Steel parking structures: long-span decks, level after level

A parking garage is a building of repeated bays, open to the weather and driven on every day. In steel it is lighter than precast or cast-in-place concrete, so the foundations are smaller and the frame goes up fast, provided the package is detailed for repetition and protected against salt. We fabricate garage frames at 2,500 metric tons a month from our own plant in Vietnam.

Typical bay
About 18 m (60 ft) clear span, stall to stall
Reference
Omakase Car Park Building D, a multi-story steel garage
Designed to
IBC 406, ASCE 7-22, AISC 360, AISC Design Guide 18
Omakase Car Park Building D, structural steel by World Steel World Steel reference Omakase Car Park Building D Multi-story steel parking structure · Thailand · 2022
Parking structures at a glanceTypical ranges · not design values
Typical spans
About 16 to 19 m (54 to 62 ft) clear span: two stall rows and the drive aisle
Heights
Two to eight levels, floor to floor about 3.0 to 3.4 m (10 to 11 ft)
Structural systems
Long-span composite or non-composite beams, braced or moment frames, ramps
Loads that size the steel
Vehicle live loads, vehicle barrier loads, wind and seismic, vibration of long spans
Codes and standards
IBC Section 406, ASCE 7-22, AISC 360, AISC Design Guide 18, AISC 341 where required
Coating and exposure
Open to weather and de-icing salt: hot-dip galvanizing or a high-performance coating system

The parking module

One clear span, repeated level after level

A plan of the typical US parking module: two rows of stalls and a two-way drive aisle, spanned column to column. Long-span beams carry the deck across it; columns stand only at the stall ends. Typical dimensions for orientation, not design values.

5.5 mStall row · 18 ft
7.3 mTwo-way drive aisle · 24 ft
5.5 mStall row · 18 ft
18.3 mclear span, about 60 ft, columns at the red marks

Vehicle barrier

About 27 kN (6,000 lb) at 460 to 690 mm (18 to 27 in) above the deck, ASCE 7-22

Salt exposure

Galvanized, three-coat or duplex system, chosen for the state and the de-icing practice

Open garage

Often no applied fire protection, within IBC 406 limits confirmed by the building official

Long spans

Walking and vehicle vibration checked by the Engineer of Record

A real Design Report for an elevated parking deck

Read the World Steel Design Report we prepared for an elevated parking deck with a special moment frame: loads, analysis, member and connection checks, 31 pages. Project names are removed; the engineering is real.

What makes this project type different

What sizes the steel in parking structures

Most US parking garages are laid out on a module of about 18 m (60 ft): a row of stalls, a two-way drive aisle and a second row of stalls, spanned without interior columns so drivers can park and turn freely. In steel, long-span beams at close spacing carry the deck, columns sit only at the stall ends, and the same bay repeats hundreds of times. That repetition is what makes a steel garage efficient to detail, fabricate and erect.

An open parking garage is its own occupancy in the IBC. Because it is open to the air, the code often allows it to be built without applied fire protection on the steel, within height and area limits the design team confirms with the building official. In exchange, the frame lives outdoors: rain, freeze-thaw and the de-icing salt that cars carry in all winter. Galvanizing or a high-performance coating system, chosen at the start, decides how long the steel lasts.

The 18 m module

Stall, aisle and stall set a clear span of about 16 to 19 m (54 to 62 ft) that repeats across the garage.

Vehicle barriers

Perimeter barriers and their supports are designed for the ASCE 7 vehicle barrier load, about 27 kN (6,000 lb) at bumper height.

De-icing salt

Chlorides from cars attack steel and deck. Galvanizing or a coating system matched to the exposure is part of the design.

Long-span vibration

Long, light floors are checked for walking vibration and the bounce of moving cars.

Open-deck fire rules

An open garage may need no applied fire protection; an enclosed one does. The design team decides which applies.

Ramps and transfers

Sloped bays, speed ramps and any retail or lobby below need their own framing and transfers.

Structures and systems

The structures in a typical package, and what we fabricate

Your Engineer of Record chooses the systems. These are the ones we see most often in this type of project, all fabricated in our plant in Vietnam.

Typical structures and systems for Parking structures
StructureTypical systemWhat we fabricate
Long-span baysWide-flange or built-up beams at close spacing over the 18 m (60 ft) moduleBeams, girders, shear tabs, camber as specified
ColumnsRolled columns at the stall ends, spliced every two or three levelsColumns, splices, base plates
Lateral systemBraced frames or moment frames, to AISC 341 in seismic regionsBraces, gussets, moment frame members
Ramps and decksSloped framing for ramps, deck support for the slab or precastRamp beams, edge angles, deck bearings
Perimeter and accessVehicle barriers, stair and elevator towers, screensBarrier rails and posts, stair towers, screen framing
Top-deck roof or solar canopyLong-span frames over the top level, as on the Omakase garageCanopy frames, purlins, solar-ready supports

Our advice before you bid

Decisions that save steel, time and rework

  • Choose the corrosion system on day one

    Galvanizing, a three-coat system or a duplex system changes the connection details and the fabrication sequence. It belongs in the specification, not in a later change.

  • Repeat the bay

    One module, one beam size, one connection, repeated: that is where a steel garage saves money. Every special bay adds drawings and cost.

  • Confirm open or enclosed early

    The openness of the facades decides the fire protection. A screen added late can change it.

  • Detail the barriers with the frame

    Barrier posts and rails are cheaper and stronger when they are planned into the edge beams, not added on site.

  • Ask for the deck interface

    Cast-in-place slab, precast plank or double tees each need their own bearing and edge details. Fix the deck system before detailing.

World Steel projects of this type

Built by World Steel, from our own plant

Steel designed, fabricated and supplied by World Steel. Photos are from our project archive and open full size.

Multi-story steel parking structure · Thailand · 2022

Omakase Car Park Building D

Steel structure designed, fabricated and supplied by World Steel. Tonnage not published.

Real photos

From our plant in Vietnam

World Steel’s own shop floors and jobs, where the steel for US projects is made: 2,500 metric tons of structural steel a month. Not stock images.

Inside our factory
Galvanized steel frames with punched bolt plates at the corners on shop trestles Photo
Galvanized frames with their bolt holes open and clean after dipping, Vietnam.
Painted members strapped into bundles and stacked for the voyage Photo
Bundles made up for an export shipment at the Vietnam plant.

How World Steel supports this

Designed to US codes, made in our plant in Vietnam

Garages already built

Omakase Car Park Building D in Thailand, a multi-story steel parking structure, and a real Design Report for an elevated parking deck you can read online.

Galvanized or coated

Hot-dip galvanizing and high-performance coating systems from Vietnam, with thickness recorded per member.

2,500 t a month

Capacity for a multi-level garage, or the garage and the building it serves, in one program.

The structural steel ecosystem

Products and solutions behind this guide

The products we make for this part of a seismic structure, the services that come with them and past World Steel projects, all one click away.

The industry behind this guide

World Steel projects of this type

Past World Steel work, shown for the structure type. It does not describe the seismic criteria of any one project.

Standards on this page

Read the standard behind it

Each standard page explains what it covers, the edition we reference and how we apply it. We design and fabricate to these standards; they are not certifications.

Keep reading

Related solutions

Questions from US contractors

Parking structures: questions we hear

Is steel a good choice for a parking garage?

Often, yes. A steel garage is lighter than a concrete one, so its foundations are smaller, and its long spans give open, column-free floors. Your Engineer of Record compares it with precast and cast-in-place concrete for your site.

Does a steel parking garage need fireproofing?

An open parking garage often does not, within the height and area limits of the IBC. An enclosed garage, or one under other occupancies, usually does. Your design team and the building official decide.

How do you protect garage steel from salt?

With hot-dip galvanizing, a high-performance coating system or a duplex system, chosen for the exposure. We record coating thickness per member and supply the touch-up material for site damage.

Have you designed a parking structure before?

Yes. Omakase Car Park Building D in Thailand is a multi-story steel parking structure that World Steel designed, fabricated and supplied, and our download center has a real World Steel Design Report for an elevated parking deck with a special moment frame.

Are shop drawings included?

Yes. Shop drawings come with every project at no extra charge, from one Tekla Structures model of the whole job. Your Engineer of Record reviews and approves the structural drawings.

Does World Steel erect the steel?

No. World Steel designs, fabricates and supplies the steel structure. Erection, the PE seal, the permit and site work are the scope of the US contractor, our customer.

A plain-English guide for US contractors, not engineering advice for a specific site. Ranges are typical, the adopted codes govern, and your Engineer of Record sets the design criteria for each project.

Bidding parking structures?

Send the drawings, the specification and the schedule. Our estimators take off the tonnage, confirm the production slot we can hold for it and return a written scope for steel designed to US codes, made in our plant in Vietnam and shipped to your US port by erection sequence.