What is EN 10204?
+
EN 10204 is the European standard that defines the types of inspection documents a manufacturer supplies with metallic products, such as steel plate, sections and coil. It names four types, 2.1, 2.2, 3.1 and 3.2, and says what each must contain and who must validate it. It does not set any property limits: those come from the product specification, such as an ASTM grade.
What is the difference between EN 10204 2.2 and 3.1?
+
A 2.2 test report gives results of non-specific inspection: typical values from the same manufacturing process, validated by the manufacturer. A 3.1 inspection certificate gives the actual results of tests on the delivered product or its test unit, validated by the manufacturer’s inspection representative who is independent of production. For structural steel, ask for 3.1.
What is the difference between EN 10204 3.1 and 3.2?
+
Both report specific inspection of the delivered product. A 3.1 is validated by the mill’s own independent inspector. A 3.2 is validated by that inspector and also by the purchaser’s authorized inspector or an inspector designated by official regulations, who witnesses the tests.
Is a mill test certificate the same as a mill test report?
+
In practice yes. US mills usually call it a mill test report or certified mill test report, made to ASTM A6/A6M or A568/A568M. Mills in Asia and Europe usually call it a mill test certificate and state the EN 10204 type. What your reviewer checks is the same: grade, heat number, chemistry and test results.
Are EN 10204 3.1 certificates accepted on US projects?
+
Yes, when they report the results the specified ASTM grade requires. AISC 360 accepts the manufacturer’s test reports made to the ASTM requirements as evidence of conformity, and the Engineer of Record reviews them against the specification. The EN 10204 type describes the document; the ASTM grade sets the numbers.
Can one certificate show both an ASTM grade and EN 10204?
+
Yes, and that is common. The certificate states the EN 10204 document type, for example 3.1, and reports steel made to an ASTM specification, such as A572 Grade 50 or A992. Some mills also dual-certify to two grades when the steel meets both.
What is a heat number?
+
The identification of one melt, or heat, of steel. All steel from a heat shares one chemistry. The heat number is printed on the certificate and marked on the steel, and it is the link a fabricator uses to trace each member back to its certificate.
What did 3.1.B mean?
+
It was a type in the 1991 edition of EN 10204: an inspection certificate validated by the manufacturer’s department independent of production. The 2004 edition replaced it with 3.1. The old 3.1.A, 3.1.C and 3.2 became the new 3.2.
Can a stockist or trader issue a 3.1 certificate?
+
A distributor can supply a certificate, but under EN 10204 it should pass on the manufacturer’s inspection document without change, and keep the product identifiable so the document still applies. A certificate retyped on a trader’s letterhead, with no mill document behind it, does not trace back to the mill.
Is an electronic or unsigned certificate valid?
+
EN 10204 allows inspection documents to be issued and validated electronically, provided the validation is identifiable. ASTM test reports printed from an electronic system are also accepted, and the organization issuing them stays responsible for their content even without a handwritten signature.
When are Charpy values needed on a mill certificate?
+
When the grade itself includes impact testing, as ASTM A1085 does, or when the specification, AISC 360 or AISC 341 calls for notch toughness, typically for heavy shapes, thick plate in welded tension joints, seismic members and steel in cold service. The test has to be ordered with the steel.
What does World Steel supply?
+
EN 10204 3.1 certificates for each heat of plate, coil and section, reporting the ASTM grade you specify, with Charpy V-notch results on request. Each heat is checked at our gate, kept to the piece marks that use it, and handed over with the material schedule. Where your specification needs 3.2, it is agreed at quote stage.
Does World Steel approve the material for our project?
+
No. World Steel buys, checks and fabricates the steel and supplies its certificates. Reviewing and accepting the material against the specification is the job of the Engineer of Record and the US contractor, our customer.