Transfer girder camber and cantilever preset: staged loads and free ends

A transfer girder does not see its full dead load until every floor above it is built. A cantilever deflects at a free end that has to land at a set elevation. Both need a different approach from floor beams, and in both cases the best answer is sometimes no camber at all.

· 6 min read · World Steel USA engineering team

Most of this series is about floor beams that receive their dead load in one pour. Two members behave differently. A transfer girder takes its load floor by floor over months. A cantilever has no support at its tip, so its free end must be set where it will finish, not where it starts. AISC Design Guide 36 (2020), Sections 5.2 and 5.3 treat each one. This article covers transfer girder camber and the cantilever preset that usually replaces camber.

What a transfer girder does

A transfer girder picks up one or more columns that cannot continue down to the foundation, often to open a lobby, a ballroom, a parking entrance or a long-span space below. The columns it carries may support many floors. Transfer girders are usually non-composite, heavy members, and engineers typically design them conservatively to limit both dead load and part of the live load deflection.

They are either welded plate girders or heavy rolled shapes, sometimes with cover plates. The transfer girders page shows typical configurations.

The staged loading problem

A floor beam reaches its full precomposite dead load in a single concrete pour. A transfer girder does not. Its dead load arrives as the steel, deck and concrete go in on each floor it supports. The girder deflects a little after each floor, and only after the last floor is complete does it reach its full dead load deflection.

That means the designer has to think about camber in stages:

  • What camber is specified in the shop?
  • How much remains after the first supported floor is placed?
  • How much remains after each floor after that?
  • Where must the concrete elevations of each floor be adjusted to finish level?

Design Guide 36 notes that the designer has to specify the camber expected to remain as each floor is placed and adjust concrete elevations accordingly. In a tall building, that schedule belongs on the drawings, and the contractor's survey of each floor feeds back into it.

Making the camber

How the camber is produced depends on the member type:

  • Welded plate girders. The web plate is cut to the camber curve and the flanges are fitted to it. Camber is checked after welding to confirm fit-up and welding have not changed it. Welding sequence can be used to adjust it, since welding the bottom flange first tends to add camber. Small corrections are made with heat.
  • Rolled wide flanges. Mechanical or heat cambering, depending on the fabricator's equipment. Heavy shapes often exceed typical press capacity.
  • Cover-plated shapes. Camber the rolled shape before welding on the cover plates.

The cambered plate girders article covers the shop process.

The alternative: no camber

Design Guide 36 offers a cost-effective alternative that fabricators may propose: detail the transfer girder without camber and adjust everything that sits on it. If the predicted deflection of the girder at each supported column is known, the supported columns can be detailed slightly longer and the floor beam connections slightly higher, so that after the girder deflects every floor lands at its intended elevation.

This has real advantages:

  • the girder is fabricated, fitted and inspected as a straight member;
  • heavy members avoid cambering they may not fit in a press for;
  • the elevation correction is spread over column lengths, which the shop controls precisely.

It also has a condition: the deflection prediction and the loading sequence must be reliable, and the Engineer of Record must direct the adjusted lengths. It is the same idea used for column shortening in tall buildings.

Cantilevers: set the tip, do not camber the beam

Cantilever beams, and the cantilever ends of continuous beams, are non-composite and must be designed for both dead and live load deflection. They are usually sized stiff enough that camber is not needed. Where a long cantilever would deflect noticeably, the usual approach is a preset elevation: the free end is set higher than its final position so that, as load arrives, it comes down to the intended level.

The AISC Code of Standard Practice, Section 3.1, lists among the information the structural design documents must show the preset elevation requirements, if any, at free ends of cantilevers relative to their fixed-end elevations. The support connection must have enough adjustment for the erector to hold the tip at that preset before the connection is fixed, and the load line should not be released until the cantilever is shored or the connection is complete.

Section 7.13.1.2(e) sets the tolerance at the free end at 1/500 of the distance from the working point. The commentary explains it is checked once the fixed end is stable and before temporary support is removed.

Why not camber a cantilever

Design Guide 36 gives several reasons to avoid cambering cantilevers, particularly those continuous over a support:

  • Reverse curvature. A continuous member with a cantilever needs camber up in the back span and down over the cantilever, a reverse camber. Reverse curves are hard to fabricate and need a much tighter radius than ordinary camber.
  • Heat cost. Such curves usually require heat cambering with many heats, which is expensive. A larger section may cost less.
  • Checking. Where camber is specified on a cantilever of a continuous member, it is checked in the shop against a camber diagram, not in the field by preset elevation.

If deflection of a continuous cantilever is still a concern, the guide suggests cambering the cantilever portion only and avoiding reverse camber.

Typical places these members appear

  • Lobby and podium transfer levels in mixed-use towers.
  • Ballroom and conference spaces in hotels.
  • Long-span entrance canopies and balconies.
  • Equipment platforms cantilevered from columns.

A staged example

Imagine a transfer girder about 15 m (50 ft) long that picks up one column carrying eight floors above a hotel ballroom. Its calculated dead load deflection at the column, once all eight floors and their slabs are complete, is 40 mm. The engineer decides to offset most of it.

  • Shop camber. The girder is cambered for 35 mm at the column location.
  • After the girder's own floor. The girder carries its own floor framing and slab and deflects perhaps 5 mm. The column it supports now sits 30 mm above its final position.
  • After each floor above. Each new floor adds roughly equal load through the column, so the girder drops about 4 mm per floor.
  • At topping out. After eight floors the girder has deflected close to its predicted 40 mm and the column has come down about 5 mm below level, within what the floor finishes can absorb.

Through construction, the supported floors near that column sit high, then gradually settle. The concrete for each floor is placed with that in mind, usually to constant thickness, so a floor placed early does not end up thin when the column later drops. The engineer's schedule tells the contractor how high each floor should be at the time of its pour.

Preset on long cantilever canopies

A long entrance canopy or balcony cantilevered from a column or backspan girder is a typical preset case. The engineer calculates the tip deflection under dead load, the canopy roofing and any hung ceiling, then specifies the tip to be set that much high. The erector holds the tip on a temporary support or a crane line at the preset, completes the support connection, then releases it. The 1/500 tolerance is checked before release.

Documents to expect

For these members, the drawings should carry the camber or preset, the stage at which it is checked, and the person responsible for the field survey.

How World Steel builds transfer girders and cantilevers

World Steel fabricates 2,500 metric tons of structural steel a month in its own IAS AC472-accredited plant in Vietnam. Heavy transfer girders are built up from plate cut up to 100 mm thick on our CNC laser lines, with the camber profile, or the adjusted column lengths your Engineer of Record chooses instead, carried from the model into the cutting files.

For cantilevers, we detail support connections with the adjustment needed to hold the preset elevation and show the preset on the erection drawings for the US contractor, our customer. Heavy built-up members are everyday work in the plant: the Sunpro Steel mill and the Long Son petrochemical complex together called for about 7,000 metric tons of steel, including heavy built-up members.

Next in the series: truss camber and joists.

Quick answers

Why is camber for transfer girders harder than for floor beams?

Because the girder takes its load in stages as each supported floor is built, and the designer has to predict how much camber remains at each stage so floor elevations can be adjusted.

Can a transfer girder be left uncambered?

Yes. Design Guide 36 suggests a cost-effective alternative: detail the girder straight and adjust the supported column lengths and beam connection elevations to the expected deflected shape.

Should cantilever beams be cambered?

Generally no. Design Guide 36 recommends adjustable connections and a preset elevation of the free end, as the AISC Code of Standard Practice provides, instead of camber.

What tolerance applies to a cantilever tip?

The AISC Code of Standard Practice sets a tolerance at the free end of a cantilever of 1/500 of the distance from the working point, evaluated after the fixed end is stable and before temporary support is removed.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

Steel beam camber series

Twenty in-depth articles built on AISC Design Guide 36: what camber is, how a shop puts it into rolled beams and welded girders, how much a composite floor beam should get, which members should stay straight, and how camber is specified, measured and accepted under the AISC Code of Standard Practice.

Camber basics

What camber is, the mill bow every rolled shape has, and the alternatives.

Making camber

Presses, torches, the strain involved, camber loss and cambered plate girders.

Composite floors

How much to camber, what changes deflection, and how the concrete goes on.

Special members

Roofs, transfer girders, cantilevers, trusses, joists and members to keep straight.

Specify and accept

The AISC 303 tolerance, shop measurement and what the drawings should say.

Bidding a large US project?

Send the bid documents, or just a footprint and an address. Our engineers check them against US code requirements and confirm what World Steel would supply, from a plant that fabricates 2,500 metric tons of structural steel a month.