IBC 2024 Chapter 6 and Chapter 7 · ASTM E119 / UL 263

Where the hours come from: US fire-resistance requirements for steel

Steel does not burn, but it loses strength as it heats. US codes respond with a simple idea: each part of the structure must keep carrying its load for a stated number of hours in a standard fire. The building code sets how many hours, a tested and listed design shows how to get there, and the fire protection on the steel is what makes the design work.

Ratings set by
IBC Table 601 and Chapter 7, by construction type
Proven by
ASTM E119 / UL 263 fire tests and listed designs
Decided by
Your architect, fire protection engineer and Engineer of Record

From occupancy to hours

How a steel frame gets its fire-resistance rating

The chain starts with what the building is for. The architect sets the occupancy group, then picks a construction type from IBC Chapter 6 that allows the height and floor area the owner wants. Type I and Type II are the noncombustible types used for most steel buildings, and each comes in a protected and an unprotected version.

IBC Table 601 then gives the rating, in hours, for each building element: the primary structural frame, bearing walls, floors and roofs. Section 703 says how a rating is proven, normally by a fire test to ASTM E119 or UL 263, and Section 704 sets how structural members are protected, including the rule that columns are protected individually and that a member holding up a rated floor or wall needs at least the same rating.

Other parts of the code add ratings of their own: fire walls and fire barriers, exterior walls close to a property line, shafts and exit stairs, and the extra rules for high-rise buildings in Section 403. Local amendments can change any of it, so the edition and amendments your jurisdiction enforces always come first.

IBC 2024 Table 601, steel types only

Ratings for the primary structural frame, floors and roofs

Hours of fire resistance by construction type, as a plain-English summary. Footnotes allow reductions, for example for roof-only framing, and your architect confirms the type and every value.

Construction typePrimary structural frameFloor constructionRoof construction
Type IA 3 hours (2 hours where it supports a roof only) 2 hours 1½ hours
Type IB 2 hours (1 hour where it supports a roof only) 2 hours 1 hour
Type IIA 1 hour 1 hour 1 hour
Type IIB No rating required No rating required No rating required
Type IIIA and VA 1 hour 1 hour 1 hour
Type IIIB and VB No rating required No rating required No rating required

Good news for many metal buildings

When steel needs no fire protection at all

Fire protection is a cost to justify, not a default. Many single-story steel buildings carry no rating.

Type IIB buildings

Most single-story warehouses, plants and retail boxes are built as Type IIB, where the frame needs no rating. Sprinklers and frontage let the building grow without changing the type.

High roofs

In many occupancies the code waives protection for roof framing where every part of the roof is 6 m (20 ft) or more above the floor below. Storage, mercantile and hazardous occupancies are among the exceptions.

Separation, not protection

Sometimes a fire wall, a fire barrier or more distance to the property line solves the problem better than coating every column. That choice belongs to your architect.

Where ratings appear

Multi-story offices, hospitals, schools, hotels, parking, high-rise and mixed-use buildings, and industrial buildings with hazardous occupancies or owner insurance rules.

Industries we serve From cold storage to aviation: the building types, systems and paperwork each US sector asks for. All industries → Building packages Planned steel building packages for the building types US owners ask for most. See packages →

Two words that change the thickness

Restrained and unrestrained ratings

Restrained

The surrounding structure resists the thermal expansion of a beam or floor in a fire. Many steel-framed floors qualify, and listed designs usually need less protection for a restrained rating.

Unrestrained

The member is free to expand and rotate, as for simply supported beams at some supports. Unrestrained ratings need more protection for the same hours.

Who decides

The classification follows the guidance in ASTM E119 and is the design team’s call. It must be shown on the drawings, because it changes the thickness the applicator puts on.

How we work Design, shop work and shipping run by one project manager, with each piece visible to you in PEB Studio. See the process →

The performance route

AISC 360 Appendix 4 and calculated fire resistance

Tested and listed designs are the prescriptive route most projects use. AISC 360-22 Appendix 4, Structural Design for Fire Conditions, adds a way to show by analysis how a steel structure behaves in a defined fire, using the elevated-temperature properties of the steel. It is used on large or unusual buildings, such as atriums, exposed steel and long-span roofs, where a fire engineering study can reduce or target the protection.

IBC Section 722 also allows calculated fire resistance for some steel members, and AISC Design Guide 19 explains how ratings, listings and calculations fit together. Both routes need the building official’s acceptance, and both are the work of the design team. We supply the member sizes, weights and section data that their calculations need.

Two standard fires

The building fire and the hydrocarbon fire

ASTM E119 and UL 263 climb steadily over hours. UL 1709 reaches about 1,093 °C (2,000 °F) within five minutes. Protection is tested, and listed, against the fire it will face.

Standard fire curves for steel The ASTM E119 and UL 263 building fire rises to about 927 °C at one hour and 1,010 °C at two hours. The UL 1709 hydrocarbon fire reaches about 1,093 °C within five minutes and stays there. Unprotected steel columns reach the 538 °C average limit within minutes. 03006009001,200 030 min1 h2 h3 h4 h °C 538 °C (1,000 °F) column average limit UL 1709 hydrocarbon fire ASTM E119 / UL 263 building fire
Standard building fire Hydrocarbon pool fire Steel column limit

Real photos

From our plant in Vietnam

World Steel’s own shop floors and jobs, where the steel for US projects is made. Not stock images.

Metal floor deck laid on each level of a steel-framed building Photo
Going up beside the plant in Vietnam: World Steel framed its own office building.
Red multi-story process tower frame next to a feed mill Photo
Process tower frame by World Steel in Vinh Long Province, Vietnam.

How World Steel supports this

Designed to US codes, made in our plant in Vietnam

Ratings captured at kickoff

Construction type, hours and restrained or unrestrained status are recorded for each member type before design starts.

Section data for the team

Weights, heated perimeters and section factors for every member, ready for the protection schedule.

Shop drawings, included

Rated members and their protection are flagged on the shop drawings at no extra charge.

The fire protection ecosystem

Products and solutions behind this guide

The products we make for this part of a seismic structure, the services that come with them and past World Steel projects, all one click away.

World Steel projects: process plants, healthcare, multi-story

Past World Steel work, shown for the structure type. It does not describe the seismic criteria of any one project.

Standards on this page

Read the standard behind it

Each standard page explains what it covers, the edition we reference and how we apply it. We design and fabricate to these standards; they are not certifications.

Keep reading

Related solutions

Questions from US buyers

US fire-resistance requirements: questions we hear

Does every steel building in the US need fireproofing?

No. Many single-story buildings are Type IIB, where the frame needs no rating. Ratings come from the construction type, the occupancy, the height and area, separations and local amendments.

Who decides the fire-resistance rating of my steel frame?

The architect and fire protection engineer, from the building code your jurisdiction enforces, with the Engineer of Record. The building official accepts it at permit.

Is a sprinklered building exempt from fire-resistance ratings?

Not automatically. Sprinklers allow more height and area for a construction type and some trade-offs, but the type still sets the ratings.

Can a fire engineering study replace listed designs?

Sometimes. AISC 360 Appendix 4 and IBC alternative means let the design team show performance by analysis, subject to the building official’s approval.

Are shop drawings included for fire-rated steel?

Yes. Shop drawings come with every project at no extra charge, with the rating, protection system and listed design shown for each rated member. Your Engineer of Record reviews and approves the structural drawings.

A plain-English summary for US buyers, not the code text and not engineering advice for a specific site. The adopted codes and standards govern, and your Engineer of Record confirms the criteria for each project.