Design process

From RFQ to released shop drawings

Steel is cut only after you, or your Engineer of Record, approve the drawings. These are the eight design steps, the documents each one produces and what we need from your side, issued under one drawing register you can audit.

Project
Your US steel package
Code basis
IBC 2024 · ASCE 7-22 · AISC 360
Drawn in
Tekla Structures
Analysis
SAP2000
Approved by
Your Engineer of Record
Status
Released for fabrication

Drawing register

Eight steps, one register, an approval gate before any steel is cut

Each step issues a named set of documents and waits for a named decision. Every row opens a full guide to that step.

Request for quote

Read the full guide
What happensSend whatever exists: architectural plans, a sketch, a takeoff or an IFC model, with the address, occupancy and any cranes, mezzanines or rooftop equipment.
Documents issuedYour RFQ file, read as one dossier
Your decisionShare what you have; we flag what is assumed
Who actsYou

Proposal and pricing

Read the full guide
What happensAn estimator and an engineer prepare proposal drawings and a scope letter: what is supplied, what is by others, the Incoterm and who is importer of record.
Documents issuedProposal drawings, scope letter, quotation
Your decisionAccept the scope or ask for alternates
Who actsWorld Steel → you

Design basis

Read the full guide
What happensCode edition, local amendments, risk category, loads, steel grades and coating are written into one sheet before any member is sized.
Documents issuedDesign criteria sheet
Your decisionConfirm loads, codes and amendments with your EOR
Who actsYou + EOR

Structural analysis

Read the full guide
What happensPrimary frames, bracing and cold-formed members are analyzed in SAP2000 to AISC 360 and AISI S100 for every governing combination.
Documents issuedCalculation set
Your decisionReview through your Engineer of Record
Who actsWorld Steel

Approval drawings

Read the full guide
What happensAnchor rod plan, base reactions, framing plans and elevations are issued for approval. Comments are logged, answered and reissued under a new revision.
Documents issuedAnchor rod plan, reactions, framing drawings
Your decisionApprove or mark up; release the foundation design
Who actsYou + EOR

Permit submittal package

Read the full guide
What happensCalculations, design drawings and product data are assembled in the order US plan reviewers expect.
Documents issuedCalculation package and submittal drawings
Your decisionYour EOR approves and seals; you submit
Who actsEOR → you

Tekla model and BIM

Read the full guide
What happensThe approved design is modeled in Tekla Structures, with an IFC file for your architect and MEP trades to check clashes.
Documents issuedTekla model, IFC export
Your decisionCoordinate with your architect and MEP trades
Who actsWorld Steel

Shop and erection drawings

Read the full guide
What happensEvery assembly, bolt and weld is detailed, and erection drawings place each piece mark on its gridline so your crew builds in the right order.
Documents issuedShop drawings, erection drawings, bills of material
Your decisionRelease for fabrication in writing
Who actsYou

Shop and erection drawings are included on every project at no extra cost. World Steel does not seal drawings: your Engineer of Record approves them, and the US contractor, our customer, handles the PE seal and the permit.

Revision control

Every sheet carries its history

Comments are logged, answered and clouded on the next revision, so your team, your erector and your inspector always work from the same set.

  1. A

    Issued for approval

    World Steel

  2. B

    Comments from your EOR answered and clouded

    World Steel

  3. C

    Approved, no exceptions taken

    Your Engineer of Record

  4. 0

    Released for fabrication

    You

Nothing is fabricated from a superseded sheet. The shop works from the Tekla model of the released revision, and every member carries an ID tied to it in PEB Studio.

Your team

The people on your design

Project engineer

Owns the design basis and the calculations, and answers technical questions from your engineer or plan reviewer.

Detailers

Build the Tekla model and produce shop, assembly and erection drawings with consistent piece marks.

Project manager

Keeps the drawing schedule, chases approvals and is your single contact from contract to final delivery.

Quality team

Confirms that drawings, material grades and inspection requirements agree before production starts.

Changes after approval

A change is a form, not a phone call

Scope moves on real projects: a tenant wants a second overhead door, the owner adds a bay, the roof must carry solar. We take the change on, but first we log it and send you its effect on drawings, schedule and price in writing. Nothing is fabricated on a verbal instruction.

If the frame looks heavier than it should, ask for a value engineering review: alternatives with calculations behind them, and your Engineer of Record makes the call.

Shop drawing coordination
Change requestExample
Requested changeAdd a 4.3 m × 4.9 m (14 ft × 16 ft) overhead door on gridline C
Drawings affectedFraming elevation, wind column, girt layout
Schedule effectSent to you in writing before work continues
Price effectQuoted and agreed in writing
Approved byYou, with your Engineer of Record

Asked by US contractors

Questions on design process

Will you work to my engineer’s design instead of your own?

Yes. We can be the steel designer, or detail and fabricate to the drawings your Engineer of Record issues. In both cases approval drawings go back to that engineer before production.

What files can I send with my RFQ?

PDF and DWG drawings, IFC models, spreadsheets and site photos, uploaded privately through the quote form.

Who seals the set for my permit?

World Steel designs and fabricates the steel structure. Your Engineer of Record reviews and approves our drawings, and the PE seal and permit are the scope of the US contractor, our customer.

When does fabrication begin?

After the approval drawings are signed off and you have released the shop drawings for fabrication in writing.

Do shop drawings cost extra?

No. Shop and erection drawings are included on every project, produced from the same Tekla model that drives the shop.

How are revisions controlled?

Every sheet carries a revision letter and every comment is logged with its answer, so your team, your erector and your inspector work from the same set.

Keep reading

Next in how we work

World Steel designs, fabricates and supplies the steel structure. You, the US contractor and our customer, erect it, and with your Engineer of Record approve the drawings and handle the PE seal and the permit.

Start a design with a clear register

Send drawings, a model or a sketch with the address. We return a scope letter and proposal drawings, then run the eight steps with you, revision by revision.