Roof beam camber: drains, slope and avoiding ponding

Roof beams are cambered on different rules from floor beams, because the goal is not a level surface but water running to the drains. Where the drains sit decides how much camber helps and how much creates a pond. This article explains both layouts.

· 6 min read · World Steel USA engineering team

On a floor, the target is a level surface. On a roof, the target is water leaving it. That changes how camber is chosen. AISC Design Guide 36 (2020), Section 5.1 explains that roof beam camber still offsets dead load deflection, but the right amount depends on the roof slope and, above all, on where the drains are. Get it wrong and the steel itself can create a pond.

Why roofs get camber

Roof members carry less dead load than composite floors in most buildings, but some roofs are heavy: concrete roof slabs, green roofs, ballasted membranes, mechanical equipment and hanging services. And roof spans can be long: big-box retail, warehouses, gymnasiums and hangars. Design Guide 36 notes that camber on roofs is typically needed where dead loads are large or spans are very long.

On roofs it is also common to offset the superimposed dead load, the roofing, insulation, equipment and ceilings that arrive after the steel. The offset can come from camber, from roof slope that keeps positive drainage, or from both.

The minimum slope

A nominally flat roof is not flat. It is typically pitched with a minimum slope of about 1 in 48, which is 1/4 in per foot or roughly 2%, from its high point to its low point. That slope can come from sloping the steel, from tapered insulation or built-up roofing, or from a combination. Camber interacts with that slope: it can help water flow toward the drains, or work against it.

Layout one: drains near the columns

In the first common layout, roof drains sit near the columns on two of the grid lines, say grids 1 and 3, and the roof slopes up to a ridge along grid 2. The roof steel is often itself sloped, with low points at the drain grids. Even when the steel is level and the slope is made in the roofing, the principle is the same: water flows toward the beam supports where the drains are.

In this layout, Design Guide 36 says it is reasonable to camber the roof beams for the structure self-weight plus 100% of the expected superimposed dead load. In the finished building a beam may still have a small upward curve. That is not harmful structurally, and unless it is unusually large it does not affect drainage, because an arched beam sheds water toward its supports, which is where the drains are.

Layout two: drains in the middle of the bays

In the second layout, drains sit at the middle of each bay. The framing is typically installed level, with a constant top-of-steel elevation, and the roofing creates the slope toward the drains.

Here, positive camber is a hazard. If the beams stay arched after all the dead load is on, the roof surface along the beams is highest at midspan and lowest at the beam supports along the grid lines, exactly the places with no drains. Water collects there. That is ponding caused purely by the steel design.

To avoid it, the guide says camber in this layout should leave a net downward curvature once all dead loads are applied. Only a fraction of the total dead load plus superimposed dead load should be offset. How large a fraction is engineering judgment, considering the loads, the spans and the net total deflection.

Ponding as a structural issue

Ponding is not only a leak problem. Water collecting in a sagging roof adds weight, which adds deflection, which collects more water. AISC 360 Appendix 2 sets out the ponding stability check for flat roofs, and ASCE 7 sets rain loads based on the drainage system. Camber that removes the sag can improve ponding behavior when drains are at the low points, but camber that moves the low points away from the drains does the opposite. The roof drainage layout should therefore be known before roof camber is set.

Roof members other than beams

Many roofs are framed with trusses, joists and joist girders rather than rolled beams.

  • Steel joists and joist girders to Steel Joist Institute specifications come with a standard camber unless the specifier says otherwise. That camber needs coordination where joists meet walls or adjacent framing at a set elevation. The truss and joist camber article covers the details.
  • Trusses are cambered at their panel points, often for dead load only, sometimes with part of the live load.
  • Pre-engineered metal building frames use tapered members with roof slopes built in, and camber is usually not specified; the frame geometry and the purlin system handle drainage.

Things to coordinate

Roof camber is a coordination exercise between the structural engineer, the architect and the roofing designer. Before setting it, confirm:

  • drain locations and the overflow or secondary drainage;
  • whether slope comes from the steel, the insulation or both;
  • heavy equipment and screens that load some beams more than others;
  • any ceilings or façades attached to roof beams that are sensitive to deflection;
  • skylights and smoke vents that need a known curb elevation.

A worked comparison of the two layouts

Picture a roof bay about 12 m (40 ft) square, with beams at 3 m (10 ft) centers spanning between girders, a concrete roof deck and a heavy rooftop unit nearby. Suppose the calculated deflection of a typical roof beam under its own weight, the deck and the roofing is 30 mm, and under all dead load including mechanical equipment and ceilings, 40 mm.

Drains at the columns. The roof slopes down to the girder lines where the drains sit. The designer can camber each beam for the full 40 mm. If the real deflection is a little less, say 32 mm because of connection restraint and the plus tolerance, the beams finish about 8 mm high at midspan. Water on the roof surface still runs along the slope to the low girder lines and on to the drains. A small hump along each beam is harmless.

Drains at mid-bay. The steel is level and tapered insulation slopes the surface to a drain at the center of the bay. Now the same 8 mm hump matters. The center of each beam is high, its ends low, and the low ends sit along the girder lines, far from the drain. Water trapped against the girder lines cannot reach the drain by the slope the roofer built. So the designer cambers only part of the dead load, perhaps 20 to 25 mm, so that each beam ends with a slight net sag toward the bay center, the same direction the insulation slopes.

The two answers differ by almost half the camber, for the same beam and the same load. That is why roof camber cannot be set from a standard percentage.

Equipment, screens and uneven loads

Roofs rarely carry uniform dead load. Mechanical units, screens, photovoltaic arrays, cooling towers and green roof zones load some beams far more than others. A beam under a heavy unit may deflect twice as much as its neighbor. If both get the same camber, one ends high and one low, and the roof surface between them twists. Where equipment is heavy, show its weight and position on the framing plan, camber those beams individually, or support the equipment on dunnage steel spanning to girders so the roof beams stay uniform.

Future equipment is a further question. If the owner plans to add units later, the camber should be set for the load that will be there for most of the building's life, and the slope should still drain with or without the future load.

How World Steel approaches roof camber

World Steel fabricates 2,500 metric tons of structural steel a month in its own IAS AC472-accredited plant in Vietnam, including long-span steel structures, steel trusses and pre-engineered metal buildings. For roofs we design, the calculations prepared for your Engineer of Record state the roof slope, the drain layout assumed and the camber of each roof member, so the reviewer can see that the low points stay at the drains.

Roof beams are cambered in the shop and measured before release; truss camber is set at the panel points in the fitting fixture and checked in shop assembly. Long-span roofs are a core part of our work, from the 5,000-metric-ton Sunpro Steel mill to the 2,500-metric-ton CPV Food factory and the M&D warehouse in Thailand.

Next in the series: transfer girder camber and cantilevers.

Quick answers

How is roof beam camber different from floor beam camber?

Roof camber aims at drainage, not a level surface. It often offsets the full structure self-weight plus the superimposed dead load, and the remaining curvature is acceptable as long as water still reaches the drains.

When can a roof beam keep some positive camber?

When the drains are near the columns and the roof slopes down to the beam supports. A slight upward curve then helps water move toward the supports and drains.

When must roof camber be limited?

When the drains sit in the middle of bays and the framing is level. A beam that stays arched would make the supports the low points, away from the drains, and water could pond.

What minimum roof slope is typical?

A nominally flat roof is typically pitched at least about 1 in 48 (1/4 in per foot), about 2%, from high to low point.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

Steel beam camber series

Twenty in-depth articles built on AISC Design Guide 36: what camber is, how a shop puts it into rolled beams and welded girders, how much a composite floor beam should get, which members should stay straight, and how camber is specified, measured and accepted under the AISC Code of Standard Practice.

Camber basics

What camber is, the mill bow every rolled shape has, and the alternatives.

Making camber

Presses, torches, the strain involved, camber loss and cambered plate girders.

Composite floors

How much to camber, what changes deflection, and how the concrete goes on.

Special members

Roofs, transfer girders, cantilevers, trusses, joists and members to keep straight.

Specify and accept

The AISC 303 tolerance, shop measurement and what the drawings should say.