End plate fabrication for seismic moment connections: welds, stiffeners, flatness and fit-up

In a bolted end-plate moment connection almost all the critical work happens in the shop. Section 6.6 of AISC 358-22 fixes how the beam is welded to the plate and how stiffeners are shaped and welded. This is what good end plate fabrication looks like, step by step, and what to check before the steel ships.

· 6 min read · World Steel USA engineering team

An extended end-plate moment connection is assembled on site in minutes, but it is made in the shop over many hours. The beam is cut square, the plate is cut and drilled, the beam is welded to the plate with demand-critical welds, the stiffeners go on, and the assembly is checked for flatness, squareness and hole position before painting. If any of that goes wrong, the erector finds a gap at the column face or bolts that will not line up, and a field fix on a seismic connection is rarely simple. Section 6.6 of AISC 358-22 sets the shop rules. This article reads them as a sequence of end plate fabrication steps.

Plate and stiffener geometry

The end plate comes straight from the calculation and Table 6.1: thickness, width, bolt gage and pitch, all within the tested range. Plate thickness can reach 57 mm for a 4E and 64 mm for an 8ES, so cutting thick plate accurately is the first step. The plate must be flat and its bolt holes on the exact pattern, because the bolts will be pretensioned against the column flange.

For the stiffened 4ES and 8ES layouts, Section 6.6.4 fixes the stiffener:

  • Length: at least the stiffener height divided by tan 30°, where the height is the end plate extension from the outside of the beam flange to the plate end. The stiffener is therefore a long triangle at 30° to the flange.
  • Landings: the stiffener ends with straight landings at least 25 mm (1 in.) long at the beam flange and at the end of the plate, rather than running out to a point.
  • Clip: where it meets the beam flange and the end plate, the stiffener is clipped to clear the flange-to-plate weld.
  • Thickness: at least the beam web thickness when the steels match; if the stiffener is a weaker steel, the web thickness times the ratio of beam yield stress to stiffener yield stress.

The beam-to-plate welds

Section 6.6.6 sets six welding rules.

No access holes

Weld access holes are not used. The flange is welded to the plate from outside, and the web is welded along its full depth. That keeps the beam web continuous to the plate and avoids the notch an access hole would create.

Flange welds

The beam flange-to-end plate joint is a CJP groove weld without backing, with the root on the beam web side of the flange. The inside face of the flange gets an 8 mm (5/16 in.) fillet weld. These welds are demand-critical, so they follow AWS D1.8 for filler metal toughness and procedure qualification.

In practice the flange is bevelled from the outside, welded, and the root area on the inside is backgouged and closed by the fillet. Section 6.6.6(5) eases one spot: for a length of 1.5 times k1 directly above and below the beam web, backgouging is not required, and a full-depth partial-joint-penetration weld is allowed there, because the web blocks access to the root.

Order of welding

For stiffened plates, the flange-to-plate weld is made before the stiffener is installed. Putting the stiffener on first would block access to the flange weld and its inspection.

Web welds

The beam web is joined to the plate by fillet welds or a CJP groove weld. Fillets must develop the full tensile strength of the web from the inside face of the flange to 150 mm (6 in.) beyond the bolt row farthest from the flange. Beyond that, the web weld only needs to carry shear.

Stiffener welds

End plate-to-stiffener joints are CJP groove welds. Stiffeners up to 10 mm (3/8 in.) thick may instead use fillet welds that develop their strength. The stiffener-to-beam flange weld is sized to the same principle.

Distortion and flatness

Heavy CJP welds on one face of a plate pull it. A thick end plate welded to a beam can come out slightly dished, with the extended parts pulled toward the beam. Pretensioned bolts cannot be relied on to pull a stiff plate flat against the column, and a gap at the faying surface changes how the bolts and plate share load. A sound shop routine controls this:

  • Weld sequence: balance passes between the top and bottom flanges and between both sides of the web.
  • Heat input and preheat: follow the WPS, which on thick plates usually calls for preheat; it limits cracking and reduces the gradients that cause distortion.
  • Restraint: clamp the plate to a stiff fixture during welding where the joint allows.
  • Check flatness and squareness after welding and cooling, on the faying face of the plate and between the plate and the beam axis.
  • Correct or reject: small distortion may be corrected by approved methods; heat straightening near demand-critical welds needs care and approval.

The standard allows finger shims at the top or bottom of the connection within RCSC limits, which absorb small gaps from column tolerances on site. They are not a substitute for a flat plate.

Fit-up and length

The beam length between end plates must match the column-to-column distance, less the column flange tolerance, because there is no field adjustment along the beam. That puts the end plate's position, squareness and the beam cut length on the critical list. Hole positions on the plate must match the column flange holes within the hole clearance. Our bolt-hole fabrication article explains why the hole process and type are recorded.

Built-up beams with end plates

Where the beam is a welded built-up section rather than a rolled shape, Section 6.3.1 adds a rule at the moment-connected end: within the lesser of one beam depth or three flange widths of the end, the web is joined to the flanges with a CJP groove weld or a pair of fillets each at least 75 percent of the web thickness, and never less than 6 mm (1/4 in.). Beyond that length, the web-to-flange weld only needs to carry the shear transfer. For the shop this means the automatic fillet welding of the girder changes size near each end, and the change point appears on the drawing. It also means the end preparation of the girder is done after the web-to-flange welds, so the end plate sits on a square, finished section.

Continuity plates in the column

The column side of an end-plate connection is part of the same package. Section 6.4 lets continuity plates up to 10 mm (3/8 in.) thick be welded to the column flanges with double-sided fillets sized for the plate's yield force over the contact area; thicker plates follow AISC 341, usually with CJP welds. Chapter 3 sets the corner clips. Because the column flange is clamped by large pretensioned bolts, its flatness matters too: a column flange pulled out of plane by continuity plate welds can leave a gap just like a distorted end plate.

Inspection before shipping

A practical checklist for each end-plate beam end:

  • plate thickness, width and steel grade, with heat number traced to its certificate;
  • bolt hole size, position, gage and pitch against the drawing;
  • flange CJP weld visual inspection and ultrasonic testing as the inspection plan requires;
  • inside fillet, web welds and stiffener welds sized and complete;
  • stiffener length, 30° angle, landings and clips;
  • flatness and squareness of the plate;
  • faying surface protected or masked as the bolting class requires;
  • protected zone marked, with no attachments.

These go into the record for the beam mark and the Manufacturing Data Record for the shipment.

Proof from our plant and projects

We weld end plates to beams every day, from light metal building rafters to heavy industrial girders, which is why the details in this article are shop routine rather than special measures. Plates and stiffeners are cut on our CNC laser machines, which handle steel up to 100 mm thick; beam-to-plate welds are made flat by welders qualified to our AWS D1.8 procedures; and ultrasonic testing of the flange CJP welds is done in house.

Our flagship jobs show the scale: the 5,000 t Sunpro Steel mill, the 2,500 t CPV Food plant and the 2,000 t M&D Warehouse in Thailand. The plant is accredited under IAS AC472, audited twice a year since 2019, and inspectors can review end plates at the plant or remotely before they ship.

How World Steel makes end plates

End plates and stiffeners are cut on our CNC laser machines, which handle steel up to 100 mm thick, from programs taken from the Tekla model. Beam-to-plate welds are made in the flat position in the shop, by welders qualified to our AWS D1.8 procedures, with balanced sequences for flatness and testing as the plan requires. Each assembly is checked against a fixture before painting. Our plant in Vietnam is accredited under IAS AC472, the first and only one in Vietnam, and the owner's inspector can visit or follow the work remotely.

Bolting and erection on site are the US contractor's scope. For the design side read the extended end-plate article, and for the seismic provisions read the AISC 341 landing.

Quick answers

Are weld access holes used in end-plate connections?

No. Section 6.6.6 does not allow weld access holes. The beam flange is welded to the end plate with a CJP groove weld without backing, rooted on the web side, plus an 8 mm (5/16 in.) fillet on the inside face.

How long must an end-plate stiffener be?

Section 6.6.4 sets the minimum length as the stiffener height divided by tan 30°, with landings at least 25 mm (1 in.) long at the flange and at the plate end, and a clip to clear the flange weld.

Which is welded first, the flange or the stiffener?

For stiffened end plates, Section 6.6.6 requires the beam flange-to-end plate weld to be made before the stiffener is installed.

How thick must the stiffener be?

At least the beam web thickness when the materials match; if the stiffener steel is weaker, the web thickness times the ratio of beam to stiffener yield stress.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AISC 358-22 prequalified connections series

Twenty in-depth articles on the 2022 standard for prequalified moment connections: the design rules every connection shares, the welding and bolting chapters, each connection family a US moment frame uses, and how the choice plays out in the high-seismic West and the New Madrid zone.

Chapters 1–2Scope and design rules

What prequalification means, what changed in 2022, member limits and the moment at the column face.

Chapters 3–4Welding, bolting and QA

Backing, weld tabs, continuity plate clips, pretensioned bolts, holes and the inspection record.

Chapters 5 and 8Welded connections

The reduced beam section and the welded unreinforced flange, welded web.

Chapters 6, 7 and 13Bolted connections

Extended end plates, bolted flange plates and the double-tee.

Chapters 9–15Brackets, slots and proprietary systems

Cast bolted brackets, the slotted web, and the patented connections in the standard.

Where it appliesUS projects

Choosing a connection, and AISC 358 in the West Coast, Intermountain and New Madrid markets.

Bidding a large US project?

Send the bid documents, or just a footprint and an address. Our engineers check them against US code requirements and confirm what World Steel would supply, from a plant that fabricates 2,500 metric tons of structural steel a month.