Decisions by phase
What to settle, and when
-
Concept and schematic
Construction type, rated elements, restrained or unrestrained status, and whether a performance-based study under AISC 360 Appendix 4 is worth it.
-
Design development
Protection system by zone, listed designs, a shortlist of products, and the primer and topcoat that suit them.
-
Steel design
Section sizes checked against coating thickness, so heavier members are used where they save coating and time.
-
Shop drawings
Piece marks carry system, rating, design number and thickness; masked areas and connection details shown.
-
Fabrication
Blasting, priming and, where agreed, shop coating, with readings recorded and tracked by member.
-
Shipping and erection
Protected packing, careful handling, then connection coating and touch-up by the contractor’s applicator.
-
Inspection and handover
Special inspection, firestopping checks, final acceptance and the records the owner keeps for the life of the building.
- Request a quote A napkin sketch, a site plan or a full permit set is enough to get a steel package priced for your US site. Start a quote →
The protection matrix
One line per member type, shared by everyone
An example layout. Values are filled from the listed designs and the manufacturer’s tables for your project.
| Member group | Rating | System | Listed design | Applied |
|---|---|---|---|---|
| Exposed lobby columns | Per Table 601 | Thin-film intumescent | Column design from the listing | Shop, touch-up on site |
| Concealed floor beams | Per Table 601, restrained | SFRM | Floor-ceiling design | On site after decking |
| Atrium roof trusses | Per Table 601 or fire study | Thin-film intumescent | Beam or truss design | Shop, touch-up on site |
| Process area supports | Per owner specification | Epoxy intumescent | UL 1709 listing | Shop, connections on site |
| Roof framing above 6 m (20 ft) | Often none required | Shop primer only | — | Shop |
Where large projects save
Levers that cut cost and time without cutting protection
Right-sized sections
Heavier, compact sections can need much less coating. Compared member by member, the steel and the coating can cost less together.
Shop coating where it pays
Coat repetitive, accessible members in the shop and keep site work to connections.
Fewer systems
Two well-chosen systems are easier to buy, apply and inspect than five.
Ratings where needed
Confirm which members really need protection; roof framing and secondary steel often do not.
Primer decided once
One primer accepted by every fire product on the job avoids stripping and recoating.
Records from the start
Inspection is quicker when the evidence arrives with the steel.
Scale
Capacity for large, fire-rated steel packages
World Steel fabricates about 2,500 metric tons (about 2,750 US tons) of structural steel a month in its own plant in Vietnam, with automatic blasting and a covered paint hall in the same line. For large US contractors, that means fire-rated frames can be fabricated, primed and, where agreed, coated in one controlled flow, in the erection sequence your site needs, and followed member by member in PEB Studio.
Featured reference · Oil and gas · petrochemical
Southern Vietnam Petrochemical Complex, Long Son
A large oil and gas process plant in southern Vietnam, built to an owner’s petrochemical specification. World Steel designed, fabricated and supplied more than 56,000 m² (over 600,000 sq ft) of steel structure for the complex: the kind of job where every member is traceable, every coat is recorded and the inspection file is as important as the steel.
Steel structure design, fabrication and supply by World Steel. Shown as process plant experience; fire protection on any project follows that project’s own specification.
Real photos
From our plant in Vietnam
World Steel’s own shop floors and jobs, where the steel for US projects is made. Not stock images.
How World Steel supports this
Designed to US codes, made in our plant in Vietnam
2,500 t a month
About 2,750 US tons of structural steel a month from our own plant in Vietnam.
Protection matrix in the model
Every piece mark carries its rating, system, design number and thickness.
Built for US contractors
We supply the steel; you run the site, the permit and the inspections.
The fire protection ecosystem
Products and solutions behind this guide
The products we make for this part of a seismic structure, the services that come with them and past World Steel projects, all one click away.
Products made in our plant in Vietnam
Solutions that come with it
World Steel projects: process plants, healthcare, multi-story
Photo
Photo
Past World Steel work, shown for the structure type. It does not describe the seismic criteria of any one project.
Standards on this page
Read the standard behind it
Each standard page explains what it covers, the edition we reference and how we apply it. We design and fabricate to these standards; they are not certifications.
Keep reading
Related solutions
Questions from US buyers
Planning for large projects: questions we hear
When should fire protection be decided on a large project?
Before the steel is sized. Ratings and systems change member sizes, primers and connection details, and late changes mean rework.
Can World Steel help compare shop and site coating?
Yes. We set out the steel, coating and site effects of each route for your team to decide.
Does World Steel apply SFRM or do firestopping?
No. Those are site trades in the US contractor’s scope. We supply steel prepared for them.
Can we track fire protection progress?
Yes. PEB Studio shows blasting, coating and QC release for each member in real time.
Are shop drawings included for fire-rated steel?
Yes. Shop drawings come with every project at no extra charge, with the rating, protection system and listed design shown for each rated member. Your Engineer of Record reviews and approves the structural drawings.
A plain-English summary for US buyers, not the code text and not engineering advice for a specific site. The adopted codes and standards govern, and your Engineer of Record confirms the criteria for each project.
Planning fire-rated structural steel?
Send the drawings, the specification and the fire protection schedule. We confirm the listed systems and primer with your team and return a written scope for steel designed to US codes, made in our plant in Vietnam and prepared, or coated, for its fire protection.