AISC 358-22 replaced the 2016 standard and the two supplements issued in 2018 and 2020. It was developed by the AISC Connection Prequalification Review Panel alongside AISC 360-22 and AISC 341-22, and it is incorporated by reference into the Seismic Provisions. The preface lists what changed. Some changes are headline items, such as a new connection; others are quiet edits that touch every chapter and show up on the shop floor. This article walks through the AISC 358-22 changes in the order a US project meets them. For the seismic provisions themselves, see what changed in AISC 341-22.
A new chapter: DuraFuse Frames
Chapter 15 adds the DuraFuse Frames moment connection. Beams connect to the column through plates, and a bolted fuse plate is proportioned to yield in shear during a severe earthquake while the beam stays essentially elastic. Because the fuse plate is bolted, it can be removed and replaced after the event. The chapter opens with a patent notice: the connection is covered by US and foreign patents, and the holder has stated a willingness to license on reasonable terms. Like the other patented chapters, it is optional. The proprietary connections article explains how such connections are bought, designed and fabricated.
Two connections are no longer proprietary
The preface states that Chapter 9, the cast bolted bracket (CBB), and Chapter 14, the slotted web (SW), were updated because these connections are no longer proprietary. For an Engineer of Record this widens the non-proprietary menu. The CBB uses high-strength cast steel brackets made to Appendix A; the slotted web is a welded connection with slots cut in the beam web beside each flange. Both are covered in the CBB and slotted web article.
Much larger reduced beam sections
The change with the widest effect is in Chapter 5. Section 5.3 now prequalifies the reduced beam section (RBS) for:
- rolled beams up to W1100 (W44) deep, with built-up beams no deeper than the rolled limit;
- beam weight up to 610 kg/m (408 lb/ft);
- beam flange thickness up to 53 mm;
- rolled columns up to W1000 (W40) deep, with built-up box columns and boxed wide-flange columns in orthogonal frames limited to 600 mm (24 in.) wide or deep.
Under the 2016 standard the RBS stopped at W36 beams of 450 kg/m (302 lb/ft) and W36 columns. The old size still matters in one place: the exception that waives supplemental lateral bracing at the reduced section, where a composite slab with welded shear connectors at no more than 300 mm (12 in.) spacing braces the beam, still applies only to beams and columns no larger than W920 (W36) and 450 kg/m (302 lb/ft). Larger RBS beams need supplemental bracing near the cut. The RBS design article covers the full procedure.
For US contractors this matters on long-span, heavily loaded frames: hospitals, laboratories, data halls and transfer levels where a W40 or W44 girder was the natural choice but fell outside prequalification. Many of those members are heavy rolled shapes; others are welded plate girders, which Section 2.3.2 allows when their profile matches a qualifying rolled shape.
End plates: bracing location and bolt equations
Chapter 6, which covers the four-bolt unstiffened (4E), four-bolt stiffened (4ES) and eight-bolt stiffened (8ES) extended end plates, gained guidance on where supplemental lateral bracing goes. Section 6.3.1 places it at the top and bottom flanges between the end of the protected zone and half a beam depth beyond it, with no bracing attached inside the protected zone. The bolt bearing and tearout equations now sum the strength of every bolt location rather than treating bolts as a uniform group, which follows AISC 360-22. See the extended end-plate article.
Changes across every chapter
The preface lists five edits applied to all connections where relevant.
A consistent rule for the slab gap
Section 2.3.4 now states one approach to isolating the concrete slab: where a connection requires it, the column and the connection elements at the face of the column are isolated from the slab so the slab does not restrain the beam's rotation at the joint. Each chapter says whether isolation applies. The RBS, WUF-W and slotted web are exempt. Extended end plates with a structural slab are prequalified only when the beam is at least 600 mm (24 in.) deep, there are no shear connectors within 1.5 beam depths of the column face, and the slab is isolated. The BFP, CBB and double-tee in SMF need the slab isolated. For detailers and the deck installer, that gap is a drawing note, a foam filler and an inspection item.
Column shapes clarified
The chapters now state plainly which column shapes each connection accepts: rolled wide flanges, built-up I-shapes, boxed wide flanges, built-up boxes, flanged cruciforms or HSS, with their depth limits. The built-up and box columns article walks through Section 2.3.
Bolt-hole fabrication
Hole-making rules were updated. Several chapters require holes in beam flanges and connection plates to be drilled, or sub-punched and reamed; one chapter also permits laser, plasma or water-jet holes. The bolt-hole fabrication article lists which process each chapter allows, which matters for a shop that cuts most of its plate on CNC laser machines.
Net-section rupture of the beam flange
Connections that bolt through the beam flange, the BFP, CBB and double-tee, now share a check that the beam's net section at the bolt holes can carry the force the gross beam delivers when it yields: the expected tensile strength times the net plastic modulus must reach the expected yield strength times the gross plastic modulus. In practice it limits bolt-hole diameter for a given beam.
Hole diameters follow AISC 360
Equations that compute bolt-hole diameters were updated to match the current AISC Specification, so the hole sizes used in strength checks match the holes the shop actually makes.
What did not change
Just as important for planning is what stayed the same. The design parameters of Section 2.4 are unchanged in form: the probable maximum moment at the plastic hinge is still the peak-strength factor times the expected yield stress times the plastic modulus at the hinge, with the factor capped at 1.2 unless a chapter states otherwise, and the moment at the column face still adds the hinge shear times the hinge distance. Chapter 3 keeps its familiar welding rules: bottom flange backing removed, backgouged and reinforced with a fillet of at least 8 mm (5/16 in.), top flange backing left in place only with a continuous 8 mm (5/16 in.) fillet to the column, and weld tabs removed to within 3 mm (1/8 in.) of the base metal. Chapter 4 still calls for pretensioned ASTM F3125 bolts installed to the RCSC Specification. The welded connections keep their geometry, and the RBS cut dimensions keep the same ranges. A team that built prequalified connections under the 2016 standard will recognize the shop work; the differences sit in member sizes, slab details, holes and a few added checks.
What the changes mean on a project
For the Engineer of Record, the expanded RBS limits and the open CBB and slotted web chapters give more non-proprietary choices for heavy frames. For the detailer, slab isolation and supplemental bracing locations become drawing items on more connections. For the fabricator, hole processes and net-section checks must be confirmed before plate is cut.
On a World Steel job our engineers check every connection against its chapter of the 2022 edition, mark protected zones, slab isolation and bracing on the Tekla shop drawings, and plan the cutting and drilling route before release. Our plant is accredited under IAS AC472, and welding to the demand-critical rules follows our AWS D1.8 procedures. The US contractor, our customer, approves the drawings; the Engineer of Record's design governs.
Proof from our plant and projects
Keeping up with editions is routine work for us. When AISC 358-22 enlarged the RBS limits, our engineers updated the connection checks in our design templates and Tekla components, so a W1000 (W40) or W1100 (W44) girder now runs through the same limit table as a W610 (W24). When the bolt-hole rules changed, we sorted every moment-connection part in our CNC programs by its required process: drilled or reamed where the chapter says so, laser cut on our machines, which handle steel up to 100 mm thick, only where it is allowed.
Behind that is a plant accredited under IAS AC472 since 2019 and audited twice a year, AWS D1.8 qualified procedures and welders, and material tested at ILAC-accredited labs or the lab the customer names. Heavy plate girders of the kind the new RBS limits invite are everyday work: our welded plate girders went into the 5,000 t Sunpro Steel mill.
Which edition your project uses
AISC 358-22 is referenced through AISC 341-22, which IBC 2024 adopts. Many jurisdictions are still on IBC 2018 or 2021 and the 2016 editions of AISC 341 and 358. California, Washington, Oregon, Utah and other high-seismic states adopt the IBC on their own cycles with state amendments, so confirm the edition in the design basis at the start. Our state and local codes page tracks adoptions, and the AISC 341 landing shows how the seismic standards fit together.
Quick answers
When was AISC 358-22 published?
ANSI/AISC 358-22 is dated August 18, 2022. It supersedes the 2016 edition together with Supplement No. 1 of 2018 and Supplement No. 2 of 2020, and it is used with AISC 341-22 and AISC 360-22.
What is the biggest change in AISC 358-22?
For most projects, the expanded reduced beam section limits: rolled beams up to W1100 (W44), 610 kg/m (408 lb/ft) and 53 mm flanges, with columns up to W1000 (W40), which brings much heavier frames into prequalification.
Is the cast bolted bracket still proprietary?
No. The preface states that the cast bolted bracket (Chapter 9) and slotted web (Chapter 14) chapters were updated because those connections are no longer proprietary.
Which edition applies to my project?
The one referenced by the building code your jurisdiction enforces. IBC 2024 points to AISC 341-22, which incorporates AISC 358-22; jurisdictions still on an earlier IBC use the AISC editions that code references.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors