Engineering and codes

Cold cambering: how a hydraulic press puts camber in a rolled beam

Almost all specified camber in US floor beams is put in cold, by a hydraulic press that yields a short length of the beam. This article walks through the machine, the limits on length, size and web thickness, and the details designers can change to make cambering easy.

· 6 min read · World Steel USA engineering team

Ask a US fabricator how a floor beam gets its camber and the answer will almost always be "in the press". Cold cambering, also called mechanical cambering, loads a rolled beam at room temperature until a short length of it yields, then releases the load. The yielded zone keeps a small permanent bend and the beam comes out with an upward curve. AISC 360 Section M2.1 permits camber to be introduced this way, and AISC Design Guide 36 (2020), Section 3.2 describes how it is done in practice.

A short history of cambering presses

The earliest US cambered beams came from the mills, which used gagging presses to load the beam at single points. Older AISC specifications limited cambered rolled beams to what the mills offered, and mills limited it to deeper sections and refused reverse or compound curves. When composite design entered the AISC Specification in 1961, demand for cambered beams rose and fabricators began to buy their own presses.

Those first shop presses copied the mill idea: a heavy frame with one large ram halfway between two reactions. The beam yielded in a short plastic hinge at the ram, so the strain was concentrated and the operator had to move the beam and press at several points to build a smooth curve. Ram capacity limited the beam size.

In 1984 a Houston fabrication engineer patented a press with two rams at roughly the third points between the reactions. Loading at two points spread the yielding over the length between the rams, gave a smoother curve with lower strain, and increased the bending capacity of the machine. Double-ram presses of this type are now the standard in US shops.

How a double-ram press works

A typical double-ram machine has:

  • two reaction points about 6 to 7.3 m (20 to 24 ft) apart;
  • two rams between them, spaced roughly 1.8 to 2.4 m (6 to 8 ft) apart;
  • restraints at the load points to stop the beam from twisting or buckling sideways;
  • roller conveyors to feed the beam in and position it.

The beam lies with its web vertical and the rams push on the top flange. Some overhang beyond each reaction is needed so the beam is held securely in the frame. As the rams advance, the portion between them yields and the outer lengths stay straight. Because of the geometry, the camber of a typical beam is concentrated in the middle quarter to third of its length, while the tangent lengths toward the ends stay straight. The shape is close to the parabola of the theoretical deflection curve.

Single-press machines also exist and can handle varying lengths. They produce a more segmented curve, with higher strain at each load point, which the operator reduces by pressing at more points.

Trial and error at the press

Cold cambering is a judgment process. The operator advances the rams a trial distance, releases them, and checks the permanent set. If the camber is short, the beam is pressed again at the same or a new position. If it is over, the beam can be turned and pressed back, or the excess can be removed with heat. An older paper warned against reversing a beam in the press, but Design Guide 36 finds no basis for that restriction when strains stay on the lower part of the yield plateau.

Camber is usually measured with a string line and tape. Design Guide 36 puts the accuracy of that measurement at about plus or minus 3 mm (1/8 in). The result is recorded to show the beam meets the tolerance. The camber tolerance article covers the measurement in detail.

Limits on length, size and web

Three limits come from the machine and the physics.

Length. With reactions 6 m or more apart and overhang needed beyond them, short beams cannot sit in the press. Design Guide 36 recommends not specifying camber on members shorter than about 7.6 m (25 ft) without checking the equipment of local fabricators. Heat cambering can do short members, but it costs more; the guide's rule of thumb is that heat cambering a 6 m (20 ft) beam costs about as much as adding 15 kg per metre (10 lb/ft) to its weight, so a heavier beam is often cheaper.

Section size. Presses exist that can camber very heavy shapes, up to around W920 × 446 (W36 × 300). But machines in most shops are sized for beams up to roughly W610 × 125 (W24 × 84). Larger cambered beams may have to go to a specialist bender or be heat cambered.

Web thickness. The rams push hard on the flange right above the web. A thin web can cripple under that concentrated force combined with the bending. Design Guide 36 recommends not cold cambering beams with webs thinner than about 6 mm (1/4 in); for those, a heavier beam or heat cambering is the better option. Double-ram machines need less force than single-ram ones and are less prone to crippling, but very thin webs remain a risk.

Holes and the tension flange

A cambered beam is bent the opposite way to the way gravity will bend it. The middle is pushed up relative to the ends, so the flange on the outside of the curve, the top flange in service, is stretched past yield in the middle portion, while the bottom flange is compressed. The yielded zone is short, but it is where the strain is highest.

That matters for holes. A bolt hole in the top flange near midspan sits in the zone of highest plastic tensile strain. The net section at the hole concentrates the strain and can crack. Design Guide 36 shows examples of such net-section fractures and recommends:

  • avoid holes in the top flange in the middle third of a beam to be cambered;
  • where holes are needed there, make them after cambering;
  • if a CNC line drills them before cambering, inspect the holes carefully afterward for any sign of cracking.

Holes in the web and at the beam ends, where the strain stays elastic, are normally made before cambering, which suits the automated drilling of modern beam lines.

The sloped end connection

A cambered beam no longer has vertical ends. The end of the beam rotates by a small angle, and the connection holes rotate with it. On long beams with large camber, the shift across the depth of a deep connection can be several millimetres. Design Guide 36 observes that in the shop the top flange tends to strain slightly more than the bottom one in a double-ram press, which adds to the slope.

Simple shear connections absorb that slope through short-slotted holes or the flexibility of angles. Moment connections, brace connections and connections that restrain torsion cannot, which is one reason beams with those connections should not be cambered.

What designers can do to help

  • Show camber only where it saves real steel, and not below about 19 mm (3/4 in).
  • Keep cambered beams at 7.6 m (25 ft) or longer and with webs of at least 6 mm (1/4 in).
  • Keep top flange holes, and any flange penetrations, out of the middle third.
  • Use simple shear connections with short slots or flexible angles at cambered beam ends.
  • Ask early which section sizes the fabricator's press can handle, especially for deep or heavy beams.

Cold cambering and coatings

Cambering is normally done before blasting and painting, so the coating is applied to the final shape and the strained zone is not cracked or flaked. Where a member is cambered after priming, the coating in the yielded zone is inspected and touched up.

How World Steel cold cambers rolled beams

World Steel fabricates 2,500 metric tons of structural steel a month in its own IAS AC472-accredited plant in Vietnam. Rolled floor beams for composite floor support steel are processed on the automatic beam line, then cambered in the shop where your Engineer of Record specifies camber.

Before cutting, our detailers check each cambered beam against the points above and raise a question if a top flange hole falls in the middle third, if a beam is short or has a thin web, or if an end connection will not tolerate the slope. After cambering, the value is measured on supports and logged against the piece mark. Rolled beams for floors such as the Tongwei Tien Giang feed mill, about 1,500 metric tons in its first phase, went through the same beam line, the same detailing checks and the same dimensional release.

Next in the series: heat cambering.

Quick answers

What is cold cambering?

Cambering a beam at room temperature by loading it in a hydraulic press until a short length yields and the beam keeps a permanent upward curve when the load is released.

What is the shortest beam that can be cold cambered?

Design Guide 36 recommends not specifying camber on beams shorter than about 7.6 m (25 ft) without first checking the local shop equipment, because the press needs reaction points several metres apart plus some overhang.

Why should flange holes be kept out of the middle of a cambered beam?

The tension flange in the middle portion is strained past yield during cambering. A hole there concentrates strain on the net section and can crack. Holes in that zone are best made after cambering or avoided.

Does cold cambering change the steel properties?

Not meaningfully. Typical cambers strain the steel only slightly beyond yield, far below the strain hardening range, so the steel unloads with properties close to the original.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

Steel beam camber series

Twenty in-depth articles built on AISC Design Guide 36: what camber is, how a shop puts it into rolled beams and welded girders, how much a composite floor beam should get, which members should stay straight, and how camber is specified, measured and accepted under the AISC Code of Standard Practice.

Camber basics

What camber is, the mill bow every rolled shape has, and the alternatives.

Making camber

Presses, torches, the strain involved, camber loss and cambered plate girders.

Composite floors

How much to camber, what changes deflection, and how the concrete goes on.

Special members

Roofs, transfer girders, cantilevers, trusses, joists and members to keep straight.

Specify and accept

The AISC 303 tolerance, shop measurement and what the drawings should say.

Bidding a large US project?

Send the bid documents, or just a footprint and an address. Our engineers check them against US code requirements and confirm what World Steel would supply, from a plant that fabricates 2,500 metric tons of structural steel a month.