In the field
Bolts only; the metal building frame needs no structural field welds
Designed to
AISC 360-22 and the RCSC Specification, plus AISC 341 when seismic rules apply
Detailing
Tekla Structures model of each joint, down to the last washer
Traceability
Each piece mark linked in PEB Studio to its weld, coating and material records
Trace a load
The ten links between roof and footing
Uplift tries to lift the roof, drifted snow presses it down and an earthquake pushes it sideways. All three travel through the same ten links, and the weakest one decides what the whole building can carry.
-
Panel to purlin
Designed by: World SteelScrew type and pattern come from tested roof assemblies, with denser spacing at corners and edges.
-
Purlin laps
Designed by: World SteelThe lap length and bolt count must deliver the continuity the purlin calculation relies on.
-
Purlin to rafter
Designed by: World SteelClips and bolts sized for both uplift and heavy snow, with anti-roll devices where the design calls for them.
-
Flange braces
Designed by: World SteelSmall angles that stop the inside rafter flange from buckling when uplift or drift flips the bending.
-
Rafter splice
Designed by: World SteelWhere a long rafter ships in pieces, bolted end plates rejoin it for the bending and shear at that spot.
-
Knee joint
Designed by: World SteelThe rafter-to-column end plate, where a rigid frame carries its peak moment.
-
Bracing
Designed by: World SteelRoof and wall braces that collect wind and seismic shear and deliver it to the base.
-
Column base
Designed by: World SteelA pinned or fixed base plate, matching the support condition the model assumed.
-
Anchor rods
Designed by: World Steel and the foundation engineerRod size, ASTM F1554 grade, layout and every reaction reach the foundation engineer well before the footing design is due.
-
Footing
Designed by: Foundation engineerEmbedment and concrete are designed by your foundation engineer from the reactions we supply.
Joint types
What drives each connection in a World Steel frame
Laid out the way a connection schedule appears on our erection drawings.
| Connection | Usual detail | Governing demand on US projects |
|---|---|---|
| Knee (rafter to column) | Extended or flush end plate, welded in the shop, bolted in the field | Snow and drift moment, uplift reversal, bolt tension |
| Rafter splice or ridge | Bolted end plates | Moment and shear, with pretension where specified |
| Bracing | Rods, angles or HSS on gusset plates | Wind and seismic shear; stricter brace rules as the Seismic Design Category climbs |
| Purlins and girts to frame | Bolted cold-formed clips | Edge and corner uplift on coasts and plains; drift beside roof steps |
| Column base | Base plate on anchor rods, shear lug if needed | Uplift, outward frame thrust and base shear |
| Crane and mezzanine supports | Brackets with seated or end-plate joints | Cyclic load, impact and vibration |
| World Steel · Tekla Structures | Designed to AISC 360-22 / RCSC | For the Engineer of Record's review and approval |
Why bolted field joints suit US crews
Welds made in our plant, bolts made on your site
In our plant
- Plates welded to members under qualified procedures and inspected before they ship
- Holes cut or drilled to the Tekla model, with laser cutting and hole-making in plate up to 100 mm (about 4 in) thick
- Coating applied and logged, including the faying surfaces your joint type allows
- Bolts, nuts and washers counted from the Tekla bolt list by joint and by shipment
On your site
- Your ironworkers bolt every frame joint: no field weld inspection on the frame
- Snug-tight, pretensioned or slip-critical, as labeled joint by joint on the drawings
- A special inspector can compare each bolted joint with the drawing
- After a storm, a heavy snow or an earthquake, bolted joints can be checked or replaced
Weather-tolerant erection
A crew can keep bolting through a Minnesota January or a Louisiana August, conditions that make field welding and touch-up painting hard to do well.
Coatings that agree
Fasteners get protection compatible with the steel around them, so they do not become the first rust spot near the ocean or in road-salt country.
Thrust at the base
A rigid frame spreads at its feet. The reactions show that horizontal thrust so the slab, hairpins or tie rods can be designed to resist it.
Plant output
2,500 t / month
About 2,750 short tons of structural steel, IAS AC472 plant in Vietnam
In your submittal
Connection documents you receive
- Joint-by-joint calculations using SAP2000 forces
- Erection drawings that give every joint its bolt grade, diameter and joint type
- Hardware lists broken down by joint and by shipment
- Anchor rod drawing with projection heights and each base plate
- Reactions at every column for every combination
- Assembly shop drawings from the same Tekla model, included at no extra charge
Read how shop drawings and the RCSC joint types are handled.
US buildings assembled with these bolted details
Asked by US project teams
Connection questions
10 answers from our engineers, grouped by topic.
Bolts and field work 4 answers
Will my erector need to weld anything?
No structural welding is needed on the metal building frame because every frame joint is bolted. Other trades may still weld embed plates, miscellaneous metals or architectural items.
Which bolt grade do you specify?
Whatever your project specification requires, which on US-code jobs is typically ASTM F3125 Grade A325 or A490. The erection drawings give the grade, diameter and joint type joint by joint.
Does every bolt have to be pretensioned?
No. RCSC lets a joint be snug-tight, pretensioned or slip-critical. We assign one to each connection during design and label it on the drawings, so the crew and the inspector work to the same instruction.
How do you make sure the holes line up on site?
Every hole comes from the same Tekla model as the drawings and is cut or drilled by machine; our laser machines cut and make holes in plate up to 100 mm (about 4 in) thick. Members are checked against the shop drawing before blasting.
Bases and foundations 3 answers
Who designs the anchor rod embedment?
We design the base plates and send the anchor rod plan with all reactions. Embedment depth, edge distance and the concrete design fall to your foundation engineer under ACI 318.
When do we get the reactions for the foundation design?
Early, ahead of the steel drawings, because the footings are poured first. The reaction package lists every column for every load combination, with seismic overstrength cases called out separately where they apply.
Can the base plates take outward thrust from the frames?
The base plates and anchor rods are designed for the thrust the frames produce, but resisting it in the ground is the foundation designer's choice: a tie through the slab, hairpins or the footing itself.
Documents and inspection 3 answers
What should we look at after a big storm or quake?
Start with corner and edge roof fasteners, trims, door jambs, brace tension and the base plates. The full season-by-season list is on our lifecycle maintenance page.
Can a special inspector check your shop welds?
Yes. Shop welds are made under qualified procedures and inspected in our plant, with results in the Manufacturing Data Record. Your inspector can witness hold points live by video or in person, and our plant is accredited under IAS AC472.
Are connection designs included in the price of the steel?
Yes. Connection design, erection drawings and shop drawings come with every World Steel project at no extra charge, for the Engineer of Record's review and approval.
Keep reading
Related engineering guides
Each one goes deeper on a part of the design this page touches.
- RCSC high-strength bolting
- Connections & anchorage system
- Seismic design
- High-wind steel buildings
- AWS D1.1 welding
- Lifecycle maintenance
All eight US site-condition guides, the standards we design to and the IAS AC472 program are on the engineering & standards hub.
Proof at scale
Photo
Photo
Get an engineer’s eyes on your US building
Share drawings, a sketch or the footprint and site address. We agree the design criteria with your Engineer of Record, then send a written scope and the list of submittals, from a plant that fabricates 2,500 metric tons of structural steel a month.