Every member in a floor is checked against a deflection limit measured between its own supports. That is right for strength and for the member's own serviceability. It is not the whole story for a level floor. AISC Design Guide 36 (2020), Section 4.3.1 calls the missing piece compounded deflection: the floor at the middle of a bay drops by the beam's sag plus the sag of the girders the beam sits on.
A typical bay
A standard bay has columns at the corners, girders spanning between columns along two sides, and beams spanning between the girders, often at equal spacing. Beams and girders are usually designed as simple spans unless they are part of the lateral system.
When a beam is checked, its ends are assumed fixed in elevation. But the ends rest on girders, and when the girders carry the beam reactions, they deflect. The beam's ends drop with them. The point at the middle of the bay therefore drops by:
- the girder deflection at the beam's connection; plus
- the beam's own deflection relative to its ends.
If the girder deflects 20 mm at midspan under the wet concrete and the beam deflects 30 mm, the center of the bay drops roughly 50 mm before any camber is considered.
Why camber alone does not fix it
Cambering the beams offsets their own deflection. It does nothing for the girders unless the girders are cambered too. A floor with cambered beams on uncambered girders will still sag in a shallow dish whose low point is the middle of each bay. With constant thickness placement, the floor follows that dish. With constant elevation placement, the dish fills with concrete.
The ponding cycle
Design Guide 36 notes that when concrete is struck to a level elevation, the extra concrete corresponds to the total floor displacement across the bay, not just to the beam sag. That extra concrete is load, and it causes more deflection, which draws more concrete, and so on. It is the same mechanism as water ponding on a flat roof.
The guide refers to an analytical approach that treats the added concrete with a ponding analogy to estimate the quantity needed for a level floor. The method converges for normal floors, but it shows two things clearly:
- the extra concrete is larger than a beam-only estimate suggests;
- stiff girders reduce it more effectively than extra beam camber.
Cambering girders
On long girders carrying heavy beam reactions, camber is often specified for the girder as well. The same principles apply:
- calculate the girder's precomposite deflection under the beam reactions, including the wet concrete each beam carries;
- offset a judged share of it, usually less than 100%, for the same reasons as beams: restraint, plus tolerance and the cost of over-cambering;
- remember that a girder framing to columns has stiff supports and some restraint;
- consider how deck continuity shifts load among the beams along the girder.
Girders that are part of a moment frame or braced frame should not be cambered, because their end connections need square ends.
Heavy girders may exceed the capacity of a typical cambering press. Built-up girders can have their camber cut into the web, as described in the cambered plate girders article.
Framing layout and stiffness changes
Section 4.3.2 of the guide adds a related caution. Abrupt changes in framing or stiffness between adjacent members can cause constructability problems before any load is applied. A cambered beam stands higher at midspan than an uncambered member or a wall beside it. The deck has to span between them, and if the difference is large, or the deck depends on multi-span installation, it may not bear properly on the lower member.
Typical places to look:
- a cambered beam parallel to a bearing wall or a concrete core;
- beams beside a column line framed with uncambered members;
- a bay where beam spacing or span changes suddenly;
- infill framing around stairs and shafts.
Remedies include a single span of deck warped at its bearing for small differences, or an added beam with about half the typical camber to step down the elevation.
A worked way of thinking
When setting camber for a bay, a designer can ask four questions:
- What is the girder deflection under wet concrete at each beam connection?
- What is each beam's deflection relative to its ends?
- What total drop does that give at the middle of the bay, and is it acceptable for the placement method?
- Is it cheaper to camber the girder, stiffen it, or accept extra concrete?
The answers change with the bay. On a long-span office floor with deep girders, girder camber is usually worth it. On short bays with stiff girders, beam camber alone may be enough.
What it means for the contractor
The contractor pricing concrete needs to know the expected bay displacement, not just beam cambers. The design documents should say whether girders are cambered, what the expected net deflection is, and whether extra concrete is anticipated. A survey of the erected steel before the first pour shows the actual top-of-steel profile across a bay, which helps the placement crew. The floor levelness article covers the surveys.
A numerical example
Take a bay 12 m (40 ft) by 9 m (30 ft). Beams span 12 m between two girders, at 3 m (10 ft) centers, so each girder carries two beam reactions near its third points. The girders span 9 m between columns.
Under wet concrete, suppose the calculations give:
- each beam: 35 mm of precomposite deflection relative to its ends;
- each girder: 15 mm at the points where the beams frame in.
The middle of the bay therefore drops about 50 mm. If the beams are cambered for 80% of their own deflection, about 28 mm, they finish roughly 7 mm low relative to their ends. But their ends are themselves 15 mm low, so the center of the bay finishes about 22 mm below the column elevation.
With constant elevation placement, that 22 mm dish fills with concrete. Over a bay of more than 100 m² (1,200 sq ft), even an average of 10 mm of extra depth is more than a cubic metre of concrete per bay, and it adds weight that deepens the dish a little further. Across a floor plate of 30 bays and ten floors, the extra concrete becomes a line item in the bid.
If the girders are also cambered for most of their 15 mm, the bay dish shrinks to the beams' small net sag, and the extra concrete falls sharply. The question for the design team is whether girder camber is practical, or whether a slightly heavier girder is simpler.
Beams framing into beams
Compounding is not limited to beams on girders. Infill beams around stairs and shafts often frame into other beams, which frame into girders. Each level adds its own deflection. Where three members stack, the low point of a small infill area can sit well below what any single member check suggests. These areas deserve their own deflection check and, often, stiffer members instead of camber, because short infill beams are hard to camber anyway.
Checklist for a bay
When reviewing a cambered floor, a useful habit is to add up the deflections along one line from a column to the center of the bay: girder at the beam connection, beam at midspan, minus the camber of each. If the total is close to the net sag the placement method expects, the bay is consistent. If it is much larger, the girders are probably the missing piece, and either girder camber or a stiffer girder should be considered before the drawings are issued. The same check, repeated for a typical bay and an edge bay, catches most surprises.
How World Steel handles beams on girders
World Steel fabricates 2,500 metric tons of structural steel a month in its own IAS AC472-accredited plant in Vietnam. On multi-story steel framing packages, our engineers check beam and girder deflections together in the floor model and show both in the calculations prepared for your Engineer of Record, including the girders proposed for camber.
Rolled girders within press capacity are cambered in the shop. Heavier welded plate girders are cut to their camber profile on our CNC laser cutting line and measured after welding. Large floor plates are routine for the plant: the Tongwei Tien Giang feed mill, about 1,500 metric tons in phase one, is one example among our multi-storey projects.
Next in the series: floor levelness on cambered steel.
Quick answers
What is compounded deflection?
The total drop of a point on the floor, found by adding a beam's deflection relative to its supports to the deflection of the girders those supports sit on.
Why does compounded deflection matter for camber?
With a level screed, the extra concrete fills the total floor displacement, not just the beam sag. Ignoring girder deflection underestimates the extra concrete and its weight.
Should girders be cambered too?
Often yes, when they are long and carry heavy beam reactions. Their camber is chosen on the same principles as beams, and the beams framing into them are cambered relative to the girder ends.
How is the extra concrete estimated?
Design Guide 36 points to a ponding analogy: the added concrete is treated like ponded water whose weight causes more deflection, solved for the whole bay.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors
- Solutions by stateState-by-state steel solutions