For a US contractor, a moment connection decides much more than the strength of a joint. It decides how many field welders the erector needs, how much ultrasonic testing goes on the deck, how long each beam hangs on the crane, how large the pieces are on the truck and how the slab is detailed at each column. The Engineer of Record makes the choice, but contractors and fabricators who understand the options can bring alternatives to preconstruction that save weeks. This guide to choosing a moment connection compares the seven non-proprietary connections in AISC 358-22.
The options side by side
Limits for rolled beams in special moment frames, from Section 5.3 and the matching Section 6.3, 7.3, 8.3, 9.3, 13.3 and 14.3 of each chapter:
| Connection | Max beam | Max weight | Max flange | Min clear span / depth (SMF / IMF) | Field joint |
|---|---|---|---|---|---|
| RBS, Ch. 5 | W1100 (W44) | 610 kg/m | 53 mm | 7 / 5 | welded |
| WUF-W, Ch. 8 | W920 (W36) | 220 kg/m | 25 mm | 7 / 5 | welded |
| End plate 4E / 4ES, Ch. 6 | 600 mm deep | no limit | 19 mm | 7 / 5 | bolted |
| End plate 8ES, Ch. 6 | 910 mm deep | no limit | 25 mm | 7 / 5 | bolted |
| BFP, Ch. 7 | W920 (W36) | 220 kg/m | 25 mm | 9 / 7 | bolted |
| CBB, Ch. 9 | W840 (W33) | 190 kg/m | 25 mm | 9 / 9 | bolted |
| Double-tee, Ch. 13 | W610 (W24) | 82 kg/m | 16 mm | 9 / 9 | bolted |
| Slotted web, Ch. 14 | W920 (W36) | 600 kg/m | 56 mm | 6.4, SMF only | welded |
Column limits add another filter. The RBS takes rolled columns to W1000 (W40); most others stop at W920 (W36). The BFP, CBB and double-tee drop to W360 (W14) columns when there is no structural slab. Box columns appear in the RBS, WUF-W, BFP, CBB and slotted web chapters, within 600 mm (24 in.), or 400 mm for the CBB; end plates and double-tees list only I-shaped and cruciform columns.
Six questions that narrow the choice
How big are the beams?
Long spans and heavy floors push toward the RBS or slotted web. Moderate beams to W920 (W36) open the WUF-W and BFP. Beams to 910 mm deep suit the 8ES end plate. Light beams to W610 (W24) suit the double-tee.
How short are the bays?
The span-to-depth minimums matter in tight plans. The welded connections and end plates need 7 beam depths in SMF; the BFP, CBB and double-tee need 9. A 9 m (30 ft) bay with a W760 (W30) girder has a clear span ratio of about 11, which suits all of them; a 6 m (20 ft) bay with the same girder does not suit the bolted plate types.
Is there a composite slab?
The RBS, WUF-W and slotted web are exempt from slab isolation. End plates with a slab need beams at least 600 mm (24 in.) deep, no studs within 1.5 beam depths of the column and an isolated slab. The BFP, CBB and double-tee in SMF need the slab isolated. Each isolation detail is a gap, a filler and an inspection item at every frame column.
Who welds on site, and who inspects?
Field CJP welding of moment connections needs welders qualified to the project WPS, preheat, weather protection, backing removal at the bottom flange and ultrasonic testing of every demand-critical weld by the special inspector. In markets where certified field welders are scarce or the season is wet and cold, such as coastal Washington, Oregon and Alaska, the bolted connections often win on schedule, even if their steel weight is higher.
Are there frames in two directions at one column?
Biaxial frames suit box or cruciform columns, which the RBS, WUF-W and BFP accept, or proprietary systems built for that case, described in the proprietary connections article.
What does the column side cost?
The WUF-W, with Cpr = 1.4 and the hinge at the face, sends the largest moment into the column, which may grow columns, continuity plates and doublers. The RBS sends the least for a given beam. On frames where strong-column weak-beam or the panel zone governs, that can decide the choice.
Shop work versus site work
Choosing a connection also chooses where the quality-critical work happens.
- Welded connections (RBS, WUF-W, slotted web): the shop prepares beam ends, access holes, cuts or slots, and welds column continuity plates, doublers and shear tabs. The flange and web CJP welds are field welds, unless the frame uses column trees, with beam stubs shop welded and spliced outside the protected zone, which moves them into the shop at the cost of larger pieces.
- Bolted connections (end plate, BFP, double-tee, CBB): the demand-critical welds, end plate to beam or flange plate to column, are made in the shop, flat, and tested there. The site bolts and pretensions.
For a contractor buying from an overseas fabricator, bolted connections and column trees put more of the connection under the shop's quality system, the plant's QC and the owner's QA at the plant, before anything ships.
Shipping and handling
A moment-frame column with flange plates or column-tree stubs is wider and heavier than a bare column. Container and breakbulk limits, truck permits and site crane picks all depend on piece size. On a large package, these logistics are worth settling when the connection is chosen, not after the shop drawings are drawn. Our shipping team sizes pieces for the voyage and the last mile with the US contractor.
Bringing alternatives to the Engineer of Record
When we price a seismic moment frame package, our engineers check each frame line against the specified connection and, where it helps the project, propose an alternative for the Engineer of Record to consider: an 8ES end plate in place of a field-welded WUF-W on a remote site, an RBS in place of a WUF-W where the column side governs, or column trees where field welding is costly. The design, the choice and any seal stay with the US engineer; our proposals come with calculations and drawings for review, in the format of the sample Design Report we publish.
Our track record behind the choice
Whichever connection the Engineer of Record selects, the work rests on the same shop record. We have fabricated packages of 5,000 t for the Sunpro Steel mill, 2,500 t for CPV Food and 2,000 t each for the Long Son petrochemical complex and the M&D Warehouse in Thailand, and multi-storey frames such as the 1,500 t first phase of the Tongwei Tien Giang feed factory. Repeat customers such as Haid Group come back to us for their next plant.
For seismic connections, that record is backed by IAS AC472 accreditation since 2019, with two audits a year, AWS D1.8 qualified procedures and welders, materials tested at ILAC-accredited labs or the lab the customer names, and inspection items agreed with the customer in a project inspection and test plan.
A quick rule of thumb
As a first pass, before the Engineer of Record runs the numbers: long spans and heavy girders point to the RBS; moderate spans with drift control point to the WUF-W; low-rise frames with no appetite for field welding point to end plates; field-bolted frames with erection tolerance point to the BFP; light beams on short bays point to the double-tee. Every first pass still ends with the limit check of the chosen chapter, and with a conversation between the Engineer of Record, the erector and the fabricator about where the welding will happen.
What World Steel brings to any of these
All seven connections are built from the same shop capabilities: accurate cutting of thick plate on CNC laser machines up to 100 mm, drilled holes where the chapter requires them, demand-critical shop welds to our AWS D1.8 procedures, ultrasonic testing, and Tekla shop drawings that show every limit and protected zone, included at no extra cost. Our Vietnam plant is the first and only fabricator in Vietnam accredited under IAS AC472, audited twice a year since 2019, with a capacity of 2,500 t per month for large projects and multi-storey frames such as the FPI Barracks in Guam, a US territory where seismic design governs. Customers follow their order in real time in PEB Studio.
Erection is the US contractor's scope, and the Engineer of Record's design governs. For the seismic provisions read the AISC 341 landing and the AISC 341 and AISC 358 page.
Quick answers
Which moment connection is most common in US seismic frames?
The reduced beam section is the most widely used special moment frame connection in US practice, followed by the WUF-W, extended end plates and bolted flange plates. Proprietary systems are common in some markets.
Which AISC 358 connections avoid field welding?
The extended end plate, bolted flange plate, double-tee and cast bolted bracket are field bolted at the moment connection. The RBS, WUF-W and slotted web normally need field CJP welds unless the frame uses column trees.
Which connection takes the largest beams?
Under AISC 358-22, the reduced beam section: rolled beams up to W1100 (W44) and 610 kg/m (408 lb/ft), with columns up to W1000 (W40).
Who chooses the connection?
The Engineer of Record, in the design. The steel supplier and the US contractor can propose alternatives during preconstruction, such as a bolted connection to reduce field welding, for the Engineer of Record to accept.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Contractor partnershipLong-term supply for US contractors
- Solutions by stateState-by-state steel solutions
- Send your drawingsGet a steel package quote from your drawings