Elevated floors are never perfectly level, whatever they are made of. Concrete is placed unevenly, beams and girders deflect, columns and cores shorten, foundations settle, and every trade has tolerances. AISC Design Guide 36 (2020) closes with an appendix on floor levelness because camber only succeeds when the people who design, fabricate and place a floor share one picture of what "level" means. This article summarizes that appendix.
Level, levelness and flatness
The guide separates three ideas that are often blurred:
- Level describes a surface held to a tolerance from a horizontal plane.
- Levelness describes a surface held to a tolerance from a specified plane, which may or may not be horizontal. It is an average change in elevation over longer distances and depends on strike-off accuracy and on structural deflection.
- Flatness describes how closely a surface follows a plane over short distances, its smoothness. It is mainly controlled by the finishing crew, re-straightening the surface with bull floats or riding trowels with float pans.
Camber affects levelness. It has nothing to do with flatness.
Levelness is a serviceability question
Levelness is almost never a safety issue. The exception is ponding taken to extremes: so much concrete added to level a sagging floor that the live load capacity is reduced. Otherwise, levelness is a question of fitness for use, and the requirement should follow the use of the space. A warehouse slab under racking, a laboratory with sensitive equipment, an office with raised access floor and a parking deck all need different things.
The guide observes that most levelness problems are not construction failures but divergent expectations among owner, architect, engineer and contractors. They begin when nobody states what is needed and where, and continue when the expected structural behavior is not passed to the contractor who must plan the work.
The ACI 117 trap
ACI 117 sets tolerances for concrete construction and gives a method to measure flatness and levelness with FF and FL numbers. Its FL levelness values apply to slabs on grade and shored suspended slabs only, not to unshored suspended slabs, because those deflect as the concrete is placed. Some specifications quote FL values for unshored composite floors anyway, which Design Guide 36 notes can lead to disputes. Special levelness requirements add cost, and if the use does not need them, they add no value for the owner.
How strike-off accuracy is controlled
ACI 302.1R, Section 10.3.2, and Appendix A Section A.1 of the guide describe three methods: wet-screed guides struck off to elevation, metal dry-screed guides set to elevation, and laser-guided screeds. It recommends wet screeds only where levelness is not critical, and notes that retrieving dry-screed guides on suspended slabs causes damage. On suspended slabs a combination is typical, a dry-screed guide on one side and the edge of the previous strip on the other. Laser screeds need the frame preloaded before strike-off, as the concrete placement article explains.
How camber fits in
Both placement methods use camber to offset part of the structure dead load: the slab, the deck and the steel. The variables with most influence on how the floor actually ends up are, in the guide's words, connection restraint, deck reactions from the span condition, fabrication tolerance and reduced span at column lines. Beams at column lines may deflect only 75 to 90% as much as interior beams, so their camber should be reduced even when the member size is the same.
The constant thickness method is typically the most economical in concrete and can include positive camber for shrinkage. The constant elevation method should give a more level floor, especially with a laser screed, but needs extra concrete and careful placement. Either can produce a serviceable floor.
Building a level floor: the shared process
Design Guide 36 argues that the strict division, engineer designs and contractor builds, can get in the way. The engineer sizes the members, sets camber and decides levelness needs. The contractor controls placement and finishing on a structure that moves as concrete is added. The contractor needs to know:
- the anticipated deflection of beams and girders;
- how the chosen placement method interacts with it;
- special conditions such as beams beside moment frames or chevron-braced bays.
The guide recommends:
- A preconstruction meeting before concrete placement to go through the design information and the planned placement method.
- A survey of the erected steel to compare the in-place camber of each beam and the elevation of its supports with the placement plan. This is not a check of fabricated camber, which must be verified in the shop under the AISC Code of Standard Practice, but a planning tool.
- A survey after the first placement to see whether the structure behaved as expected and adjust the method for later areas.
Where exceptionally level floors are needed, the engineer may choose deeper or heavier beams to reduce camber, which makes deflection easier to manage. In special cases a topping slab may be needed, at a cost in money and schedule.
Steel frame tolerances
Floor elevation also depends on where the steel sits. Under the AISC Code of Standard Practice, beams that connect to a column are not set to an absolute elevation but at a specified distance from the top of the column piece, with a tolerance of about +5 mm to −8 mm (+3/16 in to −5/16 in). The column top itself varies with fabrication and erection tolerance, foundation settlement and column shortening.
- Low-rise buildings, under about 10 stories, rarely need column adjustment for these differences, though conditions such as CJP-welded moment frames or lightly loaded mullion columns may.
- Concrete core buildings up to about 30 stories have traditionally ignored column shortening because it offsets core shrinkage. Where cores are set high for shrinkage, column lengths should be increased to match.
- High-rise buildings can adjust column elevations at splices by shims or by adjusting the root gap as AWS D1.1 permits.
Column tops should be surveyed as erected.
Writing a levelness requirement that works
A levelness requirement that can actually be met on a cambered steel floor tends to share a few features:
- it applies only where the use needs it, such as an equipment room, a laboratory or an area with a thin finish, not to the whole building by default;
- it describes the expected structural behavior, including the camber basis and the placement method, so the contractor can plan for it;
- it uses a measurement method suitable for an unshored suspended slab rather than slab-on-grade FL numbers;
- it says when it is measured, typically after the slab has been placed and before finishes, recognizing that later loads and shrinkage will move the floor again;
- it gives the contractor and the engineer a process for adjusting the placement after the first areas are surveyed.
Where a space truly needs a very level surface, the guide's advice is to design for it: deeper or heavier beams that need less camber, girders with less deflection, and if necessary a topping slab placed after the structure has deflected.
Levelness over the life of the building
A floor that is level at the end of construction will not stay exactly the same. Concrete shrinkage adds deflection, mostly in the first weeks. Superimposed dead load from partitions, finishes and equipment arrives later. Live load comes and goes. Columns and cores continue to shorten slightly. Camber design addresses the construction stage; the composite design and the deflection limits address what happens after. Owners who need a very level floor long term should know which stage their requirement applies to.
How World Steel supports a level floor
World Steel fabricates 2,500 metric tons of structural steel a month in its own IAS AC472-accredited plant in Vietnam, for floors from offices to data centers where equipment needs a flat, level surface. Our part is the steel: camber as specified and measured in the shop, column pieces fabricated to length with any shortening allowance your Engineer of Record gives, and connection elevations held to the tolerances of the AISC Code of Standard Practice.
We hand the US contractor, our customer, a camber and dimensional record by piece mark, so their survey of the erected steel starts from known shop values. Process plants with level equipment floors, such as the 2,500-metric-ton CPV Food factory and the 1,000-metric-ton New Era cold storage, were fabricated in the same plant with the same dimensional records.
Next in the series: roof beam camber and drainage.
Quick answers
What is the difference between level, levelness and flatness?
Level means close to a horizontal plane. Levelness is how closely a surface follows a specified plane, which may slope. Flatness is smoothness over short distances and depends mainly on the finishing crew.
Can ACI 117 FL values be specified for an elevated composite slab?
ACI 117 states that its FL levelness values apply to slabs on grade and shored slabs, not unshored suspended slabs. Specifying them anyway is a common source of disputes.
Who is responsible for a level floor?
Both sides. The engineer sizes members, sets camber and states levelness needs; the contractor plans placement and finishing. Design Guide 36 recommends a preconstruction meeting and surveys to bridge the two.
Do steel erection tolerances affect floor elevation?
Yes, slightly. Beams are set relative to the top of their column piece, and the column top varies with fabrication, erection, settlement and shortening. On low-rise buildings this rarely needs adjustment.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Design ReportWhat our US-code design report contains
- Contractor partnershipLong-term supply for US contractors
- Solutions by stateState-by-state steel solutions