Natural mill camber: the ASTM A6 straightness allowance on rolled beams

No rolled beam is perfectly straight. ASTM A6 allows a small out-of-straightness that the industry calls natural or mill camber. Here is how large it can be, why it is turned upward, and why it stops mattering once the engineer specifies a camber.

· 6 min read · World Steel USA engineering team

The word camber appears in two different places in a US steel job. The engineer uses it for a curve that is designed and specified. ASTM A6/A6M uses it for something that nobody designed at all: the small bow a rolled shape keeps after it leaves the mill. The industry calls that second kind natural mill camber, and it helps to understand it before looking at the specified kind.

This article draws on AISC Design Guide 36 (2020), Sections 1.2 and 3.1, and on ASTM A6/A6M. The values are a selection; the editions named in your project specification govern.

How a wide flange gets its bow

A wide flange begins as a near-shape casting, often a "dog bone" with thickened edges where the flanges will be. The casting is reheated and passed through rolling stands that press it step by step into the final cross section. When it leaves the last stand it is long, hot and cooling unevenly: flange tips cool faster than the junction of flange and web, and thin parts cool faster than thick ones.

That uneven cooling leaves residual stresses locked in the section and pulls the shape out of line. Mills therefore straighten every shape after cooling, usually in a roller straightener and sometimes with a gagging press. The aim is not a perfectly straight bar, which is not achievable, but a shape that sits inside the out-of-straightness tolerance of ASTM A6/A6M.

The ASTM A6 limit

For most wide flange shapes, ASTM A6/A6M allows a maximum camber of about 3 mm for each 3 m of length, which in the inch-pound form of the specification is 1/8 in times the length in feet divided by ten. A 9 m (30 ft) beam may therefore leave the mill up to roughly 10 mm (3/8 in) out of straight about its strong axis and still be a perfectly good A6 product. Shapes ordered for use as columns can carry tighter limits, and sweep about the weak axis has its own values in the same tables.

Three details about this tolerance surprise people:

  • The peak can be anywhere. The largest deviation from a straight line does not have to sit at midspan. It can be near one end.
  • The shape can be irregular. A beam can have more than one slope along its length rather than one smooth bow.
  • The bow can change sides. One part of the beam can deviate upward and another part downward, a mild reverse curve.

As long as the whole profile stays inside the tolerance envelope, all three are acceptable. Design Guide 36 notes that most shapes are delivered with less natural camber than the maximum.

Why the bow is turned upward

If a beam has no specified camber, the fabricator still has to decide which flange becomes the top. The rule is simple: look at the predominant direction of the bow and make that the top, so any natural camber points up.

The reason is practical. An upward bow of a few millimetres is cancelled by the self-weight of the steel, the deck and the slab. A downward bow adds to the deflection the engineer calculated, and a floor that was meant to deflect 20 mm may end up 30 mm low. ASCE 7 Appendix C, Section C.4 and the AISC Code of Standard Practice both say that beams detailed without specified camber should be positioned so that any minor camber is upward.

In a shop with an automatic beam line, the orientation is decided at intake, before holes are drilled, because the hole pattern fixes which flange is the top. That is one reason we look along each shape at the material intake station rather than only reading its certificate.

When natural camber stops mattering

The moment an engineer specifies camber for a member, the natural bow becomes irrelevant. The fabricator puts the beam in a press, or heats it, and imposes a new curve that is many times larger than the A6 allowance. Whatever small deviation was there before is superseded by the induced shape, and the member is measured against the specified camber and the tolerance of the AISC Code of Standard Practice, not against ASTM A6.

For the designer this means two things:

  • For uncambered beams, natural camber can be neglected in design, provided it is oriented upward.
  • For cambered beams, the specified value is what counts, and the mill bow does not need to be added or subtracted.

Mill camber versus mill-cambered beams

A second meaning of "mill camber" survives from the past. Before shop presses were common, US mills offered cold cambering as an extra on the purchase order. The mill loaded the beam with a gagging press at points along its length until it took a permanent set. Early AISC specifications even said that camber in rolled beams over a certain depth should be only what the mill offered.

Ordering cambered beams from the mill had drawbacks. It tied the camber to the mill rolling schedule, and older AISC manuals warned that some of the camber might be lost in shipment, suggesting that only about three quarters of it could be counted on. Design Guide 36 reviews that warning and finds no evidence for real loss in handling, as explained in the camber loss article. Today nearly all specified camber is put in by the fabricator.

Natural camber and tolerances on site

Natural camber within ASTM A6 is accepted as delivered. It is not "corrected" in the shop unless the member has to meet a tighter tolerance than A6 provides, for example a column with a special straightness limit or an architecturally exposed member. When a tighter limit is needed, it belongs in the project specification, because the default for rolled shapes is the A6 tolerance.

On the jobsite the erector sees natural camber as a small rise in uncambered beams. Since it is upward and small, it disappears under the deck and slab. Problems arise only when a beam is set upside down, which is why the top flange of each piece is marked and the erection drawings show its orientation.

Natural camber in built-up and welded members

Built-up members such as welded plate girders do not have a mill camber in this sense. Their straightness depends on how the plates are cut and how the welds pull as they cool. The fabricator controls it with welding sequence, fixtures and straightening, and the AISC Code of Standard Practice sets the straightness tolerance of the finished member. When a welded girder needs camber, the camber is usually cut into the web plate, as described in the cambered plate girders article.

What to write in the specification

For most projects nothing special is needed: rolled shapes to ASTM A6 straightness, beams without specified camber erected with natural camber up, and specified camber shown per member on the drawings. Add a note only when:

  • a member needs straightness tighter than ASTM A6;
  • exposed steel has an appearance requirement;
  • a beam must be delivered with no camber, for example because a façade or equipment is attached before the slab is poured.

A quick check at intake

A simple intake check is enough: lay the shape on supports, look along it, and run a line if the bow seems large. A shape outside the A6 tolerance is set aside for straightening or returned, before it reaches drilling.

How World Steel deals with natural mill camber

World Steel fabricates 2,500 metric tons of structural steel a month in its IAS AC472-accredited plant in Vietnam. Rolled shapes are bought to the ASTM specification on your drawings, mainly from Vietnamese mills, and each one is checked at intake against its EN 10204 3.1 certificate and the ASTM A6 dimension and straightness tables.

For uncambered beams, the top flange is chosen so any natural camber is upward before the shape goes to the automatic beam line. For beams your Engineer of Record cambers, the specified value is produced in the shop and measured at straightening and dimensional control. Intake on this scale is routine for us: the 5,000 metric tons of the Sunpro Steel mill passed through the same yard, heat by heat and shape by shape.

Next in the series: camber vs shoring and stiffer beams.

Quick answers

How much natural camber does ASTM A6 allow in a wide flange beam?

For most wide flange shapes, about 3 mm for every 3 m of length (1/8 in per 10 ft), measured as the maximum deviation from a straight line. Some shapes ordered as columns have tighter limits.

Which way should natural camber face?

Up. The AISC Code of Standard Practice asks that beams without specified camber be fabricated and erected with any natural camber upward, and ASCE 7 Appendix C says the same.

Does mill camber count toward the specified camber?

No. When the engineer specifies camber, the fabricator cambers the beam to that value and the original out-of-straightness is superseded by the new curve.

Can natural camber be in the middle of the beam only?

Not necessarily. The largest deviation can be anywhere along the length, the beam can have several slopes, and the deviation can even change sides. All of that is acceptable inside the tolerance envelope.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

Steel beam camber series

Twenty in-depth articles built on AISC Design Guide 36: what camber is, how a shop puts it into rolled beams and welded girders, how much a composite floor beam should get, which members should stay straight, and how camber is specified, measured and accepted under the AISC Code of Standard Practice.

Camber basics

What camber is, the mill bow every rolled shape has, and the alternatives.

Making camber

Presses, torches, the strain involved, camber loss and cambered plate girders.

Composite floors

How much to camber, what changes deflection, and how the concrete goes on.

Special members

Roofs, transfer girders, cantilevers, trusses, joists and members to keep straight.

Specify and accept

The AISC 303 tolerance, shop measurement and what the drawings should say.