Cambered plate girders: cutting the camber into the web

A welded plate girder does not need a press or a torch to get its camber. The web plate is cut to the camber curve before the flanges go on. The skill is in keeping that curve through welding, and in knowing when to skip camber and adjust the connections instead.

· 6 min read · World Steel USA engineering team

Rolled beams get their camber by being bent, cold in a press or hot with a torch. Welded plate girders can skip that step. Because a plate girder is built from separate plates, its camber can be designed into the shape of the web before the girder exists. AISC Design Guide 36 (2020), Section 5.2 describes the method for heavy girders, and it is the normal way to produce cambered plate girders for long spans, transfer levels and industrial buildings.

Why plate girders are cambered differently

A welded plate girder, also called a built-up I-section, has three main plates: a web and two flanges, joined by continuous fillet or groove welds. Its depth, flange widths and plate thicknesses are chosen freely, which is why engineers use them where rolled shapes run out: long spans, very heavy loads, deep transfer girders.

That same freedom applies to camber. Rather than bend a finished girder, the fabricator gives the web plate the profile of the cambered girder. When the flanges are fitted to the web, they follow its edges, and the girder is cambered from the start.

Cutting the camber curve

The process starts in the model.

  • The camber diagram. The engineer specifies the camber, usually as a midspan value with a parabolic or circular profile, or as ordinates at stated points.
  • The web profile. The detailer models the web with its top and bottom edges offset by the camber ordinates along the length. For a girder with a straight cross section, both edges get the same offsets so the depth stays constant.
  • Nesting and cutting. The web profile is nested on plate and cut by CNC laser, plasma or oxy-fuel, so the curve is produced to the accuracy of the cutting machine rather than an operator's eye.
  • Fit-up. The flanges are clamped or jacked to the curved web edges in a fit-up fixture and tack welded.

On a typical camber the curve is so gentle that flange plates bend to it easily within the elastic range during fit-up. The curved and cambered members page shows the same principle applied to arched rafters, where the curve is much tighter.

Holding the curve through welding

The hard part of a cambered plate girder is not the cutting but the welding. Every flange-to-web weld shrinks as it cools, and shrinkage on one side of the girder pulls it toward that side. Design Guide 36 notes two practical points:

  • Weld sequence sets the result. Welding the bottom flange first tends to add positive camber, because the bottom shrinks while the top is still free. Welding the top first tends to reduce it. Fabricators plan the sequence, and sometimes alternate between flanges, to land on the specified camber.
  • Check after welding. The camber is measured after all main welds are complete, not after fit-up, because fit-up camber can change during welding.

Submerged arc welding on long girders puts in a lot of heat in a continuous run. Shops with experience of a given girder size learn how much each sequence moves it and set the web profile, or the sequence, to compensate.

Correcting small differences

If a girder comes out slightly under or over its camber after welding, small corrections are made with heat. Design Guide 36 lists heat cambering as the usual way to correct a small camber change in a welded girder. The work follows AISC 360 Section M2.1, with heated areas kept at or below 650°C (1,200°F) for ordinary structural steel, or 595°C (1,100°F) for quenched and tempered plate. The heat cambering article explains the patterns.

Heavy rolled shapes and cover plates

Not every transfer girder is a plate girder. Heavy rolled shapes, sometimes with cover plates, are also used. For these, Design Guide 36 advises:

  • camber a rolled wide flange by mechanical or heat cambering, depending on the fabricator's equipment capacity;
  • if cover plates are added, camber the rolled shape before welding the cover plates, so that the plates follow the cambered beam and the welds are not fighting a press.

Heavy shapes are often beyond the capacity of a typical shop press, which is one reason deep transfer members are so often built up from plate.

The cost-effective alternative: no camber at all

For transfer girders in particular, the guide offers an option that surprises some designers: detail the girder without camber and adjust the elevations of what sits on it instead. If the expected deflection of a transfer girder is known, the columns it supports can be detailed slightly longer, and the floor beam connections set slightly higher, so that each floor arrives at the right elevation after the girder deflects. The girder itself stays straight, which simplifies fabrication, fit-up and inspection.

This only works when the deflection is predictable and the sequence of loading is known, which is why it needs the Engineer of Record's direction. The transfer girder camber article covers the staged loading in detail.

Crane girders: the exception

Built-up members that carry cranes are treated differently. Design Guide 36 recommends that crane girders not be cambered at all; they should be sized with enough stiffness for the crane design requirements in AISC Design Guide 7. Where a crane girder is built from a wide flange with a cap channel, the welding of the channel tends to pull the girder into negative camber, which must be corrected so the runway is not low at midspan. The AIST TR-13 crane girder articles cover crane girder deflection limits.

Box girders and nonsymmetric sections

Box girders are cambered the same way as I-girders: both webs are cut to the camber profile. Members that are not symmetric about their vertical axis are another matter. Design Guide 36 warns that trying to camber a section that is unsymmetric about the y-axis tends to twist or warp it, and recommends against it. Sections unsymmetric about the x-axis, such as a girder with unequal flanges, can be cambered but may not fit a press, so cutting the web or using heat is the usual route.

What to show on the drawings

For a cambered plate girder, the fabricator needs:

  • the camber at midspan and the profile, or ordinates at stated points;
  • whether the camber is for steel self-weight only or a stated dead load;
  • the bearing and splice locations, so field splices fall at the right ordinates;
  • any limits on heat correction the engineer wants to impose.

For girders shipped in pieces and spliced in the field, each piece is cut and checked to its share of the camber diagram in the shop.

Splices and shipping lengths

Long cambered girders are often too long to ship in one piece. Field splices are placed at points the engineer accepts, and each shipping piece is cut to its part of the camber profile. At a bolted splice, the splice plates are drilled to the sloped geometry so the pieces meet at the right angle; at a welded splice, the joint preparation follows it. The camber of the assembled girder is confirmed by a shop trial assembly or by checking each piece and the splice geometry separately.

Inspection points for cambered girders

A cambered plate girder is typically checked at several stages: the cut web profile against the cutting file, the fit-up before welding, the camber and sweep after welding, and the final dimensions after any correction. Recording each stage on the inspection report shows not only that the girder met its tolerance, but also how it got there, which is useful if a similar girder later behaves differently.

How World Steel makes cambered plate girders

World Steel fabricates 2,500 metric tons of structural steel a month in its own IAS AC472-accredited plant in Vietnam, and welded plate girders are one of our core built-up products. The camber profile goes from the Tekla model straight into the cutting files for our CNC laser cutting machines, which cut plate up to 100 mm thick.

Flanges are fitted to the shaped web and welded by submerged arc at our fitting and welding station, with a welding sequence chosen to hold the curve. Camber is then measured on supports, recorded by piece mark, and corrected within the AISC 360 heat limits if needed. Built-up girders of this kind carried the heavy loads of the Sunpro Steel mill and the 2,000-metric-ton Long Son petrochemical complex, and shaped webs formed the curved rafters of the Goldfields Arts Centre.

Next in the series: how much camber a composite beam should get.

Quick answers

How is camber put into a welded plate girder?

The web plate is cut with its top and bottom edges following the camber curve, then the flanges are fitted to the shaped edges and welded. The girder comes out cambered without bending or heating.

Can welding change the camber of a plate girder?

Yes. Shrinkage of the flange-to-web welds pulls the girder. Welding the bottom flange first tends to add camber, so the welding sequence is planned to hold the curve, and camber is checked after welding.

What if the camber is slightly off after welding?

Small corrections are usually made with controlled heat, within the AISC 360 Section M2.1 temperature limit.

Should cover plates be added before or after cambering a rolled beam?

After. Design Guide 36 recommends cambering a rolled wide flange before welding cover plates to it.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

Steel beam camber series

Twenty in-depth articles built on AISC Design Guide 36: what camber is, how a shop puts it into rolled beams and welded girders, how much a composite floor beam should get, which members should stay straight, and how camber is specified, measured and accepted under the AISC Code of Standard Practice.

Camber basics

What camber is, the mill bow every rolled shape has, and the alternatives.

Making camber

Presses, torches, the strain involved, camber loss and cambered plate girders.

Composite floors

How much to camber, what changes deflection, and how the concrete goes on.

Special members

Roofs, transfer girders, cantilevers, trusses, joists and members to keep straight.

Specify and accept

The AISC 303 tolerance, shop measurement and what the drawings should say.

Bidding a large US project?

Send the bid documents, or just a footprint and an address. Our engineers check them against US code requirements and confirm what World Steel would supply, from a plant that fabricates 2,500 metric tons of structural steel a month.