AISC 358 bolting requirements: pretensioned F3125 assemblies, installation and chapter rules

Bolted moment connections keep field welding off the job, but they move the critical work into the bolts, holes and faying surfaces. Chapter 4 of AISC 358-22 sets the AISC 358 bolting requirements every connection shares, and the connection chapters add their own. Here is the full set in one place.

· 6 min read · World Steel USA engineering team

A bolted moment connection is attractive in the United States for one reason above all: it moves welding off the jobsite. Field welding of beam flanges to columns needs certified welders, preheat, weather protection, overhead positions and ultrasonic testing on a deck. A bolted connection replaces all that with high-strength bolts that an ironworker can install and an inspector can verify quickly. The trade-off is that the bolts, the holes and the surfaces they clamp now carry the seismic demand, so they need rules as strict as any weld. Chapter 4 of AISC 358-22 sets the AISC 358 bolting requirements shared by all connections, and the bolted chapters add their own.

Section 4.1: which fastener assemblies

Bolts in prequalified connections are pretensioned high-strength bolts to ASTM F3125, in Grades A325, A325M, A490, A490M, F1852 or F2280, unless a connection chapter permits another fastener. F1852 and F2280 are the twist-off tension-control versions of A325 and A490. Our article on F3125 bolt grades explains the grades, and our structural bolts page shows what we supply with a package.

The phrase "unless permitted" matters for a few connections. The cast bolted bracket may use ASTM A354 Grade BD bolts or threaded rods, and the ConXL connection uses ASTM A574 socket-head bolts, and their chapters say so. Outside those cases, a substitute fastener takes the connection out of prequalification.

Section 4.2: installation

Installation follows AISC 341 and the RCSC Specification, the 2020 edition referenced in Section 1.2, unless a chapter says otherwise. RCSC sets the pretensioning methods: turn-of-nut, calibrated wrench, twist-off tension-control bolts and direct tension indicators, along with pre-installation verification of each lot on the job. Our RCSC page summarizes them.

AISC 341 adds its own rules for bolted joints in the seismic force-resisting system, covered in the AISC 341 series article on seismic bolted and welded joints: bolts are pretensioned, faying surfaces are prepared as the provisions require for each joint type, and bolts are not designed to share load with welds in the same faying surface. For the fabricator, the faying surface requirement becomes a paint mask on the drawing: the contact area of a slip-critical surface is left bare, or coated only with a primer qualified for the required slip class.

Section 4.3: quality control and assurance

QC and QA for bolting follow AISC 341. On the shop side that means the hole size, type and position are checked against the drawing, faying surfaces are inspected before shipping, and bolt assemblies are traceable to their lot certificates. On site, the inspection of pretensioning, including the pre-installation verification, falls to the US contractor's erector and the owner's inspector.

Extra rules in the connection chapters

Chapter 4 is short because most bolt rules live in the chapters that use them.

Extended end plates, Chapter 6

  • Bolts meet Chapter 4 (Section 6.5).
  • The gage between bolt lines may not exceed the beam flange width (Section 6.6.1).
  • The minimum pitch is the bolt diameter plus 13 mm (1/2 in.) for bolts up to 25 mm (1 in.), and the diameter plus 19 mm (3/4 in.) for larger bolts (Section 6.6.2).
  • Finger shims at the top or bottom of the connection are allowed within the RCSC limits (Section 6.6.5).
  • Table 6.1 bounds gage and pitch for each of the 4E, 4ES and 8ES layouts, and the 2022 edition sums bearing and tearout over every bolt location.

Bolted flange plate, Chapter 7

  • Flange plate bolts are A490, A490M or F2280 only, with threads excluded from the shear plane, and a maximum diameter of 28 mm (1 1/8 in.) (Section 7.4.4).
  • Bolts are symmetric about the beam axes, two per row, and the bolt group is no longer than the beam depth.
  • Beam flanges get standard holes; flange plates get standard or oversized holes, and all are drilled or sub-punched and reamed.
  • Shims up to 6 mm (1/4 in.) total may sit between plate and flange (Section 7.4.5).

Double-tee, Chapter 13

T-stubs bolt to the column flange with four or eight tension bolts and to the beam flanges with shear bolts, with holes drilled or sub-punched and reamed. The chapter warns that a double-tee can be strong enough yet too flexible to count as fully restrained, so bolt layout affects stiffness as well as strength.

Reduced beam section in an IMF, Section 5.5

For an IMF, the RBS beam web may be connected with a bolted single plate instead of a CJP weld. That plate is designed as slip-critical, with bearing at the holes limited by AISC 360 Equation J3-6a. Holes are standard, or short-slotted parallel to the flanges in the plate or the web, not both. The bolts may be pretensioned before or after welding.

A last point on supply: bolts for a seismic package are best bought as complete assemblies from one manufacturer lot, with the bolt, nut and washer certified together, rather than mixed from stock. RCSC pre-installation verification tests assemblies, not loose parts, so a mixed box can fail on site even when every piece meets its own standard.

Problems we plan out before the steel ships

Bolted moment connections fail inspections for a handful of repeat reasons, and almost all of them are decided in the shop.

  • Paint on a slip-critical surface. A full coat of finish paint over a faying surface that needed bare steel or a Class B primer means grinding on site. The paint mask belongs on the shop drawing and the paint shop's checklist.
  • Holes out of position. A bolt group that is a few millimetres off on an end plate cannot be reamed into place without changing the edge distance the design relied on. CNC hole programs checked against the Tekla model avoid that.
  • The wrong hole type. An oversized hole drilled where the chapter calls for standard holes, or a slot in both the plate and the web, takes the joint out of prequalification.
  • End plate distortion. Welding the beam flange to a thick end plate can pull it out of flat, leaving a gap at the column face that the bolts cannot close. Weld sequence, preheat and a flatness check before release prevent it, as the end-plate fabrication article explains.
  • Mixed lots. Bolts, nuts and washers that cannot be traced to one assembly lot cannot be verified on site. Bundling assemblies by lot and tagging them by connection mark keeps the erector's pre-installation check simple.

Each of these costs far more to fix in the field than to prevent in the plant, which is why we treat a bolted connection as a shop quality item first.

Why bolted connections suit overseas fabrication

For a US contractor buying steel from overseas, a bolted connection shifts quality from the field to the shop. The end plate, flange plate or T-stub is welded to the member under shop conditions, inspected and documented before it leaves the plant. What remains on site is bolting. That is one reason extended end plates are common in metal building frames and why BFP and double-tee connections are popular where field welding is expensive. The tighter tolerances it demands are covered in the bolt-hole fabrication article.

Proof from our plant and projects

Bolted connections are where most of our work already lives. Metal building frames, pipe racks and industrial structures are bolted on site, and end-plate members, flange plates and splice plates are routine output of our shop, on jobs up to the scale of the 5,000 t Sunpro Steel mill and the 2,000 t M&D Warehouse in Thailand. Hole positions come straight from the Tekla model into our CNC programs, and first-piece checks catch any deviation before the run continues.

For seismic packages we add what Chapter 4 asks: bolt grades and pretension methods listed on the drawings, faying surfaces masked in the paint system, and bolt assemblies bundled by lot and connection mark. Customers follow their order in real time in PEB Studio, from cutting to packing. The plant is accredited under IAS AC472, audited twice a year since 2019.

How we handle Chapter 4 on a job

On a World Steel moment frame package, our engineers list every bolted joint with its grade, diameter, hole type, faying surface class and pretension method on the shop drawings, mask faying surfaces in the paint system, and check hole positions on the CNC program before the plate is cut. We can supply connection plates and bolt assemblies with the steel, with certificates. The plant in Vietnam is accredited under IAS AC472. Bolting on site is the US contractor's scope, and the US contractor, our customer, approves the drawings.

For projects in the West Coast and New Madrid markets, where many contractors prefer bolted moment connections to limit field welding and the special inspection that comes with it, we also prepare a bolting schedule for the erector: each connection mark, its bolt count, grade, length and pretension method, packed and labeled in the same order as the erection sequence. It turns the site work into a checklist rather than a search through crates.

Read the bolting rules beside the AISC 341 landing and the AISC 341 and AISC 358 page.

Quick answers

Which bolts does AISC 358 require?

Section 4.1 requires pretensioned high-strength bolts to ASTM F3125 Grades A325, A325M, A490, A490M, F1852 or F2280, unless a specific connection chapter permits other fasteners.

Can bolts in a prequalified connection be snug tight?

No. Chapter 4 calls for pretensioned bolts, installed to AISC 341 and the RCSC Specification. Snug-tight joints are not used in the seismic force-resisting connections the standard covers.

What bolts does a bolted flange plate connection use?

Section 7.4.4 requires ASTM F3125 Grade A490, A490M or F2280 assemblies in the flange plates, threads excluded from the shear plane, at most 28 mm (1 1/8 in.) diameter and two bolts per row.

Does World Steel supply the bolts?

We can supply structural bolt assemblies with the steel package, to the ASTM grade the design calls for, with certificates. Installation and pretensioning on site are the US contractor’s scope.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AISC 358-22 prequalified connections series

Twenty in-depth articles on the 2022 standard for prequalified moment connections: the design rules every connection shares, the welding and bolting chapters, each connection family a US moment frame uses, and how the choice plays out in the high-seismic West and the New Madrid zone.

Chapters 1–2Scope and design rules

What prequalification means, what changed in 2022, member limits and the moment at the column face.

Chapters 3–4Welding, bolting and QA

Backing, weld tabs, continuity plate clips, pretensioned bolts, holes and the inspection record.

Chapters 5 and 8Welded connections

The reduced beam section and the welded unreinforced flange, welded web.

Chapters 6, 7 and 13Bolted connections

Extended end plates, bolted flange plates and the double-tee.

Chapters 9–15Brackets, slots and proprietary systems

Cast bolted brackets, the slotted web, and the patented connections in the standard.

Where it appliesUS projects

Choosing a connection, and AISC 358 in the West Coast, Intermountain and New Madrid markets.