Steel office frame with composite floor beams before the slab is placed

Engineering and codes

Camber vs shoring vs a stiffer beam: three answers to wet concrete

A composite floor beam carries wet concrete on its own before the slab can help it. Engineers have three ways to deal with that moment: make the beam stiffer, camber it, or shore it. Each one moves cost and risk to a different place.

· 6 min read · World Steel USA engineering team

A composite floor beam leads two lives. In the first, it is a bare steel beam carrying the metal deck, the wet concrete and the workers placing it. In the second, the slab has hardened, the shear studs lock it to the top flange, and the beam is part of a much stiffer composite section. The deflection that matters most for camber happens in the first life, and there are three ways to deal with it: a stiffer beam, a cambered beam, or a shored beam. This article compares camber vs shoring and the stiffer beam, following AISC Design Guide 36 (2020), Section 1.3 and Chapter 4.

The problem: the precomposite stage

Under its own weight and the wet concrete, the bare steel beam bends. Its stiffness is only that of the steel section, typically a third or less of the composite stiffness it will have later. A beam that easily meets the live load deflection limit as a composite member may sag noticeably under the wet slab alone.

That sag has consequences. If the concrete is screeded to a level surface, more concrete fills the dip, which adds weight, which adds deflection, a cycle engineers call concrete ponding. If the concrete is placed to a uniform thickness, the floor follows the sag. Either way, the designer has to decide where the deflection goes.

Option one: a stiffer beam

The simplest answer is a beam stiff enough that the wet concrete barely moves it. The deflection limits are checked in both stages and the beam is sized for whichever governs.

Strengths. No special fabrication, no coordination of camber values, predictable elevations for the deck and the slab, and simple erection.

Costs. More steel. On typical spans, keeping precomposite deflection small can add a noticeable amount of weight per beam, multiplied by hundreds of beams on a large floor plate. Deeper sections can also cost ceiling space.

Where it fits. Short beams, beams that cannot be cambered for connection reasons, spandrels with brittle façades, and floors where very tight levelness justifies extra stiffness.

Option two: camber

The beam is sized for strength and for the composite live load limit, then cambered to offset all or part of the precomposite dead load deflection. The bare beam starts with an upward curve, the wet concrete pulls it down, and the floor ends near its intended profile.

Strengths. Lighter steel, usually the lowest total cost, and a level enough floor for standard finishes. Design Guide 36 gives a rule of thumb that a weight saving of roughly 4.5 to 6 kg per metre (3 to 4 lb/ft) on a typical floor beam is enough to pay for mechanical cambering in the shop.

Costs. Engineering judgment on how much to camber, more information on the drawings, a shop operation and a shop measurement. Over-cambering leaves a hump and thinner slab; under-cambering leaves extra concrete.

Where it fits. Typical composite floor beams from roughly 7.6 m (25 ft) up, with webs thick enough to press and simple shear connections at both ends.

Option three: shoring

Temporary shores hold the beam up while the concrete is placed and cures. Once the slab reaches the strength needed to act compositely, the shores come out and the composite section carries everything, including the dead load.

Strengths. All deflection is resisted by the stiff composite section, so steel beams can be the lightest of the three options.

Costs. Shores fill the floor below and hold up other trades. The bottom flange has to be braced at the shores. And when the shores are removed, the dead load deflection now happens in hardened concrete, which tends to crack over the supporting girders. Mild reinforcing limits the crack width but does not stop the cracks.

Where it fits. Special areas, renovations where the structure cannot deflect, or very long spans where neither stiffness nor camber is practical.

How the industry moved from shoring to camber

Design Guide 36 tells the history briefly. In the 1960s and 1970s many fabricators had no cambering equipment, heat cambering was slow, and mill cambering ran on the mill schedule. Shoring was often the economical answer. In the 1980s large double-ram hydraulic presses arrived in fabrication shops, and cambering a rolled beam became a quick, cheap operation. From then on, camber became the default for most unshored composite floors in the US.

Comparing them on one bay

Imagine a typical office bay with beams about 12 m (40 ft) long and a normal weight slab on composite deck.

  • With stiffer beams, the designer picks a section whose bare steel deflection under the slab is small, perhaps one or two sizes heavier than the composite design needs.
  • With camber, the designer keeps the lighter section, calculates the precomposite deflection, and specifies a camber of roughly three quarters of it. The composite beam camber article explains that choice.
  • With shoring, the lightest section works, but the contractor plans shores for every bay and accepts the slab cracking risk.

For most floors, camber wins on total cost and schedule. The stiffer beam wins where camber is not advisable, and shoring wins only in special cases.

The trap of treating camber as free

Camber is cheap, but it is not free, and it is not a substitute for judgment. Some limits apply:

  • Beams shorter than about 7.6 m (25 ft) are hard to fit in a typical press; heat cambering is possible but costly.
  • Beams with very thin webs can cripple under the press rams.
  • Members in lateral systems, spandrels with brittle façades and crane girders should stay straight.
  • Very small cambers, under about 19 mm (3/4 in), rarely change the floor enough to justify the operation.

In those cases the stiffer beam is the honest answer. The when not to camber article covers each case.

What the contractor needs to know

Whichever option is chosen, the contractor's means and methods depend on it. Camber changes the elevation of the top of steel before the slab, which matters for deck installation and screed setting. Shoring changes the schedule of the floor below. Stiffer beams change the steel tonnage and sometimes the ceiling height. The design drawings should say which approach is used and, for cambered beams, how the concrete is to be placed.

A simple decision path

Design teams can work through the choice for each beam type:

  • Is the beam part of a frame, a spandrel with a brittle façade, a crane girder or a cantilever? Then a stiffer uncambered member.
  • Is it shorter than about 7.6 m (25 ft) or does it have a thin web? Usually a stiffer member.
  • Would the camber be under about 19 mm (3/4 in)? Leave it straight.
  • Otherwise, camber the beam, with the percentage chosen for the slab and placement method.
  • Is there a special area, a renovation or a span where neither works? Consider shoring there only.

This is not a formula, and the engineer of record may weigh it differently, but it reflects the logic of Design Guide 36 and the habits of most US floor designs.

What the owner should hear

For an owner, the choice is often presented as cost alone. It is also about risk and schedule. Cambered floors are well understood by US contractors, keep the floor below free for other trades, and put most of the control in the shop where it can be measured. Shored floors keep the steel lightest but slow the program and tend to crack over girders. Stiffer beams cost more steel but remove a variable. A short note in the design narrative explaining which approach was chosen, and why, helps everyone read the drawings the same way.

How World Steel supports the decision

World Steel fabricates 2,500 metric tons of structural steel a month in its own IAS AC472-accredited plant in Vietnam, much of it for multi-story steel framing and composite floor support steel. When our engineers prepare the design calculations and drawings for your Engineer of Record's review, the design report states the precomposite deflection of each typical beam, the camber proposed, and the beams kept straight on purpose.

Where a few kilograms of steel per metre would remove the need for camber, our value engineering review shows both options so your engineer can choose. Those comparisons come from real floors: the plant has fabricated multi-story frames such as the Tongwei Tien Giang feed mill and the Haid Vinh Long feed mill, where beam weight and floor schedule both mattered.

Next in the series: cold cambering in the shop.

Quick answers

Is camber cheaper than a heavier beam?

Usually. Design Guide 36 gives a rough guide that saving about 4.5 to 6 kg of steel per metre of beam (3 to 4 lb/ft) pays for mechanical cambering of a typical floor beam. Below that saving, a heavier uncambered beam can be the better buy.

Why do engineers avoid shoring composite floors?

Shores occupy the floor below, need bottom flange bracing, and slow the trades. When they are removed, the hardened slab takes the dead load deflection and tends to crack over the girders.

Does camber change the strength design of the beam?

No. A beam must be strong enough for all its loads whatever camber it has. Camber only affects serviceability, the deflected shape and the concrete volume.

Can a project mix the three approaches?

Yes. Many floors camber the typical beams, use heavier uncambered beams where camber is not advisable, such as moment frames or short spans, and shore only special areas.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

Steel beam camber series

Twenty in-depth articles built on AISC Design Guide 36: what camber is, how a shop puts it into rolled beams and welded girders, how much a composite floor beam should get, which members should stay straight, and how camber is specified, measured and accepted under the AISC Code of Standard Practice.

Camber basics

What camber is, the mill bow every rolled shape has, and the alternatives.

Making camber

Presses, torches, the strain involved, camber loss and cambered plate girders.

Composite floors

How much to camber, what changes deflection, and how the concrete goes on.

Special members

Roofs, transfer girders, cantilevers, trusses, joists and members to keep straight.

Specify and accept