Capacity design is the idea behind every seismic steel frame: decide where the steel will yield, then make everything around that point strong enough to carry the force the yielding part can deliver. In a moment frame the yielding part is the beam, near the column. Section 2.4 of AISC 358-22 turns that idea into numbers that every connection chapter reuses: the probable maximum moment at the hinge, the shear at the hinge, and the moment at the face of the column. Get these right and the welds, bolts, plates, panel zone and column are sized for the real demand, not for an analysis force that the earthquake will exceed.
Two resistance factors
Section 2.4.1 starts with resistance factors. Where a strength is computed with AISC 360, its own factors apply. Where AISC 358 gives the equation, it uses two:
- ϕd = 1.00 for ductile limit states, such as flexural yielding of the beam;
- ϕn = 0.90 for nonductile limit states, such as bolt rupture or weld fracture.
The split is deliberate. A ductile limit state that is slightly exceeded gives warning and keeps strength; a brittle one does not, so it keeps a margin.
Where the hinge forms
Section 2.4.2 leaves the plastic hinge location, Sh, to each chapter, measured from the face of the column. The values tell you how each connection works:
- Reduced beam section: at the center of the cut, a + b/2 from the column face.
- WUF-W: at the face of the column, Sh = 0.
- Unstiffened end plate (4E): the lesser of half the beam depth or three flange widths.
- Stiffened end plates (4ES, 8ES): the stiffener length plus the end plate thickness.
- Bolted flange plate and double-tee: near the bolt farthest from the column, as each chapter defines.
Moving the hinge away from the face lowers the moment the column-face welds see, which is the reason the RBS and flange plate connections exist.
The probable maximum moment, Mpr
Section 2.4.3 defines Mpr = Cpr Ry Fy Ze. Each term has a job.
- Fy is the specified minimum yield stress of the yielding element.
- Ry raises it to the expected yield stress, because real steel is usually stronger than its minimum grade. AISC 341 Table A3.2 sets Ry; for ASTM A992 shapes it is 1.1. Our materials and expected strength article in the AISC 341 series explains why.
- Ze is the effective plastic section modulus at the hinge: the gross Zb for most connections, the reduced ZRBS at the center of a reduced beam section.
- Cpr covers peak strength, including strain hardening and local restraint. Unless a chapter says otherwise, Cpr = (Fy + Fu) / 2Fy, capped at 1.2. For A992 steel with Fy = 345 MPa (50 ksi) and Fu = 450 MPa (65 ksi) that gives 1.15. The WUF-W chapter sets Cpr = 1.4, based on test data showing a high degree of strain hardening.
The shear at the hinge, Vh
Section 2.4.4 takes a free body of the beam between the two hinges. With moment Mpr at each end and gravity on the span, the shear at the hinge is Vh = 2Mpr / Lh + Vgravity, where Lh is the distance between hinges. The two terms are taken with the same sign, so Vh is the larger of the two end shears.
The gravity load is the ASCE 7-22 seismic combination 1.2D + f1L + 0.15S, with f1 the code live load factor but not less than 0.5. A user note adds that under the International Building Code a factor of 0.7 replaces 0.15 for snow where the roof does not shed it, which matters in Alaska, the northern Rockies and high-elevation Utah and Nevada. If only one end of the beam has a moment connection, the free body runs from that hinge to the far support instead.
The moment at the column face, Mf
Section 2.4.5 carries the moment back to the column: Mf = Mpr + Vh Sh. The gravity load between the hinge and the face is usually negligible and may be left out, or included if the designer prefers. Mf is the moment the flange welds, end plate, bolts or flange plates must resist, and the moment that drives the continuity plate and panel zone checks.
A worked illustration
Take an illustrative A992 beam with Ze of 5,000 cm³ (305 in³) in a reduced beam section. Mpr = 1.15 × 1.1 × 345 MPa × 5,000 cm³ ≈ 2,180 kN·m. With 8.0 m between hinges and 100 kN of gravity shear, Vh ≈ 2 × 2,180 / 8.0 + 100 ≈ 645 kN. With the hinge 0.60 m from the face, Mf ≈ 2,180 + 645 × 0.60 ≈ 2,570 kN·m. The RBS chapter then checks that Mf does not exceed ϕd times the expected plastic moment of the full beam. These figures only show the chain; the Engineer of Record's calculation governs every project.
Beam shear, continuity plates, panel zones and moment ratio
Sections 2.5 to 2.8 finish the chain.
- Section 2.5 sets the required beam shear: Vh plus the gravity shear between the hinge and the column face.
- Section 2.6 sends continuity plates to AISC 341 unless the chapter says otherwise. The end-plate chapter has its own procedure, and Chapter 3 sets the corner clips. Our D1.8 article on continuity plate and doubler welding covers the shop side.
- Section 2.7 sends panel zones to AISC 341, using the face moment from both beams.
- Section 2.8 sends the column-beam moment ratio, strong column weak beam, to AISC 341, projected from Mpr and Vh. The special moment frame article explains the ratio.
The protected zone
Section 2.9 defines a default protected zone from the face of the column flange to half a beam depth beyond the hinge, unless the chapter gives its own. Most chapters do: the RBS zone ends at the far end of the cut, the WUF-W zone runs one beam depth from the face, and the bolted flange plate zone includes the plates and one beam depth past the last bolt. AISC 341 then bans welds, shot-in fasteners, holes and attachments there. The protected zones guide shows how we mark them.
Common slips in the chain
Most errors we see in connection review are not in the formulas but in the inputs.
- The wrong Ze. For a reduced beam section, Mpr uses the reduced modulus at the center of the cut, but the face-of-column check compares Mf with the expected plastic moment of the full beam. Mixing the two hides an overstressed weld or a cut that is too shallow.
- The wrong Lh. The distance between hinges is shorter than the column-to-column span by two hinge distances. Using the full span understates Vh, and the error grows as the connection pushes the hinge further from the face.
- One-sided gravity. Vh is the end where the seismic shear and the gravity shear add. Taking the average, or the end where they cancel, undersizes the shear tab and the web weld.
- Grade mismatch. Ry and Cpr depend on the grade actually supplied. If a beam specified as A992 is substituted with a higher-strength grade, the hinge gets stronger and every capacity-designed element behind it must be checked again. That is why grade substitutions on seismic members go back to the Engineer of Record, and why our mill certificates carry the heat number of every moment-frame member.
- Snow on a flat roof. In snow country the 0.15S term may need to be 0.7S under the IBC. On a heavy roof in Anchorage or Park City that difference is not small.
Proof from our plant and projects
Our engineers carry this chain every day, not only on seismic jobs. The same capacity-design logic sizes the welds and bolts of the crane runway girders and heavy frames we fabricated for the 5,000 t Sunpro Steel mill. For seismic work, our sample Design Report shows how loads, combinations and member checks are laid out for an Engineer of Record, and the same format carries a moment connection calculation from Mpr to the column checks.
On the shop side, the result of the calculation becomes the hinge location, the protected zone and the demand-critical welds on our Tekla drawings. Protected zone marking on the steel is available on request, and the owner's inspector can check it at the plant or remotely. The plant is accredited under IAS AC472, audited twice a year since 2019.
Why this chain matters to the shop
Fabricators do not compute Mpr for the Engineer of Record, but every number in the chain becomes a physical item: the hinge location sets where the cut, stiffener or last bolt goes; Mf sets plate thickness, weld size and bolt diameter; the protected zone sets where nothing may be welded or shot. When we build a connection the shop drawings show the hinge location, the protected zone and the demand-critical welds, so the US contractor's reviewer can trace each back to the calculation.
Our engineers work in steel building design to the code editions your jurisdiction adopts and hand calculations to the Engineer of Record for review. The plant in Vietnam is accredited under IAS AC472, with AWS D1.8 qualified procedures and welders for the demand-critical joints. For the seismic provisions behind these steps, read the AISC 341 landing.
Quick answers
What is Mpr in AISC 358?
Mpr is the probable maximum moment at the plastic hinge: Cpr times Ry times Fy times the effective plastic section modulus Ze at the hinge. It estimates the largest moment the yielding beam can develop, including strain hardening.
What is Cpr?
Cpr accounts for peak connection strength. Unless a chapter states otherwise it equals (Fy + Fu) / 2Fy, not more than 1.2. Some chapters set their own value, for example 1.4 for the WUF-W connection.
Which gravity load goes into the hinge shear?
Section 2.4.4 uses 1.2D + f1L + 0.15S on the beam between hinges, where f1 is the code live load factor but at least 0.5. Under the IBC, 0.7S is used where the roof does not shed snow.
Where is the protected zone by default?
Unless the connection chapter defines it differently, Section 2.9 sets the protected zone from the face of the column flange to half a beam depth beyond the plastic hinge.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors