Seismic design happens in two places: in the engineer's model and on the drawings. The model decides which members yield and how much; the drawings tell the fabricator, the erector and the inspector what that decision means for each piece of steel. If a protected zone or a demand-critical weld is not on the drawings, it does not exist on site. That is why AISC 341 has a whole section, Section A4, Structural Design Drawings and Specifications, on what the contract documents must show. In the 2022 edition it was reorganized to align with Section A4 of AISC 360-22. This article explains what belongs on seismic design drawings and how it flows to the shop.
Why the drawings carry so much weight
In ordinary steel work, a beam is a beam: the fabricator needs its size, length, camber and connections. In a seismic system, two identical beams can be very different products. One may be a gravity beam with simple shear tabs. The other, the same size and length, may be a special moment frame beam with a reduced beam section, demand-critical complete-joint-penetration welds, a protected zone where no stud or clip may go, backing removal and reinforcing fillets, and notch-tough filler metal.
The fabricator cannot work this out from the size. It must come from the drawings. AISC 341 therefore makes the Engineer of Record responsible for designating, on the contract documents, everything that turns an ordinary member into a seismic one.
What Section A4 asks the design drawings to show
AISC 341-22 Section A4 refers first to the general requirements of AISC 360-22 Section A4 and then adds the information specific to the seismic force-resisting system (SFRS). The list is long; the core items are:
The system and its members
- The designation of the SFRS, meaning the system type from ASCE 7, such as special moment frame or special concentrically braced frame, so everyone knows which chapter of AISC 341 applies.
- Identification of the members and connections that are part of the SFRS, including those of the system's columns, braces, links, collectors and chords.
- The configuration of connections, including any prequalified connection type under AISC 358 and its key dimensions.
- Material specifications for each element, including any requirement for Charpy V-notch toughness on heavy sections.
Where yielding happens
- The locations and dimensions of protected zones, the regions of the yielding members where nothing may be welded, drilled, shot or attached. For a reduced beam section, that is typically from the face of the column to the far end of the reduced section.
- Lateral bracing locations for beams and columns of the SFRS where the standard requires them, including braces at plastic hinges.
What the welds must be
- Locations of demand-critical welds, the complete-joint-penetration welds and other welds AISC 341 designates, which must use notch-tough filler metal and follow AWS D1.8.
- Weld access hole geometry where a special shape is required.
- Backing: where steel backing must be removed, and where it may stay with a reinforcing fillet weld.
- Weld tabs: where they must be removed and the end of the weld finished.
- Continuity plates and doubler plates, with the welding required at the column k-area.
- The lowest anticipated service temperature (LAST) of the steel, when it is lower than 10 °C (50 °F), because it changes the test temperature for demand-critical filler metal under AWS D1.8.
Composite and concrete interfaces
For composite systems, Section A4 adds the requirements for reinforcing steel, steel anchors and the connections between steel and concrete, including the transfer of diaphragm forces from concrete slabs into steel collectors.
Specifications: what goes in the project manual
Some requirements read better as text than as notes on a sheet. The project specification for structural steel typically adds:
- The governing editions: AISC 341-22, AISC 360-22, AISC 358-22, AWS D1.1 and D1.8, the RCSC Specification.
- The quality control and quality assurance requirements of AISC 341 Chapter J, including the inspection tasks and nondestructive testing extents.
- Submittal requirements: welding procedure specifications, procedure qualification records, filler metal certificates, heat input envelope test records and mill certificates.
- Any owner requirement beyond the code, such as marking protected zones on the steel or witnessing specific hold points.
From design drawings to shop drawings: Chapter I
AISC 341 Chapter I, Fabrication and Erection, picks up where Section A4 ends. Section I1 requires the shop drawings to show the items the design drawings designate, so that the information travels with the steel: the SFRS members and connections, the protected zones, the demand-critical welds, the access hole, backing and weld tab requirements, and the bolted joints that need prepared faying surfaces. Erection drawings must show the same information for field work, including the protected zones and the field welds and bolts in the SFRS.
That chain matters because the people who handle the steel later, the erector's crew and the trades who follow, may never see the design drawings. A protected zone shown only on the engineer's sheet does not stop an electrician from welding a hanger clip to a moment frame beam. A protected zone shown on the erection drawing, and ideally marked on the steel, does.
Common gaps in seismic drawings
Fabricators and inspectors see the same gaps again and again. Each one becomes a request for information (RFI) and a delay:
- System not designated. The drawings show braces but do not say whether they are an ordinary or a special concentrically braced frame, so the detailing rules are unclear.
- Protected zones described in words only. "Protected zones per AISC 341" without dimensions forces the detailer to guess.
- Demand-critical welds not flagged. If the drawings do not identify them, the fabricator cannot assign the right filler metal, procedures or testing.
- No service temperature. On buildings with exposed steel in cold climates, a missing LAST leaves the filler metal toughness undefined.
- Collectors not identified. Collector beams and their connections need overstrength forces; if they look like ordinary beams on the drawings, they get ordinary connections.
- Composite interfaces missing. Shear connectors, embedded plates and reinforcing at steel-to-concrete joints are left to "by others" without dimensions.
How drawing completeness changes cost and schedule
Seismic detailing is expensive where it applies and wasteful where it does not. When the drawings are vague, a careful fabricator prices the worst case: every complete-joint-penetration weld treated as demand critical, every beam end treated as a protected zone, every joint ultrasonically tested. When the drawings are precise, the price reflects what the structure actually needs.
Schedule follows the same pattern. Each unanswered question becomes an RFI, and each RFI holds the detailing of a frame line until the Engineer of Record answers. On a large multi-storey project, a handful of open questions about protected zones or weld designations can hold back hundreds of tonnes of steel. Clear Section A4 information is one of the cheapest ways to keep a seismic steel package on time.
Who reviews what
The review chain for seismic drawings has three links. The Engineer of Record reviews the shop drawings for conformance with the design intent, including the SFRS designations, protected zones and connection configurations. The fabricator's quality control checks that the shop drawings match the approved design drawings before release to the shop, and that the finished steel matches the shop drawings. The quality assurance agency for the owner verifies, under Chapter J, that the work matches the approved documents. Each link relies on the information Section A4 puts at the start of the chain.
A practical checklist for contractors
Before you send a seismic steel package out for pricing, check that the drawings or specifications answer these questions:
- Which ASCE 7 system is each frame, and which AISC 341 chapter applies?
- Which members and connections are in the SFRS?
- Where are the protected zones, with dimensions?
- Which welds are demand critical, and is AWS D1.8 specified?
- What are the access hole, backing and weld tab requirements?
- Which bolted joints are pretensioned, with which faying surface class?
- What is the lowest anticipated service temperature, if below 10 °C (50 °F)?
- Which code editions govern, and what inspection and testing does the specification require?
A package that answers all eight is priced accurately the first time, and the shop drawings come back for approval with fewer comments.
How World Steel turns design drawings into seismic shop drawings
World Steel designs and fabricates steel for US projects in its IAS AC472-accredited plant in Vietnam, and shop drawings are included on every project at no extra cost. On seismic work our detailers model the structure in Tekla and carry every Section A4 item onto the shop and erection drawings: the SFRS members and connections, the ductility class of each member, the protected zones with dimensions, the demand-critical welds, the access hole geometry and the backing and weld tab treatment. See Tekla model and BIM and shop and erection drawings.
When the design drawings leave a gap, we raise an RFI through the US contractor to the Engineer of Record before detailing that area, rather than guess. Drawings go to the Engineer of Record for review and approval, and fabrication starts only on approved drawings. You can review a real example in our sample approval drawings, follow every drawing revision and member in PEB Studio, and ask for protected zones to be marked on the steel itself so the US contractor's crews can see them on site.
The next article covers the loads the seismic system must carry beyond the code design force: overstrength, diaphragms, chords and collectors under Section B.
Quick answers
Who prepares the seismic design drawings?
The Engineer of Record prepares or approves the structural design drawings and specifications. When connection design is delegated, the steel designer prepares calculations and drawings that the Engineer of Record reviews and approves.
Must protected zones be shown on the drawings?
Yes. AISC 341 requires the locations and dimensions of protected zones to be shown on the structural design drawings, and Chapter I carries them onto the shop and erection drawings.
Why does the lowest anticipated service temperature matter?
It decides the toughness test temperature for demand-critical weld filler metal under AWS D1.8. If the steel will be colder in service than 10 °C (50 °F), the drawings must say so.
What changed in AISC 341-22 Section A4?
The requirements were reorganized to align with Section A4 of AISC 360-22, so the information for the seismic system is listed in the same structure as the rest of the steel design documents.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- Seismic steel structuresSDC D to F framing we fabricate for US jobs
- Seismic regionsWhere seismic design governs in the US
- California seismic designThe everyday AISC 341 market
- Accredited testing labsILAC ISO/IEC 17025 testing on every project
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors


