Multi-bridge programs

Eighteen footbridges, four spans, one design family

For a program in Guyana we designed and fabricated eighteen enclosed steel footbridges, built in pairs beside existing road bridges over rivers and creeks. Four span lengths covered every crossing, so the details repeated and the shop ran the job like production work. A US parks, campus or development program with many crossings can run the same way.

ROAD
ROAD
ROAD
ROAD
ROAD
ROAD
ROAD
ROAD
ROAD

Diagram · 18 footbridges, a pair at each crossing

The Guyana program, 2026

What eighteen footbridges came down to

18 footbridges

Nine crossings, a footbridge on each side of the road bridge

4.3 kN/m² crowd load

About 90 psf on the walkway, as the design notes set it

Built-up chords

A572 Grade 50 or equal, double-sided welds on built-up sections

Grade 8.8 bolts

Bolted field splices drilled from templates in our plant

3D design model of a pair of steel box-truss pedestrian bridges over a river in Guyana
3D design model of two steel truss footbridges on steel columns beside a road bridge in Guyana

3D design models from our proposal drawings. Not photographs.

Span family, drawn to scale

Four lengths covered every crossing

26 m (85 ft)

The shortest crossings and the typical design shown in the proposal set.

33 m (108 ft)

Mid-length creeks, same chords and splices, one more panel.

40.25 m (132 ft)

Wider rivers, deeper members on the same detail family.

47.5 m (156 ft)

The longest crossings, with a top main beam and strut layout.

Repeat, do not redraw

Six details drawn once and built eighteen times

One splice family

Chord splices drawn once and reused, so templates and drill programs repeat from bridge to bridge.

Common gussets

Gusset and connection plates nested on the CNC table in batches for several bridges at once.

Shared floor beams

Floor beams and cleats sized for the deck width every bridge shares.

One deck detail

Checker-plate deck panels and handrails detailed once and repeated along every span.

Same camber rule

Long members carry the same pre-camber rule, span/500, set in the general notes.

One coating system

The same blast and coating specification for all eighteen bridges, measured member by member.

Eighteen bridges, no mix-ups

Every plate knows which bridge it belongs to

Cut

Plates and strips carry the job number from the moment they are cut.

Marked

Each piece gets its bridge and piece mark in paint and on a tag.

Tracked

PEB Studio records which bridge, which bundle and which container.

Packed

Each crossing ships as its own set with its bolts and plates.

On our shop floor

The program in production

Flange strips cut from plate laid out on the shop floor
Operator checking cut parts on the CNC cutting table
Bridge member on the welding line roller conveyor
Plate girders with splice holes while welders work further down the shop
Fitters at a stiffened girder while the crane lifts a drilled splice box
Bridge member set in a fit-up jig with a drilled gusset plate
Fitter drilling bolt holes in welded bridge girders in the World Steel plant
Welder grinding a bridge member with a shower of sparks in the World Steel shop

Questions

Bridge programs: common questions

How many footbridges did you fabricate for Guyana?

Eighteen enclosed steel box-truss footbridges, built in pairs beside existing road bridges at river and creek crossings, with spans of 26, 33, 40.25 and 47.5 m (85 to 156 ft).

Why use one design family for many bridges?

Repeated details mean templates, jigs and CNC programs are reused. Fabrication becomes faster and more consistent, and your engineer reviews one detail family instead of eighteen different bridges.

Can bridges ship one crossing at a time?

Yes. Each crossing can ship as a complete set with its bolts and plates, in the order your crews plan to build them.

Do you erect the bridges?

No. World Steel designs, fabricates and ships the steel. Erection, foundations and the lift are the scope of the contractor, our customer.

Can erection drawings be in another language?

Yes. For the Guyana program the erection drawings were issued in English and in Chinese for the erection crew. Tell us what your crew needs.

Planning a program of crossings?

Send the list of crossings with spans and widths. We propose a design family, the steel weight per bridge and a shipping order crossing by crossing.