Reduced beam section (RBS) moment connection: limits and design under AISC 358-22 Chapter 5

The reduced beam section is the most used prequalified moment connection in US seismic steel. By trimming the beam flanges near the column it moves the plastic hinge away from the welds. AISC 358-22 enlarged its limits a great deal. Here is how Chapter 5 works, from the cut geometry to the column checks.

· 7 min read · World Steel USA engineering team

If you walk a steel frame under construction in Los Angeles, Seattle or Salt Lake City, the beams of the moment frames often look as if someone took a bite out of them near each column. That shape is the reduced beam section (RBS), the "dogbone", and it is the most widely used prequalified moment connection in US seismic steel. It is simple, non-proprietary and needs no extra plates. Chapter 5 of AISC 358-22 sets its rules, and the 2022 edition enlarged them so much that the RBS now reaches beams that used to need a different connection.

How the RBS works

Section 5.1 describes it in one line: portions of the beam flanges are selectively trimmed next to the beam-to-column connection, so that yielding and hinge formation occur mainly within the reduced section. The column-face welds still carry a large moment, but less than they would if the beam hinged right at the face. The trimmed region becomes a controlled fuse, and the CJP flange welds, the column and the panel zone are protected by capacity design.

Section 5.2 prequalifies the RBS for SMF and IMF and exempts it from the slab isolation rule of Section 2.3.4. A composite deck can run right up to the column.

Beam limits

Section 5.3.1 lists the beam limits:

  • rolled wide-flange or built-up I-shapes meeting Section 2.3;
  • depth up to W1100 (W44), built-up sections no deeper;
  • weight up to 610 kg/m (408 lb/ft);
  • flange thickness up to 53 mm;
  • clear span-to-depth ratio of at least 7 for SMF and 5 for IMF;
  • width-to-thickness ratios to AISC 341, with the flange width taken at the ends of the center two-thirds of the cut;
  • lateral bracing to AISC 341, plus supplemental bracing near the reduced section, attached no more than half a beam depth beyond the end of the cut farthest from the column, and never inside the protected zone.

There is an exception for the supplemental bracing. Where the beam carries a concrete structural slab connected between the protected zones with welded shear connectors at no more than 300 mm (12 in.) spacing, and the beam is no larger than W920 (W36) and 450 kg/m (302 lb/ft) with a column no deeper than W920 (W36), the top and bottom flange bracing at the reduced section is not required. Larger frames need the brace.

The protected zone, Section 5.3.1(8), runs from the face of the column to the end of the cut farthest from the column.

Column limits

Section 5.3.2 accepts any rolled or built-up column of Section 2.3, with the beam connected to the column flange. Rolled columns go up to W1000 (W40); built-up wide-flange columns no deeper; cruciform columns no wider or deeper than that. Built-up box columns are limited to 600 mm (24 in.) in width and depth, as are boxed wide-flange columns that take moment frames in both directions. There is no limit on column weight and no extra flange thickness rule.

The welds and the web

Section 5.4 requires the beam flanges to be joined to the column flange with CJP groove welds meeting the AISC 341 rules for demand-critical welds, with weld access holes shaped to AISC 360. Chapter 3's backing and weld tab rules apply.

Section 5.5 sets the web connection. In an SMF, the beam web is joined to the column flange with a CJP groove weld running between the weld access holes. A single-plate shear tab at least 10 mm (3/8 in.) thick runs between the access holes and may serve as backing for the web weld. Weld tabs are not required at the ends of the web weld, and erection bolt holes in the web are allowed.

An IMF may use the same welded web or, as an exception, a bolted single-plate shear connection designed as slip-critical, with bearing limited by AISC 360 Equation J3-6a, the plate checked for shear yielding and shear rupture, and fillet welds to the column of at least 5/8 of the plate thickness on each side. Holes are standard, or short-slotted parallel to the flanges in either the plate or the web, not both.

The design procedure

Section 5.7 sets thirteen steps.

  1. Choose trial sizes and cut dimensions, within: a between 0.5 and 0.75 times the flange width; b between 0.65 and 0.85 times the beam depth; c between 0.1 and 0.25 times the flange width. Confirm the frame for all code load combinations with the reduced section, and check drift. Elastic drift may be taken as 1.1 times the gross-section drift for flange reductions up to 50 percent, interpolated for less.
  2. Compute ZRBS, the plastic modulus at the center of the cut: Zb minus 2 c tbf (d − tbf).
  3. Compute Mpr with Ze = ZRBS, per Section 2.4.3.
  4. Locate the hinge: Sh = a + b/2.
  5. Compute Vh, the shear at the hinge.
  6. Compute Mf, the moment at the column face.
  7. Compute Mpe, the expected plastic moment of the full beam: Ry Fy Zb.
  8. Check Mf ≤ ϕd Mpe. If not, deepen the cut, move it, or change the section and repeat.
  9. Check beam shear to AISC 360, with the required shear from Section 2.5.
  10. Design the web connection per Section 5.5 for that shear.
  11. Check continuity plates per Section 2.6.
  12. Check the panel zone per Section 2.7.
  13. Check the column-beam moment ratio per Section 2.8.

Step 8 is the heart of the connection: the cut must be deep enough that the moment delivered to the column face by the reduced section stays below the expected strength of the full beam. The cut radius follows from the geometry, R = (4c² + b²) / 8c, shown in Figure 5.1. Our probable maximum moment article walks through steps 3 to 6.

Design trade-offs

The RBS buys a safer joint at the cost of a weaker beam. The cut reduces stiffness, which raises drift, and it reduces strength, which may push the beam size up. In return it lowers the moment at the column face, which eases the strong-column weak-beam ratio, the panel zone and the continuity plates. In tall frames controlled by drift, designers often start with the deepest allowed cut and size the beams for stiffness; in frames controlled by strength, a shallower cut is enough.

The connection is also tolerant on site. The beam flanges are field welded to the column, so the erector can absorb length variations in the root opening, and the web is welded or slip-critical bolted. Field welding is the cost: demand-critical CJP welds, overhead bottom flange welding with backing removal, and ultrasonic testing.

RBS with built-up and heavy members

Section 5.3.1 lets the RBS work with built-up I-shaped beams, provided their profile matches a qualifying rolled shape and their web-to-flange joint is a CJP weld with reinforcing fillets from the beam end to one beam depth past the hinge, as Section 2.3.2a requires. For a reduced beam section, the hinge sits at the center of the cut, so the CJP zone runs well past the end of the cut. For heavy columns, the RBS accepts built-up I, boxed, box and cruciform sections within the 600 mm (24 in.) box limit. These combinations are common on the large projects we supply, where member sizes are driven by long spans and tall stories.

Where the RBS is used in the US

The RBS is the default special moment frame connection on many California multi-story seismic steel buildings, Seattle and Portland offices, Anchorage and Salt Lake City hospitals and schools, and parking structures across the West. The larger 2022 limits make it practical for long-span frames over open floors, laboratories and data halls, where W1000 (W40) and W1100 (W44) girders are common. It is also used in IMF systems on soft-soil sites in the New Madrid zone.

Proof from our plant and projects

Multi-storey frames are a core part of our work. Our multi-storey projects include the 1,500 t first phase of the Tongwei Tien Giang feed factory, office buildings for our own group, and a three-storey college of medicine in the Philippines, a school in an earthquake-prone country. For a US territory with high seismic design values we supplied the FPI Barracks in Guam.

On an RBS package, that experience means beam ends arrive with bevels, access holes and cuts made from one program, column continuity plates and doublers welded to AWS D1.8 procedures, and every limit of Section 5.3 checked on paper before steel is cut. The plant is accredited under IAS AC472, audited twice a year since 2019.

How World Steel builds RBS frames

On an RBS project our engineers check every beam and column against Section 5.3, draw the cut geometry and the protected zone on the Tekla shop drawings, and plan the column shop welds: continuity plates, doublers and shear tabs, to AWS D1.8 procedures. The flange cuts are made to Section 5.6, explained in the next article on RBS flange cut fabrication. Beam-end preparation for the field CJP welds, bevels, weld access holes and backing, is done in the shop so the erector receives ready joints.

Our plant in Vietnam is the first and only fabricator in Vietnam accredited under IAS AC472, with a fabrication capacity of 2,500 t per month for large multi-storey steel framing packages. Field welding and erection are the US contractor's scope; the Engineer of Record's design and the US contractor's approval govern. For the system rules behind the RBS, read the AISC 341 landing and the AISC 341 series article on special moment frame design.

Quick answers

What is a reduced beam section connection?

An RBS, often called a dogbone, is a moment connection in which parts of both beam flanges are cut away in a circular shape near the column, so the plastic hinge forms in the reduced section, away from the flange welds at the column face.

How large can an RBS beam be under AISC 358-22?

Section 5.3.1 allows rolled beams up to W1100 (W44), 610 kg/m (408 lb/ft) and 53 mm flange thickness, with a clear span-to-depth ratio of at least 7 for SMF and 5 for IMF.

What are the RBS cut limits?

Section 5.7 limits the start of the cut a to 0.5 to 0.75 times the flange width, the cut length b to 0.65 to 0.85 times the beam depth, and the cut depth c to 0.1 to 0.25 times the flange width.

Does an RBS need slab isolation?

No. Section 5.2 exempts the RBS from the slab isolation rule of Section 2.3.4, which is one reason it is popular in composite floor framing.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AISC 358-22 prequalified connections series

Twenty in-depth articles on the 2022 standard for prequalified moment connections: the design rules every connection shares, the welding and bolting chapters, each connection family a US moment frame uses, and how the choice plays out in the high-seismic West and the New Madrid zone.

Chapters 1–2Scope and design rules

What prequalification means, what changed in 2022, member limits and the moment at the column face.

Chapters 3–4Welding, bolting and QA

Backing, weld tabs, continuity plate clips, pretensioned bolts, holes and the inspection record.

Chapters 5 and 8Welded connections

The reduced beam section and the welded unreinforced flange, welded web.

Chapters 6, 7 and 13Bolted connections

Extended end plates, bolted flange plates and the double-tee.

Chapters 9–15Brackets, slots and proprietary systems

Cast bolted brackets, the slotted web, and the patented connections in the standard.

Where it appliesUS projects

Choosing a connection, and AISC 358 in the West Coast, Intermountain and New Madrid markets.