Engineering and codes

Camber tolerance and shop measurement under the AISC Code of Standard Practice

The AISC Code of Standard Practice lets a cambered beam have more camber than specified but never less. This article explains the beam and truss camber tolerances, how camber is measured in the shop, and why Design Guide 36 says the shop, not the jobsite, is where camber should be verified.

· 6 min read · World Steel USA engineering team

A camber value on a drawing is only useful if everyone agrees how close the delivered beam must be. The AISC Code of Standard Practice for Steel Buildings and Bridges, AISC 303, sets that camber tolerance, and AISC Design Guide 36 (2020) explains how it plays out in the shop and on the floor. This article covers the beam and truss tolerances, how camber is measured, and where it should be verified.

The tolerances below are as cited in Design Guide 36 from the 2016 edition of AISC 303. Section numbers can move between editions; the edition named in your contract documents governs.

Beam camber tolerance

For beams and similar members specified with camber, the tolerance is:

  • minus zero, plus 13 mm (1/2 in) for members 15 m (50 ft) long or less;
  • for members longer than 15 m, a further plus 3 mm (1/8 in) for each 3 m (10 ft) of length beyond 15 m.

A 12 m (40 ft) beam specified with 30 mm of camber is acceptable from 30 mm up to 43 mm. A 21 m (70 ft) beam gets about 6 mm more allowance, so its upper limit is about 19 mm above the specified value.

Why the tolerance is plus only

The minus-zero rule makes the specified camber a minimum. That fits how designers choose camber: they already camber for less than the calculated dead load deflection, typically 75 to 85% of it, to allow for connection restraint and this very plus tolerance. If the shop could deliver less than specified, the margin would vanish.

The consequence, as Design Guide 36 notes, is that most cambered members arrive with more camber than specified. A study of mill-cambered beams found they averaged noticeably more than the design value. Designers should allow for that when choosing camber, especially on thin slabs where the plus tolerance is large compared with the deflection.

Two adjacent beams could in theory differ by the full 13 mm. Once loaded, their deflections tend to even out if their supports and restraints are similar, so the floor does not show the full difference.

Natural camber is a different tolerance

Beams with no specified camber are not held to the camber tolerance at all. Their straightness follows ASTM A6/A6M, which allows about 3 mm per 3 m of length (1/8 in per 10 ft), and they should be erected with any natural camber up. The natural mill camber article explains the difference.

Truss camber tolerance

For shop-fabricated trusses specified with camber, Section 6.4.5 of AISC 303 sets the variation at each specified camber point at plus or minus 1/800 of the distance from that point to the nearest support, measured in the shop in the unstressed condition. Trusses without specified camber are held to the same limit with a zero ordinate at each panel point. Field-assembled trusses follow Section 7.13.1.2. The truss camber article covers them.

How camber is measured

For rolled beams and girders, the usual method is still a string line and tape:

  • the member lies on supports with its web horizontal or vertical as the procedure states, typically laid flat so self-weight does not bend it about the strong axis;
  • a taut line is stretched between reference points at the ends;
  • the offset from the line to the flange is measured at midspan, and at quarter points where a profile is checked.

Design Guide 36 puts the accuracy of this method at about plus or minus 3 mm (1/8 in). Some newer cambering machines have built-in measuring devices, and optical or laser methods are used on long girders. Whatever the method, the guide says the reading should be recorded to show the member meets the tolerance.

Measure in the shop, not on site

Appendix B of Design Guide 36 is direct: require that camber be verified in the fabrication shop by quality control, quality assurance or both. It calls this the safest, most reliable and most cost-effective way to inspect camber.

The reasons are practical:

  • in the shop the member is unloaded and on known supports;
  • on site, once erected, the beam carries its self-weight and deck, sits on connections and supports that have their own tolerances, and is hard to reach;
  • correcting camber in the shop is routine; correcting it on site is not.

Appendix A adds that a survey of the erected steel before concrete placement is still valuable, but as a planning tool for the placement crew, comparing in-place camber and support elevations with the placement plan, not as a check of fabricated camber.

Tolerances that sit beside camber

Camber is one of several dimensional checks a cambered member gets:

  • length and end preparation;
  • sweep about the weak axis;
  • depth, flange tilt and web offset for built-up members;
  • hole location and spacing, including the sloped hole pattern at the ends of a cambered beam;
  • for erection, beam elevation relative to the top of the column piece, about +5 mm to −8 mm (+3/16 in to −5/16 in) under AISC 303.

What to write in the specification

To make the tolerance work as intended, the project documents should:

  • show the specified camber for each member;
  • confirm the AISC 303 edition that governs;
  • require camber measurement and records in the shop by piece mark;
  • state any tighter tolerance needed for special floors;
  • state whether owner QA will witness camber checks.

Common questions at the shop and on site

"The beam arrived 10 mm above the specified camber. Is it rejected?" Not if it is within the plus tolerance. On a beam up to 15 m (50 ft), anything up to 13 mm above the specified value meets AISC 303. The designer chose the camber knowing that.

"The site survey shows less camber than the shop record." That is expected. On site the beam carries its own weight in the strong axis, often the deck, and sits on connections and supports that have their own tolerances. A site reading is not comparable with a shop reading taken laid flat. If there is real doubt, the shop record by piece mark is the reference, and the member can be checked again unloaded.

"Can a beam that is under camber be fixed?" Yes, in the shop. It goes back into the press, or a small heat correction is made within the AISC 360 Section M2.1 temperature limit, and it is measured again.

"Can a beam that is over the tolerance be fixed?" Also yes. It can be pressed back the other way or reduced with heat. Design Guide 36 finds no basis for the old advice against reversing a beam in the press while strains stay low.

"Who witnesses the measurement?" The fabricator's quality control measures and records every cambered member. Where the project requires owner quality assurance, the QA agency may witness or check a sample. Either way, the record should travel with the member.

Measurement records that help everyone

A useful camber record for each member shows the piece mark, the specified camber, the measured camber, the tolerance applied, the method, the date and the inspector. When the US contractor plans concrete placement, those numbers let the crew see in advance which bays will carry more camber than average and where the floor is likely to be high.

Measurement on long and heavy members

Very long beams and plate girders need more care. A string line over 20 m or more sags under its own weight and wind, so a laser or optical level gives a more reliable reading. Supports must be placed so the member is not bent by its own weight in the direction being measured, which usually means measuring with the web horizontal or using several supports at known elevations. For girders shipped in pieces, each piece is measured against its part of the camber diagram and the result combined, or a shop trial assembly confirms the whole.

How World Steel measures and records camber

World Steel fabricates 2,500 metric tons of structural steel a month in its own IAS AC472-accredited plant in Vietnam, audited twice a year with IAS experts. Every cambered member is measured on supports at our straightening and dimensional control station, and the specified value, the measured value and the tolerance are entered against the piece mark on its dimensional inspection report.

Camber is checked again at QC release and packing before shipping. Remote inspector access and witnessed checks are available on request for your QA agency. Every member of the 5,000-metric-ton Sunpro Steel mill and the 2,000-metric-ton Long Son petrochemical complex left the plant with a dimensional record of this kind, under our IAS AC472 quality system.

Next in the series: specifying beam camber on drawings.

Quick answers

What is the camber tolerance for a beam under the AISC Code of Standard Practice?

Minus zero, plus 13 mm (1/2 in) for members up to 15 m (50 ft) long, with an additional 3 mm (1/8 in) allowed for each 3 m (10 ft) beyond 15 m.

Why is there no minus tolerance?

So the specified camber is a minimum. Designers set camber below the full calculated deflection, and the plus-only tolerance keeps beams from arriving flatter than the design assumed.

Where should camber be measured?

In the fabrication shop, by quality control and, where required, quality assurance. Design Guide 36 calls it the safest, most reliable and most cost-effective place to inspect camber.

How accurate is a string line camber measurement?

About plus or minus 3 mm (1/8 in), according to Design Guide 36. The reading should be recorded to show the member meets the tolerance.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

Steel beam camber series

Twenty in-depth articles built on AISC Design Guide 36: what camber is, how a shop puts it into rolled beams and welded girders, how much a composite floor beam should get, which members should stay straight, and how camber is specified, measured and accepted under the AISC Code of Standard Practice.

Camber basics

What camber is, the mill bow every rolled shape has, and the alternatives.

Making camber

Presses, torches, the strain involved, camber loss and cambered plate girders.

Composite floors

How much to camber, what changes deflection, and how the concrete goes on.

Special members

Roofs, transfer girders, cantilevers, trusses, joists and members to keep straight.

Specify and accept

The AISC 303 tolerance, shop measurement and what the drawings should say.