Beams get camber by being bent. Trusses get it by geometry. A truss is built from straight pieces joined at panel points, so its camber is set by locating those panel points on a curve and cutting every member to fit. AISC Design Guide 36 (2020), Sections 5.4 and 5.5 describe how truss camber and joist camber are specified and checked. This article summarizes both.
How much camber a truss gets
Trusses are so varied, from light roof trusses to transfer trusses carrying floors, that Design Guide 36 does not prescribe one method. The amount is a serviceability decision: camber for dead load only, or for dead load plus part or all of the live load. Analysis software makes truss deflection easy to compute, but the result still depends on assumptions about connection stiffness, support restraint and actual loads, so the camber is a design approximation.
Where camber is required, the camber diagram is usually a parabolic curve, specified by its ordinates at the panel points.
Making the camber
How the camber is built in depends on the chord type.
Wide flange chords. On heavy trusses with W-shape chords, the chords are fabricated as straight members. They are sloped between splices at the camber points so the chord line follows the curve as a series of chords. The diagonals and verticals are cut to the lengths that match the sloped geometry. No member is bent.
WT, angle and HSS chords. Lighter shop-welded trusses can have their chords curved to the camber, either with heat or by jacking the chord into a fixture to the required curve. Double-angle diagonals are adjusted in length during fit-up.
HSS trusses with direct-welded webs. When HSS web members are welded directly to HSS chords, Design Guide 36 recommends specifying gapped joints rather than overlapped ones at cambered trusses. The gap gives the fabricator room to adjust each web member to the cambered chord. Overlapped joints lock the geometry and leave no room.
The shop tolerance
AISC Code of Standard Practice Section 6.4.5 covers shop-assembled trusses. In plain terms:
- for trusses specified with camber, the camber at each specified camber point may vary by plus or minus 1/800 of the distance from that point to the nearest support;
- camber is measured in the fabricator's shop, in the unstressed condition;
- for trusses specified without camber, the same limit applies at each panel point with a zero camber ordinate.
On a 30 m (100 ft) truss, the midspan point is 15 m from the nearest support, so the tolerance there is about plus or minus 19 mm (3/4 in). Near the supports it is much smaller.
Trusses that are not shop assembled
Section 6.4.5 assumes the truss is assembled in the shop, where fit-up and camber can be checked. Modern practice often skips full shop assembly on large trusses: members are cut and drilled from the 3D model on CNC equipment, connections are slip-critical bolted, and the truss is first assembled on site. Design Guide 36 describes three ways those trusses are checked, following AISC Code of Standard Practice Section 7.13.1.2:
- Field assembled, unstressed. The truss is laid down or fully shored and assembled in the unstressed condition. The same tolerances apply as if shop assembled. This is typical when there is space on site.
- Field assembled, supported. The truss is assembled in its stressed position in special fixtures. Used when space is tight or when many identical trusses justify the fixtures.
- Assembled element by element in place. Temporary support or an alternative erection plan is required, submitted to the owner's designated representatives, and the tolerance of Section 7.13.1.2(d), 1/500 of the distance between working points, is met in the supported condition with working points at the temporary supports.
Trusses fabricated in sections and spliced in the field have each section checked in the shop and the camber checked again when spliced.
Shop trial assembly
For complex or long trusses, a full or partial trial assembly in the shop remains the most direct check: the truss is laid out on supports, bolted up, and the camber at each panel point measured against the diagram. It also confirms fit-up of every connection before shipping. On long-span roofs and bridges, owners often require it.
Steel joists and joist girders
Open web steel joists and joist girders produced to the Steel Joist Institute standard specification come with a standard camber unless the specifier says otherwise. Up to spans of about 30 m (100 ft), the standard camber follows a radius of roughly 1,100 m (3,600 ft); beyond that it is about span/300. As examples from the SJI table, a joist about 12 m (40 ft) long gets roughly 16 mm (5/8 in), and one about 30 m (100 ft) long roughly 108 mm (4-1/4 in).
The camber is built in on the rigging table as the chords and webs are placed. Once the joist is erected, its self-weight and other dead load start to pull it down, so the camber measured in place is less than on the table.
Coordinate it. SJI's own user note warns that the standard camber needs coordinating where joists meet adjacent framing or a wall at a fixed elevation. Steel deck is often designed for three spans, so elevations may need to transition. For double-pitched joists with steep top chords, more than about 1 in 6, or arched top chords, it may be better to specify no camber where elevations must match.
Composite joists. SJI's practice for CJ-series composite joists is camber for 100% of the non-composite dead load, the joist, bridging, deck and slab, with the slab placed to uniform thickness, so the floor is about level after the pour. Joist bearings act as pins with little restraint, which is why full camber works here when it rarely does for beams. If the designer wants a level floor after composite loads, extra camber can be specified.
Checking truss camber in practice
Measuring a truss is different from measuring a beam. The truss is laid on supports at its bearing points in the unstressed condition, usually on its side for shop assembly or upright in a fixture. A taut line or an optical level is set between the bearing points, and the offset of each specified camber point on the bottom chord, or the working line, is measured and compared with the camber diagram.
Because the tolerance is proportional to the distance to the nearest support, it is tight near the bearings and wider toward midspan. A useful record lists each panel point, its specified ordinate, the measured ordinate and the allowed variation. For trusses shipped in sections, each section is checked against its part of the diagram, and the splice geometry is checked so the sections line up in the field.
Truss camber and connected framing
Truss camber affects what sits on the truss. Purlins, deck and roof slope follow the top chord, so a cambered roof truss changes the roof profile, which must still drain. Floor framing on a transfer truss sees the truss deflect as floors are added, as with a transfer girder. Hangers from the bottom chord move with it. These interactions should be noted on the drawings so the trades that connect to the truss know whether its camber will remain or disappear under load.
Joists from a different supplier
On many US projects joists and joist girders come from a joist manufacturer while the structural steel comes from the fabricator. Where both meet, at joist girder seats on columns or joists bearing on steel beams, the joist camber and the beam camber both affect the deck elevation. The design documents should state whether standard joist camber applies, so the steel detailer can set seat elevations to suit.
How World Steel fabricates cambered trusses
World Steel fabricates 2,500 metric tons of structural steel a month in its own IAS AC472-accredited plant in Vietnam, including steel trusses for long-span roofs, transfer levels and arched roof truss frames. Panel point ordinates from the camber diagram are set in the Tekla model, so chord slopes and web member lengths come out of the CNC cutting files already matching the curve.
Trusses are fitted in fixtures at our fitting and welding station, and camber at each specified point is measured in the unstressed condition against the 1/800 tolerance before release; trial assembly is arranged where the project calls for it. Trial assembly is part of our practice on demanding jobs, such as the CP4 bridge in Singapore, and our trusses span the roofs of projects from the Goldfields Arts Centre to the Sunpro Steel mill.
Next in the series: when not to camber.
Quick answers
What is the shop tolerance for truss camber?
Under AISC Code of Standard Practice Section 6.4.5, camber at each specified camber point may vary by plus or minus 1/800 of the distance from that point to the nearest support, measured in the shop in the unstressed condition.
How is camber produced in a truss with wide flange chords?
The chords are made as straight pieces and sloped between splices at the camber points to follow the camber diagram, and the diagonals are cut to the lengths that match.
Why specify gapped joints on cambered HSS trusses?
A gap between web members at a chord connection gives the fabricator room to adjust web member lengths during fit-up to match the cambered chord.
Do steel joists come cambered?
Yes. Joists and joist girders made to SJI specifications have a standard camber unless the specifier says otherwise, roughly based on a 1,100 m (3,600 ft) radius up to 30 m (100 ft) spans and span/300 beyond.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors