Power generation · renewables · utilities

Energy, power and utilities: heavy halls, equipment steel and owner rules

Power and utility projects mix heavy crane-served halls with dozens of smaller equipment structures, shelters and platforms. Like oil and gas, they are built to owner specifications, and like heavy industry, they are designed around the equipment inside.

Typical scope
Turbine halls, boiler and equipment structures, shelters
Cranes
Maintenance cranes over turbines and generators
Built to
The utility or owner specification, on top of the code
GPPD Energy Factory, structural steel by World Steel World Steel reference GPPD Energy Factory Energy industry · Dong Nai Province, Vietnam · 2020
Energy, power and utilities at a glanceTypical ranges · not design values
Typical spans
24 to 45 m (80 to 150 ft) for turbine and generator halls
Heights
Tall halls and multi-level equipment structures
Structural systems
Crane-served frames, braced equipment structures, shelters and platforms
Loads that size the steel
Crane loads, equipment and piping loads, wind and seismic, owner load cases
Codes and standards
Owner specifications, AISC 360, ASCE 7-22 risk categories, AWS D1.1
Coating and exposure
Outdoor and coastal exposure; galvanizing or high-performance coatings

What makes this project type different

What sizes the steel in energy, power and utilities

Gas turbine and combined-cycle plants, waste-to-energy plants, water and wastewater treatment works and battery storage sites all need structural steel, and they share three traits: maintenance cranes over heavy equipment, many small outdoor structures, and an owner specification that sets material, coating and inspection rules.

Utility work is also often in a higher risk category under ASCE 7-22, because the facility must keep working after a storm or an earthquake. That raises the design loads, and the Engineer of Record sets them. We fabricate, coat and document the steel to match.

Maintenance cranes

Cranes over turbines, generators and pumps set the hall frames and runways.

Risk category

Essential facilities may be Risk Category III or IV, raising wind, snow and seismic loads.

Equipment and piping

Heavy equipment and piping supports bring point loads and operating cases.

Outdoor structures

Shelters, platforms and supports exposed to wind and weather all year.

Corrosion

Outdoor and coastal sites usually call for galvanizing or high-performance coatings.

Owner documentation

Utilities expect complete material, weld and coating records.

Structures and systems

The structures in a typical package, and what we fabricate

Your Engineer of Record chooses the systems. These are the ones we see most often in this type of project, all fabricated in our plant in Vietnam.

Typical structures and systems for Energy, power and utilities
StructureTypical systemWhat we fabricate
Turbine and generator hallsCrane-served rigid or braced framesColumns, runway girders, rafters or trusses
Equipment structuresBraced multi-level framesColumns, beams, bracing, grating supports
Shelters and enclosuresLight frames over equipmentFrames, roof and wall steel
Platforms and accessPlatforms, stairs, ladders and railsAccess steel, galvanized or coated
Workshops and storesClear-span maintenance buildingsFrames, purlins and girts

Our advice before you bid

Decisions that save steel, time and rework

  • Confirm the risk category first

    It changes every design load. Your Engineer of Record sets it from ASCE 7-22 and the owner’s requirements.

  • Galvanize what lives outdoors

    Small outdoor structures are cheaper to galvanize once than to maintain for decades.

  • Treat the crane as equipment

    Get crane data from the supplier, as for any heavy industrial hall.

  • Agree the record format

    Utilities often have their own document control. Set it up before the first shipment.

  • Pack by structure

    Many small structures ship best as kits, one bundle per structure, labeled for the site.

World Steel projects of this type

Built by World Steel, from our own plant

Steel designed, fabricated and supplied by World Steel. Photos are from our project archive and open full size.

Energy industry · Dong Nai Province, Vietnam · 2020

GPPD Energy Factory

Steel structure designed, fabricated and supplied by World Steel. Tonnage not published.

Real photos

From our plant in Vietnam

World Steel’s own shop floors and jobs, where the steel for US projects is made: 2,500 metric tons of structural steel a month. Not stock images.

Inside our factory
Crew assembling a large steel truss on the shop floor Photo
A large truss being put together in the Vietnam fabrication hall.
Steel bundles stacked high on a packing frame awaiting loading Photo
A packing frame in the Vietnam plant stacked with bundles before they are loaded out.

How World Steel supports this

Designed to US codes, made in our plant in Vietnam

Galvanized or coated

Hot-dip galvanizing and high-performance coatings from Vietnam.

Structures as kits

One labeled bundle per structure for sites with many small structures.

Complete records

Mill certificates, weld and coating records in the owner’s format.

The structural steel ecosystem

Products and solutions behind this guide

The products we make for this part of a seismic structure, the services that come with them and past World Steel projects, all one click away.

The industry behind this guide

World Steel projects of this type

Past World Steel work, shown for the structure type. It does not describe the seismic criteria of any one project.

Standards on this page

Read the standard behind it

Each standard page explains what it covers, the edition we reference and how we apply it. We design and fabricate to these standards; they are not certifications.

Keep reading

Related solutions

Questions from US contractors

Energy, power and utilities: questions we hear

What energy structures do you fabricate?

Turbine and generator halls, equipment structures, shelters, platforms, access steel and maintenance buildings. We confirm the structures in our scope for each job.

Can you meet a utility’s specification?

Send it with the bid. We confirm each requirement or tell you before award where an alternative must be approved.

Do you supply transmission towers?

No. Our work is building and equipment structural steel, not transmission or telecom towers.

Is galvanizing available?

Yes. Hot-dip galvanizing and duplex systems are available for outdoor and coastal structures.

Are shop drawings included?

Yes. Shop drawings come with every project at no extra charge, from one Tekla Structures model of the whole job. Your Engineer of Record reviews and approves the structural drawings.

Does World Steel erect the steel?

No. World Steel designs, fabricates and supplies the steel structure. Erection, the PE seal, the permit and site work are the scope of the US contractor, our customer.

A plain-English guide for US contractors, not engineering advice for a specific site. Ranges are typical, the adopted codes govern, and your Engineer of Record sets the design criteria for each project.

Bidding energy, power and utilities?

Send the drawings, the specification and the schedule. Our estimators take off the tonnage, confirm the production slot we can hold for it and return a written scope for steel designed to US codes, made in our plant in Vietnam and shipped to your US port by erection sequence.