

Search the piece mark. The locked list shows which container and bundle it shipped in, so most "missing" steel is found in another box.

World Steel

If the record shows it never shipped, our team confirms it from the shop data and agrees the replacement and its shipment with you.

A piece is damaged

Your crew

Photograph it on the truck, before the driver leaves, and log it by piece mark, bundle and container.

World Steel

We compare your photos with the loading photos and video to see where it happened, and agree the remedy with you: repair detail or replacement.

A piece does not fit

Your crew

Stop and send the piece mark with a photo and the measurement before anyone cuts or burns.

World Steel

We pull the shop drawing revision, fit-up and dimensional records for that member so your Engineer of Record decides on facts.

Site road · trucks enter here A B C D E F G H BUILDING FOOTPRINT Crane Seq 1 · A–C Seq 2 · C–F Seq 3 · F–H
Sample laydown plan. Each sequence is stored beside the bay it goes into and inside the crane radius; the real plan is your erector’s.

Laydown

Store it in the order it goes up

Bundles arrive labeled by sequence and gridlines. Put each sequence where the crane will pick it, and keep coated steel dry until it is set.

  • Sequence 1 · Gridlines A–CColumns, base anchors, first rafters
  • Sequence 2 · Gridlines C–FColumns, rafters, bracing
  • Sequence 3 · Gridlines F–HEnd frames, girts, trim
Off the groundBundles on timber dunnage, never in mud or standing water.
Sloped to drainCoated members tilted so rain runs off and does not sit on flanges.
Air between piecesSpacers keep air moving so condensation dries instead of staining the coating.
Near its gridlineEach sequence stored inside the crane radius of the bay it goes into.
SAMPLE
World SteelMade in Vietnam for your US project
Piece markR2-14
BundleB-031 of 48
Sequence2 · gridlines C–F
Weight1,240 kg (2,734 lb)
QR codeOne scan

The label

One scan in your yard opens the member’s whole record

The label tells your crew where the piece goes, when it is needed and what the rigging has to lift. The QR code opens the rest: the record PEB Studio built while the member moved through the plant.

  • Mill heatEN 10204 3.1 certificate of the plate it was cut from
  • InspectionsFit-up, weld and dimensional checks it passed
  • CoatingBlast profile, film thickness and adhesion readings
  • QC releaseWho released it to packing, and when

From our plant

Bundles as they leave Vietnam, as your crew will see them

Rows of labeled steel bundles ready to leave the plant Photo
Labeled bundles lined up for dispatch from World Steel in Vietnam.
Painted members strapped into bundles and stacked for the voyage Photo
Bundles made up for an export shipment at the Vietnam plant.
Steel bundles stacked high on a packing frame awaiting loading Photo
A packing frame in the Vietnam plant stacked with bundles before they are loaded out.

World Steel

What ships with every delivery

  • QR label on every member and every bundle
  • Bundles packed and shipped in erection sequence
  • Packing list locked at the seal, in your crew’s language
  • Loading photos, video, seal number and VGM for each container
  • Receiving status in PEB Studio, member by member
  • Shortage and damage reports traced against shop and loading records

The US contractor, our customer

What your team runs on site

  • Trucking from the port and site access, with your broker
  • Unloading equipment, cranes, rigging and laydown area
  • Checking in each delivery and reporting exceptions on the day
  • Storage on site and protection of coated steel
  • Erection, with drawings approved by your Engineer of Record

Questions from site teams

Jobsite delivery questions

What does our crew need to check in a World Steel delivery?

A phone or tablet that can scan QR codes and access to PEB Studio for your project. The labels, the locked packing list and the bundle list by sequence come from us before the container arrives.

How is a shortage told apart from steel that is simply in another container?

Search the piece mark. The packing list locked at the seal shows the container and bundle it shipped in. If the record shows it never shipped, our team confirms that from the shop data and agrees the replacement with you.

Who pays for damage in transit?

That follows the Incoterm and the contract for your job, and the cargo insurance under it. Our loading photos, video and seal record help show where the damage happened, so the claim goes to the right party.

Can the packing list be in our receiving crew’s language?

Yes. PEB Studio prints packing lists in 19 languages, so the list your crew checks against can be in the language it reads best.

Does World Steel unload or erect the steel?

No. World Steel designs, fabricates and ships the steel structure. Unloading, cranes, storage on site and erection are by the US contractor, our customer, with drawings approved by its Engineer of Record.

Is there a general receiving checklist we can give our site team?

Yes. Our article on receiving structural steel on site covers laydown planning, unloading and storage for any imported steel. This page covers what is specific to a World Steel delivery.

Shipping from Vietnam Export packing ISPM 15 wood packaging Receiving checklist Contractor partnership

Plan the deliveries for your next steel package

Send your drawings and the site constraints. We plan the container split and the bundle sequence around your crane and laydown area, from a plant that fabricates 2,500 metric tons a month.