Everything in this series ends up as a few words and numbers on the structural drawings. If they are clear, the fabricator cambers the right members by the right amount, the inspector knows what to check, and the contractor knows how the floor will behave. If they are vague, the job finds out on the day of the pour. This final article turns AISC Design Guide 36 (2020) into a checklist for specifying beam camber in the design documents.
Camber belongs in the contract documents
The AISC Code of Standard Practice requires that camber a designer wants be shown in the contract documents. ASCE 7 Appendix C, Section C.4 says the same in serviceability terms: special camber needed to bring a loaded member into proper relation with other trades should be set out in the design documents, and if camber involves erecting a member under preload, that should be noted too.
The fabricator does not choose camber. It reads it, details it, makes it and measures it. Camber that appears only in a calculation package, or only in a reply to an RFI, is camber at risk.
Show it member by member
Design Guide 36's first rule of thumb is to show the required camber for each member on the framing plans or in the model. A single note such as "camber all floor beams 25 mm" looks efficient but hides exactly the places where camber should change:
- beams at column lines, which deflect less;
- beams next to uncambered members or walls, where the deck must step;
- frame beams and spandrels, which should not be cambered;
- beams with different spans or loads in the same bay.
Showing the value at each beam on the plan, or as a member attribute in the model, makes those differences visible to the checker, the detailer and the inspector.
State the basis
Camber values make sense only with their assumptions. The general notes or the camber schedule should say:
- what load the camber offsets: a stated share of the precomposite dead load, the full self-weight and superimposed dead load on a roof, or a staged load on a transfer girder;
- the concrete placement method assumed, constant thickness or constant elevation;
- whether extra concrete is anticipated for a level slab, so it is included in the bid;
- for trusses, the camber diagram and the panel point ordinates;
- for cantilevers, the preset tip elevation instead of camber;
- for transfer girders, the camber expected to remain as each floor is placed, or the adjusted column lengths if the girder is left straight.
Apply the limits
Design Guide 36's rules of thumb read well as a set of drawing checks.
- Reduce camber at column lines for shorter clear span, more restraint and lighter deck reactions.
- Avoid top flange holes in the middle third of cambered beams.
- No camber under about 19 mm (3/4 in): it barely affects levelness.
- No camber on spans under about 7.6 m (25 ft) without checking local equipment; a larger beam is often cheaper.
- No camber on webs under about 6 mm (1/4 in): thin webs cripple in the press.
- No camber on members with moment, brace or torsional connections: use a larger member.
- No camber on nonuniform cross sections: they twist without special procedures.
- No camber on crane beams or girders: size them for stiffness.
- No camber on spandrels supporting brittle façades: size them for stiffness.
- No camber on cantilevers: use adjustable connections and a preset tip elevation.
The when not to camber article explains each.
Name the tolerance and the inspection
The general notes should name the edition of the AISC Code of Standard Practice that governs and, if anything stricter is needed, say so. They should also carry the third rule of thumb: camber to be verified in the fabrication shop by quality control and, where the project requires it, quality assurance. Design Guide 36 calls shop verification the safest, most reliable and most cost-effective way to inspect camber. The camber tolerance article covers measurement.
Coordinate with the trades
Camber touches the deck, the concrete and the façade. Good documents:
- show connection details at cambered beam ends with short slots or flexible angles to absorb the end slope;
- tell the deck designer where cambered beams meet uncambered supports;
- say whether studs and edge forms are field welded, and any limits on field welding to cambered members;
- flag special conditions next to moment frames and chevron-braced bays;
- call for a preconstruction meeting on concrete placement and a survey of the erected steel.
Shop drawing review
The shop drawings are the last check. A reviewer should confirm that every cambered member on the design drawings carries the same value on its shop drawing, that no frame beam or spandrel picked up a camber it should not have, that flange holes in the middle third are drilled after cambering or omitted, and that the end connection details suit the sloped ends. Questions are cheapest here, before steel is cut.
A sample note set
A compact set of general notes might read:
- Camber shown for each member on framing plans is the minimum; tolerance per AISC 303 as adopted.
- Camber offsets the stated share of precomposite dead load; slab placed to constant elevation; extra concrete anticipated as noted.
- Members without camber shown: erect with natural camber up.
- Do not camber frame beams, spandrels supporting masonry, crane girders or cantilevers.
- Camber to be measured and recorded in the shop for each cambered member.
Common mistakes in camber specifications
Reviewing framing plans from many projects, the same problems recur:
- A blanket camber note on every beam, including frame beams and short infill beams.
- No reduction at column lines, leading to high points along the grid.
- Camber shown in the calculations but not on the drawings, so the detailer never sees it.
- No placement method stated, so the contractor screeds level over beams cambered for constant thickness, and the slab ends thin.
- Very small cambers, under about 19 mm (3/4 in), that add shop work without changing the floor.
- Holes for slab edge or equipment connections in the top flange at midspan, drilled before cambering.
- Moment connections at one end of a cambered beam, where the end slope cannot be absorbed.
- Camber values in imperial on metric drawings, or the reverse, without a clear unit, which invites a factor-of-25 error.
Each of these is easy to catch at the drawing stage and expensive to fix after cutting.
Camber in the model
On projects delivered through a BIM model, camber should be an attribute of each member in the model, not only a text note. The detailer's model then carries it into the shop drawings, the CNC files and the inspection record without retyping. If the design model and the detailing model are separate, the camber attribute should be part of the data exchange, and the shop drawing review should confirm that the values came across.
Units and sign conventions
Two small habits prevent many errors. First, state the unit beside every camber value or in the camber schedule heading, and use the same unit system as the rest of the drawings. On US jobs that may be inches; on drawings prepared with metric dimensions, millimetres with inches in parentheses. Second, define the direction: camber is upward unless noted, and any reverse camber, which should be rare, is shown with a clear sketch. A camber diagram for trusses and girders should give ordinates at named points rather than a curve alone, so the shop and the inspector measure the same thing.
How World Steel works from your camber specification
World Steel fabricates 2,500 metric tons of structural steel a month in its own IAS AC472-accredited plant in Vietnam. Shop drawings are included at no extra cost on every project. During shop drawing coordination, our detailers carry every camber value from your design documents into the Tekla model and the shop drawings, run the checks above, and return questions through the US contractor, our customer, before cutting.
Where our engineers prepare the design, the design report lists the camber basis and each member's value for your Engineer of Record's review and approval. To start, send your drawings and we will reply with our questions on camber along with the rest of the scope. The same review process ran on the 5,000-metric-ton Sunpro Steel mill, the 2,000-metric-ton Long Son petrochemical complex and multi-story frames such as the Tongwei Tien Giang feed mill.
This completes the series; return to the first article, steel beam camber explained.
Quick answers
Where should camber be shown on the drawings?
For each member, on the framing plans or as a member property in the model. A blanket note hides the special conditions, such as column lines and frame beams, where camber should differ.
Does the fabricator decide the camber?
No. Camber is part of the design and must be shown in the contract documents by the Engineer of Record. The fabricator produces it, measures it and records it within the AISC Code of Standard Practice tolerance.
Should the drawings say how the concrete is placed?
Yes. Camber values depend on whether the slab is placed to a constant thickness or a constant elevation, and the contractor needs to know which was assumed, and whether extra concrete is expected.
What should the general notes say about inspection?
That camber is to be verified in the fabrication shop by quality control and, where required, quality assurance, with the measured value recorded for each cambered member.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors
- Solutions by stateState-by-state steel solutions