Concrete placement on cambered beams: constant thickness or constant elevation

The same cambered floor can be placed two ways: at a constant slab thickness that follows the steel, or to a constant elevation that fills the dips. Each needs a different camber and a different placement plan. Here is how they compare and what each demands from the designer and the contractor.

· 6 min read · World Steel USA engineering team

Camber is only half of a level floor. The other half is how the concrete goes on. AISC Design Guide 36 (2020) devotes its Appendix A to floor levelness, and its central point is that the camber value and the concrete placement on cambered beams must be chosen together. The two common methods, constant thickness and constant elevation, are both structurally acceptable, but they ask different things of the camber, the drawings and the contractor.

Two ways to strike off a slab

On unshored composite floors, the concrete is struck off either to a uniform thickness or to a uniform elevation.

  • Constant thickness. The screed rides a set distance above the deck. The slab is the same thickness everywhere, and its top surface follows whatever shape the steel takes under the wet concrete.
  • Constant elevation. The screed is set to a fixed elevation, often with a laser. The top surface is level, and the slab is thicker wherever the steel has deflected.

Design Guide 36 notes that practice in the US is mixed: some engineers specify one and some the other. In both, camber offsets part of the structure dead load, so that the theoretical floor elevation is close to level once the concrete is placed, and the remaining deflection allowance is checked against the composite loads.

Constant thickness: let the slab follow the steel

With constant thickness, camber is chosen so that the top of slab is approximately level under the precomposite load. The designer can use a higher camber percentage, up to about 90% of calculated dead load deflection, because the slab thickness is fixed regardless of what the beam does.

Advantages

  • The slab is always the specified thickness, so the fire rating and stud cover are protected.
  • No extra concrete beyond the design thickness.
  • It is usually the most economical method in concrete.
  • It can be designed with a small positive camber to offset later shrinkage deflection.

Limits

  • The finished surface reflects any difference between actual and predicted deflection. Those variations are normally acceptable for standard interior finishes but not for very flat floor requirements.
  • High points at column line beams show if their camber was not reduced.

Adjusting on the job. With adjustable dry-screed guides set to the slab thickness, the contractor can use a survey of the first slabs placed to compensate in similar areas later.

Constant elevation: make the top level

With constant elevation, the aim is a level slab even when the beams deflect differently from the calculation. Design Guide 36 lists the key requirements.

Camber must be less than the actual deflection. If the beam is still arched after placement, the level screed leaves the slab thinner than specified at midspan. That can:

  • reduce the fire rating where slab thickness was set for fire, requiring added fireproofing under the deck;
  • in extreme cases reduce the strength of the composite floor;
  • on thin slabs, leave shear stud heads near or above the finished surface.

Allow for the extra concrete. Where camber is less than the precomposite deflection, the dips fill with concrete, which adds weight and more deflection. The deflection calculation should include this extra concrete, and the contract documents should tell the contractor to expect it so it is in the bid. The quantity depends on the deflection of the whole bay, beams on girders, as the compounded deflection article explains.

Preload before screeding. Beams and girders keep moving as concrete is added. ACI 302.1R, Section 3.3.5, cautions that when a laser or similar instrument sets a uniform strike-off elevation, the frame must be preloaded so deflection takes place first. In practice the whole bay and the adjacent bay need their concrete before screeding, so both the beams and their supporting girder have deflected.

Set the screed to the high point. The screed or laser is set to give the minimum slab thickness over the highest point of deflected steel, usually next to a column. Checking slab depth at key points confirms the beams deflected roughly as expected.

Screed guides and equipment

ACI 302.1R describes three ways to control strike-off: wet-screed guides struck to elevation, dry-screed guides of metal set to elevation, and laser-guided screeding machines. Section 10.3.2 says wet-screed guides should be used only where levelness is not critical. On suspended slabs, retrieving dry-screed guides from both sides of each strip damages the work, so a combination is typical: a dry-screed guide on one side and the edge of the previously placed slab as a wet-screed guide on the other. Self-propelled screeds can be laser guided to elevation or set to gauge off the deck.

Choosing camber for each method

Constant thickness Constant elevation
Typical camber offset Up to about 90% of calculated precomposite dead load deflection About 75 to 85%, lower for thin slabs
Slab thickness Fixed Varies, thinnest at high points
Extra concrete None Yes, include in deflection and bid
Surface Follows the steel Level
Main risk Visible high and low areas Thin slab over arched beams

These ranges come from the designer survey in Design Guide 36. The composite beam camber article explains the reasoning.

Why the choice belongs on the drawings

The engineer picks the camber; the contractor picks the means and methods of placement. If the two are not aligned, the floor fails even when both are done well. Design Guide 36 recommends that the design documents state the intended placement method, the anticipated deflections and any special conditions, and that a preconstruction meeting confirm the plan. The floor levelness article covers the surveys that follow.

A preconstruction meeting agenda

Design Guide 36 recommends a preconstruction meeting before concrete placement. A practical agenda covers:

  • the placement method assumed in design and the camber basis;
  • the predicted precomposite deflection of typical beams, column line beams and girders;
  • whether extra concrete is expected, and roughly how much per bay;
  • the screed system to be used, dry screed, wet screed, laser screed, or a combination;
  • the preloading plan if a constant elevation is used: which bays must carry concrete before strike-off;
  • special conditions, such as beams next to moment frames or chevron-braced bays, where deflection will differ;
  • the survey of erected steel before the first pour and the slab depth checks during it;
  • who decides on changes after the first placement, and how they are communicated.

Surveys before and after the first pour

A top-of-steel survey before placement shows the actual camber of each erected beam and the elevation of its supports. It is not a check of shop camber, which is verified in the shop, but it tells the crew where the steel is high and low today. After the first placement, a survey of the slab and of slab thickness at key points shows whether the beams deflected as predicted. If they deflected less, for example because of more restraint than assumed, the crew can adjust later placements, by raising the screed elevation in constant elevation areas or by adjusting dry-screed guides in constant thickness areas. That feedback loop is what turns a calculated camber into a floor that meets its levelness requirement.

Choosing between the methods

In practice the choice often follows the use of the floor. Offices with raised access floors or carpet usually tolerate the constant thickness method well. Laboratories, data halls and spaces with thin finishes over large areas often justify the extra concrete and care of constant elevation. Parking decks need drainage slopes, which changes the question altogether. Whatever the choice, the camber must be set for it.

How World Steel supports the placement plan

World Steel fabricates 2,500 metric tons of structural steel a month in its own IAS AC472-accredited plant in Vietnam. For composite floor support steel, our framing calculations for your Engineer of Record state the placement method assumed and the precomposite deflection of each beam type, so the contractor's concrete subcontractor can plan screed elevations and extra concrete.

With the steel we deliver a camber record by piece mark. Together with the US contractor's survey of the erected steel, it tells the placement crew where the high points are before the first pour. If you are a US contractor planning a large floor program, our contractor partnership page explains how we work with your team. Our multi-story references, from the Tongwei Tien Giang feed mill to the Haid Vinh Long feed mill, are listed with photos in our multi-storey projects.

Next in the series: compounded deflection.

Quick answers

What is the difference between constant thickness and constant elevation placement?

With constant thickness, the slab is the same thickness everywhere and its top follows the deflected steel. With constant elevation, the top is struck level and the slab is thicker wherever the steel deflects more.

Which method needs more concrete?

Constant elevation, because the dips caused by beam and girder deflection are filled. That extra concrete adds load and should be shown in the contract documents so it is included in the bid.

Why must the bay be preloaded before a laser screed sets the elevation?

Because the beams and girders keep deflecting as concrete is added. ACI 302.1R cautions that the frame must be loaded to allow deflection before strike-off, which means the bay and the adjacent bay must carry their concrete before screeding.

Which method is cheaper?

Constant thickness is usually the most economical in concrete. Constant elevation gives a more level surface but needs extra concrete and more careful placement.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

Steel beam camber series

Twenty in-depth articles built on AISC Design Guide 36: what camber is, how a shop puts it into rolled beams and welded girders, how much a composite floor beam should get, which members should stay straight, and how camber is specified, measured and accepted under the AISC Code of Standard Practice.

Camber basics

What camber is, the mill bow every rolled shape has, and the alternatives.

Making camber

Presses, torches, the strain involved, camber loss and cambered plate girders.

Composite floors

How much to camber, what changes deflection, and how the concrete goes on.

Special members

Roofs, transfer girders, cantilevers, trusses, joists and members to keep straight.

Specify and accept

The AISC 303 tolerance, shop measurement and what the drawings should say.