Flagship project
Our largest job was the steel of a steel maker’s own mill
Sunpro Steel Factory, Can Tho City, Vietnam: a steel production plant built from about 5,000 metric tons of World Steel structural steel and completed in 2024. It is the reference we put in front of every large US contractor planning a mill or a heavy crane building.
- A steel maker is the hardest customer for a steel structure. Sunpro Steel chose World Steel for the full frame of its own plant.
- Laced crane columns, heavy built-up members and crane runways were modeled, detailed, fabricated, coated and packed in one plant.
- The same team designs mill buildings for US projects to AIST Technical Report No. 13, CMAA, AISC and ASCE 7.
-
Sunpro Steel
5,000 t
(5,500 short tons) of steel
Our largest single job: the whole structure of a steel production plant, designed, fabricated and supplied by World Steel.
-
Sunpro Steel
150 t
(165 short tons) overhead crane
The heaviest crane World Steel has designed a building for, running on laced crane columns and built-up runway girders.
-
Sunpro Steel
2,500 t
(2,750 short tons) a month
Fabrication capacity of World Steel’s own IAS AC472-accredited plant, so a mill package runs beside other work.
-
Sunpro Steel
2024
plant completed
Steel production plant in Can Tho City, Vietnam, for a steel maker that knows its material.
Steel mill areas
From scrap to shipping: what each part of a mill asks of its steel
A steel mill is designed from the process outward. The cranes, furnaces and casters in each area set the bay widths, hook heights and loads, and the frame is sized around them. Areas marked Sunpro Steel are part of the plant we supplied.
- Scrap baySunpro Steel Tall, wide bays for scrap handling cranes with magnets or grabs, heavy impact on the runway and walls that take knocks from loaders.
- Melt shop and furnace platformSunpro Steel Heavy platforms around the furnaces, radiant heat near the steel, ladle cranes over hot metal and the largest crane loads in the plant.
- Continuous casterSunpro Steel A raised caster platform, the casting floor and runout tables, with tight alignment for equipment and cranes for ladles and tundishes.
- Rolling mill Long bays over the rolling line, roll shop cranes, foundations kept clear of the column grid and vibration from the stands.
- Product storage and shipping Long-span storage bays with magnet or C-hook cranes for billets, bars and coils, and truck or rail loading under the crane.
At Sunpro Steel the 3D model package was split by plant area, among them the scrap bay, the induction furnace platform and the continuous caster platform, so each area could be detailed, fabricated and shipped in its own sequence.
Made in World Steel’s plant, Vietnam
The Sunpro Steel run on our shop floor
These photos were taken in World Steel’s own plant while the Sunpro Steel members were in fabrication: laced crane columns on the shop supports, coating, packing and dispatch. A US mill package runs through the same halls.
Cut and drilled
Plates cut by CNC, holes drilled or cut by laser up to 100 mm (4 in) thick, slots for the bolted splices.
Built up and laced
Crane legs, roof legs and lacing fitted and welded into laced crane columns, heavy built-up girders on the beam lines.
Blasted and coated
Indoor blasting and coating, with the end plates and faying surfaces masked as the drawings require.
Packed and marked
Members wrapped, stacked on timber dunnage and tagged with piece marks matching the erection drawings.
-
Laced crane columns lined up on shop supports, the Sunpro Steel run filling the hall.
-
A heavy laced crane column welded under the shop crane.
-
Crane legs and roof legs joined by lacing, end plates slotted for the bolted splices.
-
Column end detail: slotted holes and bracket plates, marked for fit-up.
-
End plates marked by the fitters before welding and inspection.
-
One hall of the World Steel plant given over to Sunpro Steel crane columns.
-
Coating a laced crane column in the shop, before packing.
-
Coated column ends checked before release.
-
Members and base plates packed and stacked under the shop crane.
-
Wrapped members with piece-mark tags, so the site crew finds each one fast.
-
The dispatch hall: wrapped Sunpro Steel members ready for the road.
-
Loading a wrapped member onto a low-bed trailer for the trip to Can Tho.
Mill crane design to US standards
The US documents behind a steel mill crane building
A mill crane building sits where a crane specification meets a building code. These are the documents we design a US steel mill structure to, and the in-depth pages on each.
What makes a mill crane building different
Hot metal over the floor
Ladle cranes carry molten metal. The crane maker designs them for that duty; the building gives them stiff runways, safe end stops and room for heat shields.
Cycles, not just tons
A mill crane may lift near capacity many times an hour for decades. Fatigue of the runway girder and its welds often decides the section, not strength.
Heat near the steel
Members close to furnaces and casters can see radiant heat. Shielding, coating choice and the temperature the steel will reach are agreed in the design basis.
Two or more cranes per bay
Mill bays often run several cranes on one runway. The load cases cover cranes side by side, and the stops and bumpers are sized for the worst one.
Tight runway alignment
Rail alignment and girder tolerances are drawn on the approval drawings, so the crane maker and the erector start from the same numbers.
Dust, fumes and ventilation
Roof monitors, louvers and the dust that settles on roofs and girders in a melt shop are part of the frame and cladding design.
Association for Iron & Steel Technology
TR-13
Guide for the Design and Construction of Mill Buildings
The US reference written for steel mill buildings, and the document many mill owners name in their specifications.
| Class | Crane load cycles |
|---|---|
| A | over 500,000about 25 lifts a day for 50 years · Scrap yards, steelmaking, continuous casting, billet and slab yards |
| B | 100,000 to 500,000about 5 to 25 a day · Busy production bays below Class A duty |
| C | 20,000 to 100,000about 1 to 5 a day · Moderate service bays |
| D | under 20,000about 1 a day or less · Maintenance and occasional-use cranes |
AIST Technical Report No. 13
What the mill building guide covers, and how we apply it
TR-13 goes further than a general building code for one reason: mill cranes work hard, all day, for decades. These are the parts of it that shape the steel we design and fabricate.
Building class from load cycles
The owner sets a class for the whole building or for each part, from the crane load repetitions expected over a service life of usually 50 years.
Scrap, melt and cast are Class A
Scrap yards, steelmaking and continuous casting buildings, billet yards and shipping are listed as Class A, the most severe: the areas of a plant like Sunpro Steel.
Higher side thrust for mill cranes
Side thrust is taken as a share of the lifted load by crane type: about 40% for ladle and mill cranes and up to 100% for scrap, slab and billet magnet cranes, well above the general building code value.
Stiffer runways in busy classes
Vertical runway deflection from one crane is held to span/1000 in Class A and B buildings and span/600 in C and D; lateral deflection to span/400.
Runway girder rules
No tension field action in crane girder webs, camber on long spans, no unplanned attachments, and welds for cyclic loading flagged on the drawings to AWS D1.1.
Bumper forces on the drawings
The crane maker’s maximum bumper force is coordinated with the steel designer and shown on the structural drawings, with the stops and their load path designed for it.
Where the owner’s specification calls for AIST Technical Report No. 13, we design the mill building to it together with AISC 360, ASCE 7 and the IBC, and state the building class, crane data and limits used on the design basis. TR-13 itself expects the drawings to be sealed by the engineer of record: that is your Engineer of Record, who reviews and approves our design.
In-depth articles
Mill buildings under AIST TR-13, part by part
Thirty in-depth articles on AIST Technical Report No. 13: crane classes and loads, soil and foundations, floors and process loads, frames, runway girders and the shop and service side, each paraphrasing the section it follows, with metric values first.
30 articles · 6 parts
Building class, dynamic crane forces, load combinations and the crane data.
Soil investigation, foundations under heavy cranes and the floor slab.
Floors, vehicles, earthquake, wind and snow, machines, ducts and harsh areas.
Columns, bracing, trusses, girts, equipment floors and connections.
Fatigue details, stiffness, backup bracing, end stops and the rail system.
Weld testing, tolerances, maintenance access, inspection and upgrades.
Steel mill solution
Design and fabrication of the whole mill structure, from one plant
What we did for Sunpro Steel is what we offer a US contractor building a mill: one team for the design, the drawings, the fabrication, the cranes on request and the shipping.
- Structural designDesign to AISC 360, ASCE 7, AIST TR-13 and AISC Design Guide 7, with a Design Report and calculations for your Engineer of Record.
- 3D model and shop drawingsA full 3D model split by plant area, approval drawings and shop drawings at no extra cost, erection drawings with piece marks.
- Overhead cranes on requestWorld Steel can supply overhead cranes with the building, so runway, columns and crane are sized from one set of data.
- Fabrication at scale2,500 t (2,750 short tons) a month in our own IAS AC472-accredited plant, laser cutting up to 100 mm (4 in) thick.
- Live tracking in PEB StudioFollow every column and girder from cutting to coating, QC release and packing, in real time.
- Packed and shipped to the USPacked by erection sequence, marked by piece and shipped to the US port your contractor chooses.
Who does what on a US mill project
World Steel supplies the steel structure and does not erect it. The US contractor, our customer, builds the plant.
-
World Steel, Vietnam
- Designs the steel structure and crane runways
- Fabricates, coats, packs and ships
- Supplies overhead cranes on request
- Gives remote access to the shop and QC records
-
The US contractor, our customer
- Erects the steel and installs the crane
- Runs foundations, anchor bolts and site work
- Engineer of Record reviews and approves the drawings
- Handles the permit and the PE seal
-
The plant owner and crane maker
- Set the crane duty, class and process loads
- Give the crane data sheet and wheel loads
- Run the crane safety program under OSHA
- Approve the layout of process equipment
For US contractors
Steel plants we can design and fabricate for in the US
Bidding a mill job? Partner with us: you keep the site, the erection and the client; we carry the design and the steel at 2,500 t a month.
Melt shops and mini-mills
Scrap bays, furnace platforms and casters for electric arc and induction furnace plants.
Rolling and finishing mills
Long crane bays over rolling lines, roll shops and finished product storage.
Coil and bar processing
Service centers, slitting lines, rebar fabrication and coil storage with heavy cranes.
Foundries and forges
Hot work bays with ladle and handling cranes, heavy platforms and ventilation.
Questions from US contractors and mill owners
Questions about Sunpro Steel and steel mill structures
What did World Steel supply for Sunpro Steel?
The steel structure of the Sunpro Steel production plant in Can Tho City, Vietnam: about 5,000 metric tons (5,500 short tons), designed, fabricated, coated and supplied by World Steel and completed in 2024. It includes laced crane columns and crane runways for overhead cranes up to 150 t.
What is the largest crane World Steel has designed a building for?
A 150 metric ton (165 short ton) overhead crane at Sunpro Steel. The runway girders, crane columns and frame were designed for the crane loads, fatigue and deflection limits of that crane.
What is AIST Technical Report No. 13?
It is the Association for Iron & Steel Technology Guide for the Design and Construction of Mill Buildings, the US reference for steel mill buildings. It classifies mill buildings by crane service, sets crane loads, runway girder details, fatigue design and deflection limits, and is often named in steel mill owners’ specifications.
Can you design a US steel mill building to AIST TR-13?
Yes. When the specification calls for it, we design the mill building to AIST TR-13 together with AISC 360, ASCE 7, AISC Design Guide 7 and the IBC, and state the building class and crane data on the design basis. Your Engineer of Record reviews and approves the design.
How does AIST TR-13 relate to CMAA 70?
CMAA 70, and AIST TR-6 for mill-duty cranes, cover the crane itself and are the crane maker’s documents. AIST TR-13 covers the building that carries the crane. We design the building from the crane maker’s data so both match.
Does World Steel supply the overhead cranes?
Yes, on request World Steel supplies overhead cranes with the building, so the crane, runway and columns are sized from one set of data. Installation on site is done by the US contractor or the crane installer.
Does World Steel erect the steel?
No. World Steel designs, fabricates and ships the steel structure. Erection, crane installation and site work are done by the US contractor, our customer, and its crews.
Who approves the drawings and seals the design?
The Engineer of Record of the US contractor or owner reviews and approves our calculations and drawings and handles the PE seal and the permit. World Steel provides the design, the Design Report and the drawings for that review.
How large a steel mill package can your plant take?
Our own plant fabricates about 2,500 metric tons (2,750 short tons) a month. Sunpro Steel, at about 5,000 t, is our largest single job so far. A large mill is fabricated in sequences so the steel the erector needs first ships first.
How are heavy crane columns shipped to the US?
Members are sized during design to fit the planned shipping, in containers where they fit or as breakbulk for long and heavy pieces, with bolted splices placed where they suit both the structure and the transport.
Can I watch fabrication of my mill steel?
Yes. PEB Studio shows every member from cutting to coating, QC release and packing in real time, and you or your inspector can visit the plant or join a remote inspection.
What crane data do you need to start?
Crane capacity, span, service class or duty, maximum wheel loads and wheel spacing, hook height, the number of cranes per bay and the bumper force. With that we design runways, columns and frame as one system.