Look along the bottom flange of a long floor beam before the concrete goes on and you may see that it is not straight. The middle sits a little higher than the ends. That rise is steel beam camber, and on most US office, hospital, school and parking framing it is there because the structural engineer asked for it.
This series of twenty articles follows camber from the definition to the shop floor, the design office and the jobsite. It is written from AISC Design Guide 36, Design Considerations for Camber, published in 2020, and from the codes that guide refers to. The explanations are our own and the values are a selection; the editions named on your contract documents govern.
A definition in one sentence
Camber is an upward curvature that is put into a horizontal member on purpose, so that when the member carries its design load the deflected shape stays within the limit the engineer has set. In most cases the curve is meant to be cancelled by the weight of the floor or roof, and by the time the building is finished nobody can see it.
That intent matters. Camber is not decoration and it is not a strength feature. A beam with 40 mm of camber is exactly as strong as the same beam delivered straight. What changes is the starting shape. The engineer is trading a little upward curve at the beginning for a flatter floor at the end.
What camber is not
Three ideas are often mixed up with camber, and the series keeps them apart.
Curved members. A rafter bent into an arch, or a beam swept sideways to follow a curved façade, keeps its curve for life. The curvature is large and visible, and the member is designed as a curved member under its own AISC design guide. Camber is small and is expected to go away under load.
Natural mill camber. Every rolled wide flange leaves the mill a little out of straight. ASTM A6/A6M allows that out-of-straightness and calls it camber too. It is a tolerance, not a design value, and it can point up, down or wander along the length. The natural mill camber article covers it.
Preset elevations. The free end of a long cantilever is often set higher than its support so that it deflects down to level. That is a preset elevation set during erection, not camber built into the member, and the AISC Code of Standard Practice treats the two differently.
Unless we say otherwise, "camber" in this series means the specified camber that the engineer of record shows on the drawings and the fabricator produces in the shop.
Why camber became common
Fifty years ago many US floors were framed with heavier beams that simply did not deflect much. Several things changed that.
- Stronger steel. Wide flange shapes moved to 345 MPa (50 ksi) grades such as ASTM A992. The same load can be carried by a lighter section, and a lighter section is more flexible.
- Better design methods. Load and resistance factor design and research on composite action let engineers use more of the strength of a beam. Strength stopped being the limit in many floor beams; deflection took its place.
- Composite floors. With shear studs welded through the metal deck, the hardened slab works with the steel beam and the floor becomes much stiffer. But before the concrete hardens the steel carries the wet concrete alone, and that is when the largest deflection happens.
- Shop equipment. From the 1980s, fabricators could buy hydraulic presses that camber a rolled beam in minutes. Camber stopped being a slow special order from the mill and became a normal shop operation.
The result is a familiar pattern. In a composite floor, serviceability, not strength, usually sets the beam size, and camber is one of the cheapest ways to meet a deflection limit with a lighter beam.
The three options for a composite floor
When the engineer sizes a composite floor beam, there are three broad ways to deal with the weight of wet concrete:
- Size the beam stiff enough that it barely moves under the wet concrete. It works, but it means heavier steel and usually more concrete.
- Camber the beam to offset all or part of the deflection the wet concrete will cause. The steel can be lighter, and the slab ends up close to the intended profile.
- Shore the beam until the concrete is strong enough to act compositely, so that the steel never carries the wet concrete alone. Shoring slows the trades below, needs bracing of the bottom flange, and can crack the slab over the girders when the shores come out.
Design Guide 36 notes that camber has long been recognized as the economical choice over upsizing, and as shop presses became common it overtook shoring on most projects. The camber vs shoring article compares the three in more detail.
Which members get camber
The most common cambered members are composite floor beams spanning roughly 9 to 15 m (30 to 50 ft). Others include:
- non-composite floor and roof beams with heavy dead load;
- transfer girders that pick up columns from several floors;
- welded plate girders on long spans, where the camber is cut into the web;
- trusses, where the camber is set at the panel points;
- open web steel joists, which come with a standard camber unless the specifier says otherwise.
Just as important is the list of members that should not be cambered: beams in moment frames and braced frames, spandrels carrying brittle façades, crane girders, short beams and thin-web beams among them. The when not to camber article explains why.
What the codes say
There is no single US code clause that tells an engineer how much camber to use. The pieces are spread across several documents:
- ASCE 7 Appendix C, Section C.4, a non-mandatory serviceability appendix, says camber needed to bring a loaded member into proper relation with other trades should be shown on the design documents, and that beams without specified camber should be erected with any minor camber upward.
- AISC 360 Section M2.1 permits camber to be introduced by mechanical means or by heat, and limits the temperature of heated areas.
- The AISC Code of Standard Practice (AISC 303) sets the camber tolerance for beams and trusses and asks that camber be shown on the contract documents.
- ASTM A6/A6M sets the natural straightness tolerance of rolled shapes.
Design Guide 36 collects the rest: how camber is made, what affects the actual deflection, and how much of the calculated deflection to offset. Its message is that camber design is part science and part judgment, and that over-cambering can be as harmful as under-cambering.
Why too much camber is a problem
It is tempting to think more camber is safer. It is not. A beam cambered for more than its real dead-load deflection stays arched after the slab is placed. If the concrete is screeded to a level elevation, the slab gets thinner at midspan. That can reduce the fire rating the slab thickness was chosen for, and on thin slabs the heads of the shear studs can end up near or above the surface. The composite beam camber article explains how engineers pick a value that avoids both sag and hump.
How this series is organized
The twenty articles follow a cambered member through its life:
- Basics: what camber is, natural mill camber, and camber against shoring or a stiffer beam.
- Shop methods: cold cambering in a press, heat cambering, the strain involved, camber loss, and cambered plate girders.
- Composite floor design: how much to camber, connection restraint, column lines, concrete placement, compounded deflection and floor levelness.
- Special members: roof beams, transfer girders and cantilevers, trusses and joists, and members that should stay straight.
- Specifying and checking: tolerance and shop measurement, and how to show camber on the drawings.
How World Steel handles steel beam camber
World Steel fabricates 2,500 metric tons of structural steel a month in its own plant in Vietnam, accredited under IAS AC472, and ships it to US projects. Floor beams for multi-story steel framing are cambered in the shop where your engineer specifies camber, and long welded girders get their camber cut into the web profile, as described on the curved and cambered members page.
The camber value comes from your Engineer of Record. We carry it from the design drawings into the shop drawings and the 3D model, camber the member, then measure it on supports and record the reading against the piece mark before release, as on our straightening and dimensional control station. The US contractor, our customer, reviews and approves the shop drawings. The same shop has framed multi-story buildings such as the Tongwei Tien Giang feed mill, about 1,500 metric tons in its first phase, and our own Ho Chi Minh City office; the full list is in our multi-storey projects.
Next in the series: natural mill camber under ASTM A6.
Quick answers
What is camber in a steel beam?
An upward curve built into the beam in the shop so that, once the dead load is applied, the beam settles to a nearly flat shape instead of sagging below level.
Is camber the same as a curved beam?
No. Camber is small and is meant to disappear under load. A curved or arched member keeps its curve in the finished building and is designed as a curved member, which AISC treats in a separate design guide.
Who decides how much camber a beam gets?
The Engineer of Record. The amount is shown for each member on the design drawings or in the model, and the fabricator produces and measures it within the tolerance of the AISC Code of Standard Practice.
Does camber make a beam stronger?
No. Strength comes from the section and the material. Camber only changes the shape the beam starts from, so the deflected shape under load ends up closer to level.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors