Older engineers remember being told that a cambered beam "relaxes" and that only about three quarters of the specified camber would remain. If that were true, a beam fabricated in Vietnam and shipped across the Pacific would be a poor bet for camber. AISC Design Guide 36 (2020), Sections 2.2 and 2.3, traces the rule to its source and reviews the evidence on camber loss. This article summarizes what it found.
Where the 75% rule came from
The 9th Edition of the AISC Manual, from 1989, included mill practice for cold cambering rolled beams with a note that camber measured at the mill might not all be present when the beam arrived, because the cambering stresses could release. It said about 75% was likely to remain. When the 1992 AISC Code of Standard Practice added camber tolerances, it said beams received from the mill with 75% of the specified camber needed no more cambering.
The reasoning was that residual stresses put in by cambering would release over time, in handling or in transit. Design Guide 36 points out that no research or measurements were offered to support it.
What residual stresses are
Residual stresses are stresses locked inside a member with no external load on it. They balance themselves across the section: tension in one place, compression in another, adding to zero.
- From rolling. As a wide flange cools after rolling, the flange tips cool first and end up in compression, while the junction of flange and web cools last and ends up in tension. Thicker material cools more slowly and the pattern varies from beam to beam.
- From straightening and gagging. Roller straightening and gagging at the mill modify that pattern mechanically.
- From fabrication. Welding and cold bending, including cambering, modify it again.
Research referenced in the guide suggests that cold bending adds residual stress of a similar order to rolling, and that with the very gentle curvature of a typical camber, the change is slight. Residual stresses do not change the ultimate strength of a beam and, apart from a small effect on the buckling strength of compression members, are not considered in member design.
Could residual stress release remove camber?
For camber to be lost, part of the beam would have to yield again in the reverse direction. Design Guide 36 tests that idea with its 12.2 m (40 ft) example beam. Even assuming a conservative peak residual tension of about 70% of yield after cambering, it would take a concentrated load of roughly 45 kN (10 kips) at midspan just to start yielding at the most highly stressed point, with most of the flange still elastic. More load still would be needed to change the camber. Ordinary handling does not apply loads like that to a beam lying on dunnage.
Vibration in transit
Vibration during shipping has also been blamed for camber loss. The guide cites a study of vibratory stress relief, a process designed specifically to relieve residual stress by vibrating a part. It only works when the vibration stress exceeds the 0.2% proof stress of the steel; below that, no relief happens. Road, rail and sea transport do not vibrate a properly blocked beam anywhere near that stress, so they cannot release its camber.
The measurement that settled it
A study in 2003 measured 18 beams, about 9 m (30 ft) long, that were cambered at a mill and shipped to a fabricator. The camber was measured at the mill and again after unloading. The differences ranged from zero to a loss of about 3 mm (1/8 in), measured with a string line and rule to the nearest 1.5 mm (1/16 in). Given the accuracy of the method, the study concluded there was no appreciable loss.
The more interesting finding was the opposite. The beams arrived with an average camber noticeably larger than the design value, because the tolerance only allows camber at or above the specified amount. Over-camber, not loss, is the real tendency, as the composite beam camber article explains.
Design Guide 36 therefore concludes that cambers measured in the shop can be expected to remain when the beams reach site. Slender members may still need special handling and blocking, but to prevent damage, not camber loss.
What can reduce camber: welding
Welding is the one fabrication process that can measurably change camber, because a weld is a local heat source and heat can move a beam, as heat cambering shows.
- Small field welds. Minimum-size stitch welds at reasonable spacing, for example to attach a bent-plate edge form, have a negligible effect.
- Built-up members. Joining two or more shapes with substantial welding can cause a measurable loss of camber. Design Guide 36 recommends that such members be shop fabricated where possible, so that any out-of-tolerance can be corrected before shipping.
- Cap channels on crane girders. Welding a channel to the top of a beam can pull it into negative camber, which must be corrected.
Shear studs
Welding a headed shear stud is like applying a small heat spot to the top flange. Fabricators know that studding long, light pieces such as embedded angles can distort them. A study on cambered beams proposed a way to estimate the camber loss from stud welding; applied to the guide's 12.2 m (40 ft) example, the calculated loss is under about 3 mm (1/8 in). The guide concludes that only very light members with high span-to-depth ratios and many studs might see a meaningful loss. For typical floor beams it can be ignored.
On US jobs, studs are usually welded through the deck in the field after erection, so the beam leaves the fabricator unstudded. The multi-story steel framing page explains why.
What this means for overseas fabrication
For a US contractor buying steel from an overseas plant, the evidence is reassuring. Camber does not "settle" on a ship. What a reviewer should ask for is:
- a camber reading for each cambered member, measured in the shop on supports;
- blocking and dunnage that support long, slender members without bending them;
- any shop welding that could affect camber completed before the measurement, not after.
What changes camber after the shop: a short list
To keep the evidence in proportion, here is what can and cannot change the camber of a typical rolled floor beam between the shop and the pour.
Cannot, in practice
- road, rail and sea transport of a properly blocked beam;
- vibration in transit;
- time spent in storage;
- normal lifting with slings at sensible pick points.
Can
- heavy welding of attachments or built-up plates after measurement;
- welding a cap channel or cover plate to the beam;
- impact damage or a beam dropped or supported at a single point;
- loads well above normal handling, such as stacking heavy material on a long, slender beam.
Slightly, and usually negligibly
- shear studs on very light, slender beams with high composite action;
- small field welds for edge forms and deck attachments.
Each item on the "can" list is controlled by doing the welding before the camber is measured and by handling and blocking long members properly.
A note for reviewers
When an inspector on site reports "less camber than the shop record", the first question is how it was measured. A beam measured upright, on its connections, carrying deck and its own weight, is expected to show less camber than the same beam measured laid flat and unloaded in the shop. That difference is deflection under load, not camber loss. Comparing like with like, an unloaded reading against an unloaded reading, is the fair test, and the evidence reviewed in Design Guide 36 says the two will agree within the accuracy of the measurement.
How World Steel protects camber from shop to site
World Steel fabricates 2,500 metric tons of structural steel a month in its own IAS AC472-accredited plant in Vietnam and ships it to US ports. Camber is measured after all shop welding is complete, recorded against the piece mark, and checked again during QC release and packing.
Long cambered beams are blocked at regular supports in the bundle and in the container or breakbulk stowage, following our packing plan for shipping from Vietnam to the USA. If your inspector wants to check camber on arrival, the shop readings give a baseline. We have shipped long, heavy members across oceans for years, from the 5,000 metric tons of the Sunpro Steel mill to the bridge spans of the CP4 bridge in Singapore, each blocked to arrive in the shape it left the shop.
Next in the series: cambered welded plate girders.
Quick answers
Do cambered beams lose camber in shipping?
Not appreciably. Design Guide 36 concludes that normal handling, blocking and transport do not load a beam enough to yield it again, so camber measured in the shop can be expected on site.
Where did the 75% camber rule come from?
From older AISC manuals and a 1992 Code of Standard Practice provision about mill-cambered beams, based on an assumed release of residual stress. No research supported it, and later measurements found no real loss.
Can vibration in transit remove camber?
No. Vibratory stress relief only works when the vibration stress exceeds the proof stress of the steel, which transport does not come close to.
Do shear studs reduce camber?
Only slightly. For a typical 12 m (40 ft) floor beam, the calculated loss is under about 3 mm (1/8 in). It could matter only for very light, slender beams with many studs.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors