On a seismic moment frame, the building official, the special inspector and the Engineer of Record all ask the same question in different words: is this connection really the one that was prequalified? AISC 358-22 Section 1.1 makes the stakes clear. A listed connection is prequalified only when it is designed and built to every requirement of its chapter. The way a project proves that is its prequalified connection submittals: the design calculations, the shop drawings and the quality records that together show each joint stays inside the standard. This article sets out what goes into them and who handles each part on a US project with an overseas fabricator.
Start in the design documents
The submittal chain starts before the fabricator is involved. AISC 341 asks the design drawings to identify the seismic force-resisting system, the members and connections that are part of it, the protected zones and the demand-critical welds. Our AISC 341 series article on seismic design drawings lists those items. For a moment frame, the Engineer of Record also names the connection type, either one specific AISC 358 connection or a short list the fabricator may choose from, and states the system, SMF or IMF.
When connection design is delegated, the structural connections page explains the split under the AISC Code of Standard Practice. The delegated designer works to the forces and system named by the Engineer of Record, who reviews the result.
The limit check
The first page of any good connection calculation is a limit check. Every chapter sets prequalification limits in its Section *.3: beam type, depth, weight and flange thickness, the clear span-to-depth ratio, column type and depth, lateral bracing and the protected zone. For a reduced beam section in an SMF, for example, the beam must be no deeper than W1100 (W44), no heavier than 610 kg/m (408 lb/ft), have flanges no thicker than 53 mm and a clear span of at least seven beam depths, with the column no deeper than W1000 (W40).
A table that lists each frame line, each beam and column, and each limit with a pass or fail makes review fast. Any fail means the joint is not prequalified. Section 1.1 then leaves two routes: change the member or connection, or present qualification evidence, usually cyclic tests under AISC 341 Chapter K, to the authority having jurisdiction. Our article on cyclic qualification testing describes that route.
The design steps
Next come the chapter's design steps in order. Every chapter ends with a numbered procedure, and following it step by step lets the reviewer compare like with like: the probable maximum moment at the hinge, the hinge location, the hinge shear, the face moment, then the connection elements and the column-side checks of continuity plates, panel zone and moment ratio. Section 1.3 requires LRFD for the connection, even if the frame was designed by ASD. The probable maximum moment article explains the shared steps.
What the shop drawings must show
Shop drawings turn the design into instructions the shop and the erector can follow. For a prequalified connection they should show, at minimum:
- connection type and chapter, for example "RBS, AISC 358-22 Chapter 5";
- cut or plate geometry: RBS dimensions a, b and c, end plate thickness and stiffener length, flange plate size and shims;
- welds: joint type, demand-critical marking, backing type and removal, reinforcing fillets, weld tab removal and finish, and weld access hole geometry;
- bolts and holes: grade, diameter, hole type and size, hole process where the chapter fixes it, faying surface class and paint mask;
- continuity plates and doublers: thickness, clips and weld type;
- protected zones, drawn on the beam with a note that no attachments, welds or shot-in fasteners are allowed there;
- supplemental lateral bracing points where the chapter requires them, and slab isolation where the connection needs it.
Our shop drawing service produces these in Tekla on every job at no extra cost, and the protected zones guide shows how the zone is marked on the steel itself.
Shop QC records
Sections 3.7 and 4.3 send quality control and assurance for welding and bolting to AISC 341, whose Chapter J and the AWS D1.8 inspection clauses set the tasks. A fabricator's QC record for a moment connection usually includes:
- material certificates for beams, columns and plates, traceable by heat number;
- the WPS and welder qualifications used on each demand-critical weld;
- fit-up, visual and dimensional checks of each connection mark;
- ultrasonic testing of shop CJP welds, and magnetic particle testing where a chapter requires it, such as at RBS notch repairs;
- hole position and process checks, and faying surface inspection before painting;
- records of any repair and its approval.
Our AWS D1.8 series article on seismic weld submittals and records covers the welding side in detail.
QA by the owner's inspector
Quality assurance is the owner's independent check, usually by a special inspection agency hired for the project. For a plant overseas, QA can work in three ways: inspectors visit the plant at agreed hold points, a third-party agency inspects on the owner's behalf, or the inspector reviews records and live video at agreed stages. Inspector visits and remote inspection access are available on request on World Steel jobs, explained on our inspector access page. Site QA of field welds and bolting stays with the special inspector on the jobsite.
Timing the submittal
On a fast-track job the moment frame is often on the critical path, so the order of submittals matters. A practical sequence is: the connection list and limit check first, as soon as frame sizes are stable; then the calculations; then the shop drawings of the frame lines that ship first. Releasing the limit check early lets the Engineer of Record catch a joint that falls outside the standard while there is still time to change a member, rather than after plate has been cut. Shipping time from our plant to a US West Coast port is part of that plan, so we agree the review dates at kickoff.
The handover record
Everything above lands in one place at the end: the Manufacturing Data Record, a bound and digital file of certificates, procedures, inspection reports and as-built notes for each shipment. Our quality records page shows how it is organized by connection mark, so a building official or a future engineer can trace any joint back to its steel and its welder.
Common gaps in a first submittal
Review comments on the first round of moment connection submittals tend to repeat. Knowing them saves a cycle.
- Limits shown for the typical bay only. The short end bay, the deeper girder at the stair and the beam framing into a column web are where limits fail. The check should cover every joint.
- Bracing points missing. Several chapters require supplemental lateral bracing at a set distance from the hinge, outside the protected zone. If it is not on the steel drawings, the deck or framing trade has nowhere to attach it.
- Slab isolation not shown. Where a connection needs the slab isolated from the column, the gap and filler belong on both the steel and the concrete drawings.
- Protected zone conflicts. Shear studs, deck welds, embed plates for façades and hangers for services all want to land on the beam near the column. The submittal should show they stay out of the zone.
- Field and shop welds mixed. Each weld should be marked shop or field, so the inspection plan can assign it to the right inspector and the right place.
- Edition not stated. The calculation should name AISC 358-22 or the edition the jurisdiction enforces, since limits changed between editions.
Proof from our plant and projects
Documentation is something we deliver on every job, not only seismic ones. Shop drawings in Tekla are included at no extra cost; inspection items and rates are agreed with the customer in a project inspection and test plan before fabrication; and the Manufacturing Data Record is assembled as the work proceeds, not at the end. Our sample Design Report, published in full, shows the level of detail an Engineer of Record receives.
Our quality system has been accredited under IAS AC472 since 2019 and is audited twice a year by IAS experts. Material tests are run at ILAC-accredited (ISO/IEC 17025) labs or the lab the customer names, as our testing labs page explains, and customers and inspectors follow progress in real time in PEB Studio. That record is what lets a building official in California or Washington accept a seismic frame fabricated in Vietnam.
Who does what
- Engineer of Record: names the system and connection, reviews the connection design and drawings, and answers RFIs on limits.
- World Steel: designs delegated connections, prepares the limit check and shop drawings, fabricates in our Vietnam plant, accredited under IAS AC472, and assembles the QC record. Our welders and procedures are qualified to AWS D1.8.
- US contractor, our customer: approves the shop drawings, coordinates inspections, erects the frame and handles any seal through the US engineer.
- Special inspector: carries out QA in the shop and on site as the statement of special inspections requires.
For the seismic provisions behind each item, read the AISC 341 landing and our seismic inspection guide.
Quick answers
What should a prequalified connection submittal include?
The connection type and AISC 358 chapter, a check of every prequalification limit, the design steps of the chapter, shop drawings that show welds, bolts, holes, protected zones and bracing points, and the QC and QA records required by AISC 341.
Who reviews the connection submittal?
The Engineer of Record reviews the connection design and drawings for conformance with the design intent; the US contractor coordinates the review and approves the shop drawings for fabrication.
What happens if a member falls outside the limits?
The connection is no longer prequalified for that joint. The Engineer of Record changes the member or connection, or presents qualification test evidence under AISC 341 to the authority having jurisdiction.
Can the owner’s inspector visit the plant in Vietnam?
Yes. Inspector visits and remote inspection access are available on request, and our quality records for each connection mark are collected in the Manufacturing Data Record.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors