Engineering · Crane buildings

Crane buildings designed to US standards, up to a 150 t overhead crane.

The largest crane World Steel has designed a factory for lifts 150 metric tons (165 short tons): the steel production plant of Sunpro Steel in Can Tho, Vietnam. The same engineers size runways, crane columns and frames for US plants to CMAA, AISC and ASCE 7.

Our largest crane building

A 150 t overhead crane at Sunpro Steel, a steel maker’s own plant

The heaviest crane World Steel has designed a factory for lifts 150 metric tons (165 short tons). It runs in the steel production plant of Sunpro Steel in Can Tho, Vietnam, built in 2024 from about 5,000 t of World Steel structural steel. The engineers who designed it size crane buildings for US plants to the standards on this page.

  • Crane bays sized for a heavy mill crane: wheel loads, lateral thrust and braking forces from the crane data, combined with wind and seismic loads.
  • Laced (latticed) crane columns: one leg carries the runway, the other the roof, so a 150 t crane does not bend the roof frame.
  • Runway girders fabricated as welded plate girders, with weld details chosen for the cycles of a production crane.
  • Designed, fabricated, coated and shipped by World Steel; erection by the contractor on site.
  • 150 t

    (165 short tons)

    Rated capacity of the largest overhead crane World Steel has designed a factory for

  • About 5,000 t

    (about 5,500 short tons)

    Structural steel for the plant, World Steel’s largest single job

  • Steel production

    Can Tho, Vietnam · 2024

    A steel maker trusted us with the buildings for its own mill

  • Laced crane columns

    Separate crane legs

    Heavy runways carried on their own laced legs, apart from the roof column

Standards map

One crane bay, eight parts, and the US documents that govern each

A crane building is where a machine standard meets a building code. Tap a part of the drawing to see which document rules it and who is responsible for it.

Cross-section of a crane bay: roof frame, laced crane columns, runway girders, rail, crane bridge, trolley, end stop and foundations 150 t Crane · CMAA Rail and clips Runway girder Crane column Frame · ASCE 7 End stop Welds · AWS D1.1 Base and footing
Schematic crane bay with laced crane columns, the arrangement used for the 150 t crane at Sunpro Steel. Not to scale.
  • The craneWorld Steel or yours

    CMAA 70 · CMAA 74 · ASME B30.2

    Bridge, trolley, hoist, wheels and bumpers, designed and rated to CMAA. World Steel can supply the crane with the building, or design to the wheel loads and class from your own crane supplier.

  • Rail, clips and padsShared

    Crane maker · AISC 303 · CMAA 70 tolerances

    Rail size, clip type, splices and the alignment tolerances the crane needs to run without skewing.

  • Runway girderWorld Steel

    AISC 360 · AISC Design Guide 7 · Appendix 3 · AIST TR-13 for mills

    Strength under moving wheel loads with impact, lateral thrust on the top flange, fatigue at each weld and deflection by class.

  • Crane column or bracketWorld Steel

    AISC 360 · AISC Design Guide 7

    Bracket, stepped or laced column carrying the runway into the frame and down to the foundation.

  • Main frame and bracingWorld Steel

    ASCE 7 · MBMA · AISC 360

    Crane loads combined with dead, wind, snow and seismic loads; frame drift at runway level; longitudinal bracing for braking.

  • End stopsWorld Steel

    Crane maker bumper force · OSHA 1910.179

    Stops at both ends of each runway, sized for the bumper force and connected so the impact reaches the bracing.

  • WeldsWorld Steel

    AWS D1.1 cyclically loaded · AISC 360

    Weld joint types, profiles and inspection chosen for joints that see stress cycles, not only static load.

  • Base and foundationYour team

    AISC Design Guide 1 · ACI 318 by others

    Base plates and anchor rods from our report; footings designed by the foundation engineer on the US side.

CMAA 70 and CMAA 74

Crane service classes A to F, and what each one asks of the building

The crane maker states the class from how often the crane lifts and how close to capacity. The building engineer turns it into a runway deflection limit, a fatigue demand and the weld details on the girder.

  • Class A: Standby or infrequent service

    Powerhouses, pump rooms, motor rooms, equipment installation and maintenance

    Runway L/600Few cycles; strength governs

  • Class B: Light service

    Repair shops, light assembly, service buildings, light warehousing

    Runway L/600Low; fatigue checked

  • Class C: Moderate service

    Machine shops, paper mill machine rooms, general fabrication

    Runway L/600Moderate; weld details matter

  • Class D: Heavy service

    Heavy machine shops, foundries, steel warehouses, container yards, lumber mills

    Runway L/800High; fatigue often governs

  • Class E: Severe service

    Magnet, bucket and magnet-bucket cranes in scrap yards, cement mills, fertilizer plants

    Runway L/1000Very high; fatigue governs

  • Class F: Continuous severe service

    Custom cranes running near capacity all shift, steel mill production cranes

    Runway L/1000Highest; every detail checked

CMAA 70 covers top running bridge and gantry cranes with multiple girders, classes A to F. CMAA 74 covers top running and under running single girder cranes with an underhung trolley hoist, classes A to D. Deflection limits are those recommended in AISC Design Guide 7 and the MBMA manual, measured under maximum wheel loads without impact; the limits for your job are fixed on the design basis.

ASCE 7 crane loads

Four forces a crane puts on the building

The IBC sends crane loads to ASCE 7, which defines them from the crane maker’s data. All four act through the rail, so the runway, the column and the bracing each take a share.

  • Maximum wheel loads

    Bridge and trolley self-weight plus rated capacity, with the trolley positioned for the worst effect on the runway.

    Effect: Sizes the runway girder, the bracket or crane leg and the foundation reaction.

  • Vertical impact

    Added to the maximum wheel loads: 25% for powered monorails and cab- or remote-operated bridge cranes, 10% for pendant-operated bridge cranes, none for hand-geared cranes.

    Effect: Raises the design force on the girder and its supports; not used for deflection or the frame drift check.

  • Lateral force

    20% of the rated capacity plus the weight of hoist and trolley, applied at the top of the rail in either direction, shared by the runways in proportion to their stiffness.

    Effect: Bends the top flange sideways, loads the bracket and drives frame drift at runway level.

  • Longitudinal force

    10% of the maximum wheel loads, applied at the top of the rail along the runway.

    Effect: Carried by the runway girder and longitudinal bracing to the foundation.

Vertical impact added to maximum wheel loads, ASCE 7 crane load provisions.
Crane type and operationImpact
Monorail cranes, powered25%
Cab-operated or remotely operated bridge cranes, powered25%
Pendant-operated bridge cranes, powered10%
Bridge cranes or monorails with hand-geared bridge, trolley and hoist0%

Load cases we run on every crane building

  • One crane, trolley at the worst endMaximum wheel loads on one runway, minimum on the other.
  • Two cranes in one bayCranes side by side or bumper to bumper, as the operator will run them.
  • Crane and wind togetherCrane forces combined with wind on the walls, as ASCE 7 and MBMA combinations require.
  • Crane and earthquakeCrane self-weight in the seismic mass, parked where the design basis states.
  • Crane hitting the stopBumper force from the crane maker into the stop, girder and bracing.
  • Crane under snow and roof loadsRoof load and crane on the same column, including drift snow at steps.

Deflection and drift

Stiffness limits that keep a crane running straight

Strength keeps the building standing; stiffness keeps the crane on its rail. AISC Design Guide 7 and the MBMA manual recommend these limits. Your specification or crane maker can ask for tighter ones, and the values agreed go on the design basis.

Runway, vertical, Class A, B, CMaximum wheel loads, no impact

L/600

Runway, vertical, Class DMaximum wheel loads, no impact

L/800

Runway, vertical, Class E, FMaximum wheel loads, no impact

L/1000

Runway, lateral, all classesCrane lateral force

L/400

Frame drift at runway, pendant-operatedCrane lateral force or wind at service level

H/100

Frame drift at runway, cab-operatedCrane lateral force or wind at service level

H/240, max 50 mm (2 in)

Fatigue

Runway details chosen for millions of wheel passes

A busy runway sees a stress cycle every time a wheel rolls past, for decades. AISC 360 Appendix 3 sets an allowable stress range for each weld and plate detail; the more cycles the crane class implies, the lower that range. AWS D1.1 adds rules for cyclically loaded joints: weld profiles, backing removal and tighter acceptance.

  • Top flange to web weld

    Wheel loads pass straight through this weld. For heavy and severe classes it is made as a complete joint penetration weld; lighter classes may use fillet welds where the stress range allows.

  • Stiffener ends

    Intermediate stiffeners are fitted tight to the top flange and stopped short of the tension flange, so no weld ends where the stress range is highest.

  • Rail attachment

    The rail is clipped, not welded, to the girder. Welding a rail to the flange puts a poor fatigue detail right under the wheel.

  • Cap channels and surge plates

    Where lateral thrust is high, a cap channel or a horizontal surge girder takes it; their welds are checked as fatigue details too.

  • Girder seats and tie-backs

    The girder end is seated and tied back so it can rotate under load without cracking the connection to the column.

  • Inspection by class

    Ultrasonic testing of the top flange welds and visual checks of every runway weld, at the rates agreed in the inspection and test plan.

Steel mill buildings

AIST Technical Report No. 13: the extra rules for a steel mill

Steel producers often ask for more than the building code. AIST Technical Report No. 13, the Guide for the Design and Construction of Mill Buildings from the Association for Iron & Steel Technology (2021 edition), is the reference US mills use for buildings that carry heavy, high-cycle production cranes. It is a guide, not a code: the owner names it in the specification and picks the building class. Its crane counterpart is AIST Technical Report No. 6 for mill cranes.

Laced crane columns under the roof of the Sunpro Steel production plant
Sunpro Steel is a steel production plant, the kind of building TR-13 was written for. Its 150 t crane runs on runways carried by laced crane columns, the arrangement mill practice favors for heavy cranes.

Four mill building classes, set by load cycles

  • Class A: Over 500,000 cycles

    More than 25 lifts a day for 50 years

    Steelmaking and continuous casting, foundries, slab, billet and scrap yards, coil handling, shipping

  • Class B: 100,000 to 500,000 cycles

    5 to 25 lifts a day for 50 years

    Busy production and finishing bays, as the owner decides

  • Class C: 20,000 to 100,000 cycles

    1 to 5 lifts a day for 50 years

    Moderate-service bays, as the owner decides

  • Class D: Under 20,000 cycles

    About 1 lift a day or less

    Light-duty bays, for example motor room maintenance cranes, as the owner decides

TR-13 §1.4: the owner studies the service and sets the class for the whole building or for each part of it, normally on a 50-year service life. The class then sets the cycle count for fatigue design.

TR-13 §3.7.2: side thrust is the largest of the table value, 20% of lifted load plus trolley, or 10% of lifted load plus the whole crane; pendant cranes use 10% impact, 10% side thrust and 20% traction. Compare ASCE 7: 20% side thrust and 10% longitudinal force for every crane. Bumper force on the stops is set with the crane designer and shown on the drawings (§3.7.3).
Mill crane (TR-13 Table 3.2)Vertical impactSide thrust, of lifted loadTraction
Mill and ladle cranes25%40%20%
Magnet cranes, finished product25%40%20%
Magnet cranes, slab, billet and scrap25%100%20%
Clamshell bucket and soaking pit cranes25%100%20%
Stacker cranes25%200%20%
Motor room maintenance cranes20%30%20%

Why mill cranes push harder

A magnet lifting slabs or a stacker crane with a rigid mast swings its load hard against the runway. That is why TR-13 asks for side thrust up to the full lifted load, or twice it for stacker cranes, where ASCE 7 asks for 20%. The difference reaches the girder top flange, the rail clips, the crane column and the frame bracing.

The crane designer supplies wheel loads, wheel spacing, rail size and bumper force. When the crane uses guide rollers instead of double-flanged wheels, TR-13 asks the crane supplier to state the rail, the fastening and any tighter alignment that the rollers need.

What mill practice adds to the building

  • Stiffer runwaysVertical runway deflection from one crane, without impact, of span/1000 in Class A and B buildings and span/600 in C and D; lateral deflection span/400 (§5.8.7).
  • Tighter frame driftFrame sway at the top of the crane girder limited to height/400 or 50 mm (2 in), whichever is less, under crane lateral forces (§5.3), stricter than the H/240 common in general buildings.
  • Fatigue by classEvery member, weld and fastener under repeated load designed to the AISC 360 fatigue rules for the cycle count of its building class (§5.7).
  • Girders free to rotateSimple-span girders with separate seat and tie-back connections, so adjacent spans do not restrain each other and the ends can rotate without cracking (§5.8.1).
  • Weld inspectionRunway girder welds to the AWS D1.1 cyclic criteria; flange and web splices 100% radiographic or ultrasonic; complete penetration flange-to-web welds 100% ultrasonic, fillet welds 100% magnetic particle or dye penetrant (§5.16.2).
  • Rail clips, not hook boltsRail clips in opposing pairs at 760 mm (30 in) or closer, 460 to 610 mm (18 to 24 in) for heavy thrust, 610 mm (24 in) at most on elastomeric pads; no hook bolts in Class A or B buildings or under cranes over 18 t (20 short tons) (§5.15.3, §5.15.4).
  • Slip-critical boltsBolted connections that see fatigue or vibration are slip-critical with pretensioned high-strength bolts (§5.13).
  • Minimum thickness and camberMain members at least 8 mm (5/16 in) thick outside and 6 mm (1/4 in) inside; girders over 23 m (75 ft) cambered for dead load plus half the live load deflection (§5.12, §5.8.8).
  • Nothing added without approvalNo clips, brackets or fixtures welded to runway girders unless shown on the design drawings or approved as a revision (§5.8.9).

Source: AIST Technical Report No. 13, Guide for the Design and Construction of Mill Buildings, Association for Iron & Steel Technology, 2021. Summarized for orientation; the report and your specification govern.

In-depth articles

Mill buildings under AIST TR-13, part by part

Thirty in-depth articles on AIST Technical Report No. 13: crane classes and loads, soil and foundations, floors and process loads, frames, runway girders and the shop and service side, each paraphrasing the section it follows, with metric values first.

30 articles · 6 parts

Crane classes and loadsSections 1.4–1.5, 3.7, 3.11

Building class, dynamic crane forces, load combinations and the crane data.

Site, soil and foundationsSections 2, 3.13, 4

Soil investigation, foundations under heavy cranes and the floor slab.

Frame, roof and floorsSections 5.2–5.14

Columns, bracing, trusses, girts, equipment floors and connections.

Runway girders and railsSections 3.7.3, 5.8, 5.15

Fatigue details, stiffness, backup bracing, end stops and the rail system.

Shop, testing and serviceSections 1.6, 5.16–5.17, App. C

Weld testing, tolerances, maintenance access, inspection and upgrades.

Rails, clips and stops

The details where the crane meets the steel

Most crane building problems on site start here: a rail out of line, a clip that cannot be adjusted, a stop at the wrong height. Each one is drawn on the approval drawings before fabrication starts.

Row of laced crane columns with runway seats at the Sunpro Steel plant
Sunpro Steel, Can Tho: runway seats on the crane legs, ready for the 150 t crane runway.
  • Rail and clipsRail section from the crane maker. Adjustable clips hold it in line but let it float for temperature and allow realignment later.
  • Elastomeric padA pad under the rail on heavy and severe classes spreads the wheel load and reduces wear on the top flange and its welds.
  • Splices and gapsRail splices staggered from girder splices; joints welded or bolted as the crane maker specifies.
  • End stopsSized for the bumper force supplied with the crane and set at the height of its bumpers, at both ends of every runway.
  • Conductor bar supportsBrackets for the power conductor along the runway, located on the drawings so nothing is welded on site.
  • Alignment tolerancesSpan, straightness, elevation and rail-to-rail tolerances checked at fabrication and set out on the drawings for the field survey.

OSHA 1910.179 and ASME B30

Safety rules for the crane in use, and what they ask of the building

OSHA and ASME B30 bind the employer who runs the crane, not the steel designer. They still shape the building: clearances, stops, access and supports have to be in the design from the first drawing.

  • OSHA 1910.179

    The federal rule for overhead and gantry cranes in general industry: inspections, rated load marking, clearances, stops and bumpers, load testing and operator rules. It binds the employer who runs the crane.

  • ASME B30.2 and B30.11

    The safety standards for overhead and gantry cranes and for monorails and underhung cranes. OSHA refers to the ANSI B30.2 standard for cranes built after August 31, 1971.

  • Clearances in the design

    Room between the crane and the roof steel, columns, walls and lights, set from the crane maker’s clearance drawing before the frame height is fixed.

  • Access for inspection

    Walkways, ladders or lift access to the runway where the owner’s inspection plan needs them, shown on the drawings.

  • Stops and bumpers

    Stops at the runway ends that match the bumpers on the crane, so the crane cannot run off the end of the rail.

  • Load test and records

    The load test of the installed crane is run by the crane supplier and owner; the building design records go in the same file.

Crane data

The crane data sheet we design from

If World Steel supplies the crane, we fill this in for you; if you buy it elsewhere, ask your crane supplier for these twelve items. With them, the runway, columns and frame are designed for the real crane instead of an estimate, and nothing has to be redesigned when the crane is ordered.

Crane data sheetMetric first, US units in brackets

IconItemUnit or formWhy we need it
Crane typeTop running, under running, gantry or monorailSets the load path and which CMAA document applies
Rated capacityt (short tons)Main and auxiliary hoist
Service classCMAA A to FFatigue cycles and deflection limits
Crane spanm (ft), rail to railFixes column lines and runway spacing
Hook height or top of railm (ft)Sets frame height and the column step
Wheel loads and spacingkN (kips) per wheel, mm (in) spacingThe real loads, from the crane maker
Bridge and trolley weightkg (lb)Lateral force, seismic mass and the minimum wheel load
Cranes per bayNumber and how they work togetherTwo cranes change the governing case
OperationPendant, cab or radioImpact factor and frame drift limit
Bumper forcekN (kips)Sizes the end stops
Rail sectionASCE or bar railClips, pad and girder top flange
Clearance drawingFrom the crane makerRoof and column clearances

Who does what

We design and fabricate the crane building steel, and can supply the crane with it.

World Steel supplies the steel structure: design, fabrication, coating and shipping, plus the overhead crane on request. It does not erect and does not stamp drawings. This is how a crane building splits on a US job.

  • World Steel

    • Designs the building, runway girders, crane columns, brackets, stops and bracing to the crane data
    • Supplies the overhead crane with the steel on request, so runway and crane are set in one design
    • Writes the Design Report with crane load cases, fatigue, deflection and drift checks
    • Fabricates and coats the steel in its IAS AC472-accredited plant in Vietnam
    • Ships with piece marks, rail clip and stop details on the drawings
  • The crane

    • Supplied by World Steel with the steel on request, or by your own crane supplier
    • Designed and rated to CMAA 70 or 74, with wheel loads, bumper force and clearance drawing
    • Installed, commissioned and load tested on site by the installing contractor
  • US contractor, our customer

    • Engineer of Record reviews and approves the design and handles the professional stamp
    • Designs foundations from our base reactions and files the permit
    • Erects the steel, surveys and aligns the rail
    • Owner runs the OSHA 1910.179 inspection program once the crane is in use

Questions from US contractors and plant owners

Questions about crane building design

What US standards apply to an overhead crane building?

The crane itself is designed to CMAA 70 (multiple girder cranes) or CMAA 74 (single girder cranes) and operated under OSHA 1910.179 and ASME B30.2. The building is designed to the IBC, which sends crane loads to ASCE 7; runway girders and crane columns are designed to AISC 360, usually following AISC Design Guide 7; metal buildings also follow the MBMA manual; welds follow AWS D1.1, with its rules for cyclically loaded joints.

What is the difference between CMAA 70 and CMAA 74?

CMAA 70 covers top running bridge and gantry cranes with two or more girders, in service classes A to F. CMAA 74 covers top running and under running single girder cranes with an underhung trolley hoist, in classes A to D. For the building, the document matters less than the data it produces: wheel loads, spacing and service class.

How does the CMAA service class change the building?

The class describes how often and how close to capacity the crane works. It sets the runway deflection limit (L/600 for A to C, L/800 for D, L/1000 for E and F in common practice), the number of stress cycles used for fatigue, and therefore the weld details and inspection on the runway girder.

What crane loads does ASCE 7 require?

Maximum wheel loads, increased by vertical impact (25% for powered monorails and cab- or remote-operated bridge cranes, 10% for pendant-operated bridge cranes, 0% for hand-geared cranes); a lateral force of 20% of the rated capacity plus hoist and trolley weight; and a longitudinal force of 10% of the maximum wheel loads. Lateral and longitudinal forces act at the top of the rail.

What deflection limits do you use for crane runways?

Unless your specification says otherwise, AISC Design Guide 7 and MBMA recommendations: vertical L/600, L/800 or L/1000 by class under wheel loads without impact, lateral L/400, and frame drift at the runway of H/100 for pendant-operated cranes or H/240 (at most 50 mm, 2 in) for cab-operated cranes. The values are agreed on the design basis and printed in the Design Report.

Why does fatigue matter more than strength on some runways?

A runway girder may see millions of wheel passes over the life of a plant. Each pass is a stress cycle, and cracks start at welds long before the steel reaches its strength. AISC 360 Appendix 3 limits the stress range at each detail, so on Class D, E and F cranes fatigue often decides the girder size and the weld types.

What is the largest crane World Steel has designed a building for?

A 150 metric ton (165 short ton) overhead crane, at the Sunpro Steel steel production plant in Can Tho, Vietnam, completed in 2024 with about 5,000 t of World Steel structural steel. Its heavy runways sit on laced crane columns.

When is a laced or separate crane column used instead of a bracket?

A bracket on the building column suits light cranes. As capacity and class rise, a stepped column carries the runway on a wider lower shaft, and for heavy cranes a laced column with a separate crane leg keeps the crane load out of the roof column, as at Sunpro Steel. We choose the type by capacity, class, runway height and the drift limit.

What is AIST Technical Report No. 13?

The Guide for the Design and Construction of Mill Buildings, published by the Association for Iron & Steel Technology (latest edition 2021). Steel producers name it in their specifications for buildings that carry heavy, high-cycle production cranes. It sorts mill buildings into classes A to D by the number of load cycles over a 50-year life and then asks for stiffer runways (span/1000 in classes A and B), tighter frame drift at the crane girder (height/400 or 50 mm), higher side thrust for mill cranes and full inspection of runway girder welds. World Steel designs steel mill buildings to it when the owner’s specification calls for it, as for the Sunpro Steel production plant with its 150 t crane.

Can World Steel supply the overhead crane too?

Yes, on request. World Steel can supply the overhead crane with the building steel, designed to CMAA 70 or 74, so the wheel loads, clearances and runway are fixed in one design and one shipment. If you buy the crane from another supplier, we design the runway to that supplier’s data sheet. Installation, commissioning and the load test are site scope.

Do you supply the crane rail and stops?

Runway girders, brackets, columns, stops and conductor bar brackets are part of the steel World Steel designs and fabricates. Rail, clips and pads are agreed in the scope of each project, always to the crane maker’s rail section; the drawings show their layout either way.

Who is responsible for OSHA 1910.179 compliance?

The employer who operates the crane: inspections, rated load marking, operator rules and load testing. The building design supports it with clearances, stops, access for inspection and supports for the conductor bar, all shown on the drawings.

How do crane loads reach the foundation?

Each crane column passes down the wheel loads, the lateral thrust and the braking force, on top of the roof, wind and seismic loads. The Design Report gives the base reactions for every crane position and load case, and the anchor rod layout comes with the approval drawings, so your foundation engineer designs footings that do not settle unevenly under the runway.

What happens to the crane in seismic design?

The bridge and trolley self-weight is included in the seismic mass, at the parked position stated on the design basis, and the runway, brackets and stops are checked for the resulting forces. Crane-building frames in high seismic zones follow AISC 341 where the seismic system requires it.

Who approves the crane building design for the permit?

The Engineer of Record of the US contractor, our customer. World Steel designs and fabricates and provides calculations and drawings ready for their review; the Engineer of Record approves them and handles the professional stamp for the permit.

Planning a factory with overhead cranes?

Send the crane maker’s data sheet, the building size and the site location. We design the runway, crane columns and frame as one system, up to the 150 t class we built for Sunpro Steel.