Where it sits in the US code stack
Where it governs in your building
A metal building system, part by part
Every part of the system, and who supplies it
MBMA practice names the parts of a metal building and the usual split of supply. Here is how that split looks on a World Steel job, where we design, fabricate and supply the steel and the US contractor builds it.
Designed, fabricated and supplied by World Steel5
Primary frames
Tapered or prismatic built-up columns and rafters, the main frames that carry everything to the foundations.
Secondary framing
Z purlins, C and Z girts, eave struts and base angles that carry the cladding back to the frames.
Bracing
Rod, cable or angle X-bracing, portal frames and flange braces that keep the building stable.
Roof and wall panels, trim
Profiled or standing-seam panels, flashings, gutters and downspouts to the panel layout.
Framed openings
Jambs and headers for doors, windows and louvers shown on the approved drawings.
Shared1
Anchor rods
Size and layout on our anchor rod plan; supply and setting in the concrete by others unless listed in our scope.
By the US contractor and others2
Foundations
Designed by your foundation engineer from the column reactions we provide, built by your contractor.
Erection
Unloading, sorting, erecting and bolting by the US contractor, our customer, using our erection drawings.
14 answers from our engineers
MBMA questions and answers
What US buyers, architects and erectors ask about metal building practice: collateral load, serviceability, crane loads, scope splits and how our drawings compare with a US supplier's.
The Manual and the code 3 answers
Is the MBMA Manual a code?
No. It is an industry reference that works inside the adopted code. Building officials and Engineers of Record use it because it explains how metal buildings meet the code.
Is World Steel an MBMA member?
No membership is claimed. We follow the practice the Manual sets out as a design and scope reference, so that our drawings and scope read the way US reviewers and erectors expect.
Does following MBMA practice change the loads?
No. Loads come from ASCE 7 through the IBC. The Manual explains how to apply them to metal buildings, for example how to treat collateral load or wind on open-sided structures, without changing the code minimums.
Loads and serviceability 4 answers
What is collateral load?
The weight of permanent items hung from or resting on the roof structure that are not part of the building itself, such as sprinklers, lights, ducts and ceilings. We state the allowance on the drawings so your MEP team can check it.
How much collateral load should we allow?
It depends on what will hang from the roof. A plain warehouse with sprinklers and lights needs far less than a food plant with process piping or a data hall with cable trays. List the services and we suggest an allowance for your Engineer of Record to confirm.
What serviceability limits do metal buildings use?
Frame drift and purlin deflection limits chosen to suit the cladding, doors, ceilings and any crane. The Manual and AISC Design Guide 3 offer guidance; the limits used are written on our drawings.
How are crane loads applied to a metal building?
Wheel loads, vertical impact and lateral and longitudinal forces are applied as the Manual and AISC Design Guide 7 describe, using the crane maker's data. Runway deflection and drift at crane level get their own checks.
Scope and supply 4 answers
Who supplies the anchor rods?
We size them and show them on the anchor rod plan. Supply and setting is by others unless the anchor rods are listed in our scope. Either way, the rods must be set to the plan before the steel arrives.
Who designs the foundations for a metal building?
Your foundation engineer, from the column reactions we provide for every load case. The Manual treats foundation design as outside the metal building supplier's scope, and so do we.
What if another trade needs to hang something not on our drawings?
Tell us before approval and we design for it. Anything added after the drawings are approved, such as a heavy unit on purlins or a new opening, needs an engineering check before it is installed.
Does World Steel erect the building or provide a crew?
No. World Steel designs, fabricates and supplies the steel; erection is by the US contractor, our customer, working from our erection drawings and piece-mark labels.
Drawings and documents 3 answers
Will your drawings look like a US supplier's?
Yes. Anchor rod plans, frame cross-sections, roof and wall framing, bracing and sheeting layouts follow the conventions US erectors and reviewers are used to, in US units next to metric.
What is a letter of design certification?
A document some jurisdictions ask a metal building manufacturer to provide, stating the design loads and codes used. We provide the design criteria and calculations; any seal or certification statement by a registered engineer comes from the US contractor's Engineer of Record.
Do we get erection drawings?
Yes. Every project includes erection drawings showing each piece mark, bolt group and bracing location, plus shop drawings at no extra charge.
More answers on every US code we design to: search all standards questions.
Why it matters
A building code tells you the loads, MBMA practice tells you how a metal building carries them
The IBC and ASCE 7 were written for every kind of building. A pre-engineered metal building has its own habits: tapered frames, lapped Z purlins, rod bracing, thin cladding that also braces the purlins. The Manual turns the code loads into the load cases and combinations a metal building designer actually checks, and adds guidance where the code is silent.
It also writes down common industry practice: what a metal building supplier normally includes, what the buyer or another trade provides, and how responsibilities are split between the supplier's engineer and the Engineer of Record. Reading a quote against those conventions is the fastest way to find a scope gap.
Where you see it
MBMA practice in a World Steel building
Collateral load
A stated allowance for sprinklers, lights, ducts and ceilings hung from the roof, separate from live load, so the frame is not quietly undersized for services.
Serviceability
Frame drift and purlin deflection set to suit the cladding, doors and any crane, not just strength. Limits are written on the drawings.
Crane loads
Wheel loads, impact and lateral thrust applied as the Manual describes, with runway design following AISC Design Guide 7.
Who supplies what
Anchor rods, foundations, erection, field-cut openings and other trades are listed in or out of our scope, item by item.
Read your quote this way
Scope items US buyers should see spelled out
| Item | Usually by the metal building supplier | Usually by others |
|---|---|---|
| Frame, purlins, girts, bracing | Designed, fabricated and supplied | Erection |
| Anchor rods | Size and layout on the anchor rod plan | Supply and setting, unless listed in our scope |
| Foundations | Column reactions for the foundation designer | Foundation design and construction |
| Roof and wall panels, trim | Supplied to the panel layout | Installation |
| Field-cut openings and other trades' supports | Framed openings shown on the drawings | Anything added after the drawings are approved |
Who does what in a metal building order
The manual's conventions, applied to a World Steel order
The MBMA manual describes how a metal building order is usually split between the manufacturer, the builder and the design team. We follow those conventions, and say where a job differs.
World Steel, the manufacturer
- Designs the building system to the loads in the order documents
- Fabricates and supplies the frames, secondary members and the items in our scope
- Issues the design report, the approval drawings and the erection drawings
US contractor, our customer
- Sets the order documents: loads, codes, scope and the items supplied by others
- Erects the building with the erection drawings
- Coordinates the foundation, the doors and the trades around the steel
Engineer of Record
- Confirms the design loads and the serviceability limits
- Reviews and approves the system design
- Designs the foundation to our reactions
Order and review comments
Four questions the manual's conventions settle on paper
Most disputes on a metal building come from scope or serviceability left unwritten. These are written into our proposal.
-
“What deflection and drift limits were used?”
MBMA manual, serviceabilityWhat our package showsThe limits agreed for roof, walls and frames are listed in the design criteria, apart from the strength checks.
-
“Who supplies the anchor rods and the doors?”
MBMA manual, scope conventionsWhat our package showsA scope table in the proposal lists every item as ours or supplied by others.
-
“How was the collateral load set?”
MBMA manual with ASCE 7What our package showsThe collateral load comes from your order documents and is shown on the criteria sheet.
-
“Are the order documents and the design in agreement?”
MBMA manual, order documentsWhat our package showsThe design report quotes the loads and codes from the order, and any change is confirmed in writing.
Go deeper
Four pages on the system the manual describes
From the frames to the purlins, the system has its own pages.
Pre-engineered metal buildings
The building system we design and supply.
Pre-engineered metal buildings →Tapered frames
Main frames shaped to their bending.
Tapered frames →Cold-formed design
Purlins and girts to AISI S100.
AISI S100 →Design report
What the system design package shows.
How the design report reads →
Real photos from World Steel
Metal building systems from frame to finished roof
Photographed in our own plant in Tay Ninh Province, Vietnam, and on World Steel jobs. Not stock images.
MBMA never works alone
The standards and guides it works with
Each link opens the full page, with its own questions and answers.
Honest status
World Steel follows MBMA practice as a design and scope reference. No MBMA membership or certification is claimed. If your Engineer of Record sets a different basis, we design to that.
Who does what
World Steel designs, fabricates and supplies the steel structure from its own plant in Vietnam. The US contractor, our customer, erects it, has the drawings approved and sealed by their Engineer of Record and pulls the permit.
Details confirmed in quote Edition: Current edition, as your specification names
Source record: https://www.mbma.com/
Last checked: —. Editions change on a cycle, so your Engineer of Record confirms which one your jurisdiction enforces.
All US codes & standardsComparing metal building quotes?
Send the quotes or your scope sheet. We line our supply up item by item against common MBMA practice, so you can see exactly what is in and what is by others.