Submittal register
Every record, what it proves and when you get it
Use this list to check our records against your specification and the submittals your building official asks for.
| Document | What it proves | Reference | When you get it |
|---|---|---|---|
| Mill test certificates | Chemistry and mechanical properties of each heat of plate, coil and section. | EN 10204 3.1, Charpy V-notch on request | Before cutting, filed by heat |
| Welding procedures (WPS) and qualification records (PQR) | Each weld is made to a qualified procedure. | AWS D1.1, D1.3, D1.8 as specified | With the shop drawings |
| Welder qualification records | The people welding your steel are qualified for that procedure and position. | AWS D1.1, D1.8 as specified | With the shop drawings |
| Inspection and Test Plan | Which checks are made, how, to what acceptance criteria, and where you hold or witness. | Agreed by both parties per project | Signed before fabrication |
| Weld inspection and NDT reports | Visual inspection of every weld; UT, MT or PT results where your specification calls for them. | Your specification, AWS D1 acceptance criteria | As each lot is inspected |
| Dimensional inspection reports | Lengths, hole positions and end plates match the shop drawing. | Shop drawings, AISC tolerances as specified | As each lot is inspected |
| Coating inspection records | Surface preparation, blast profile, film thickness and adhesion of each coat. | Your coating specification | As each lot is coated |
| Nonconformance reports | What failed, how it was repaired or remade, and the re-inspection that closed it. | Our NCR procedure | With the closing photos |
| Packing lists and load plans | Which piece marks are in which bundle and container. | Matched to shipping marks | At loading |
How the WPS, PQR and welder records are written and qualified to AWS D1.1
How the data book fills up
Four dividers, filled while your steel is made
- Signed ITP
- WPS and PQR for the job
- Welder qualification records
- Mill certificates by heat
- Weld, NDT and dimensional reports
- NCRs with photos
- Coating inspection records
- Final release by QC
- Packing lists and load plans
- One indexed data book
- Searchable by piece mark and heat
- Ready for your submittal and closeout
See before you award
Read a sample Inspection and Test Plan
The sample shows how we lay out checks, methods, acceptance criteria and hold and witness points. It is a sample: the inspection items and rates for your job are agreed by both parties.
Sample ITP · free download
Sample Inspection and Test Plan (ITP), PEB warehouse
Free download: a sample of the ITP World Steel issues with a quotation: every check from shop drawings to packing, with hold, witness and review points for each party.
PDF · 129 KB · 5 pages · English and Vietnamese
How we build an ITP with you: the Inspection and Test Plan checkpoint. All samples: download center.
Kept for three years
Welding and Dimension Inspection Reports are kept at least three years after the job.
Live in PEB Studio
Every record is filed against its piece mark as it is made, so you can check progress during the job.
Delivered as PDF
The data book is indexed so a reviewer can jump from a piece mark to its certificate and reports.
Questions
Questions about quality records
What is in the data book?
Mill certificates by heat (EN 10204 3.1, Charpy V-notch on request), WPS and PQR, welder qualification records, the signed ITP, weld, NDT and dimensional reports, coating inspection records, closed NCRs, packing lists and load plans.
When do we receive the welding procedures?
With the shop drawings, before fabrication starts, so your Engineer of Record and inspector can review them first.
Do you do NDT on every weld?
Every weld gets a visual inspection. Ultrasonic, magnetic particle or dye penetrant testing is done to the extent your specification sets, and the results go into the data book.
Can we see a sample before we award?
Yes. A sample ITP for a warehouse project is free in our download center. It is a sample: the inspection items and rates for your job are agreed by both parties.
How long do you keep the records?
Welding and Dimension Inspection Reports are kept at least three years. Your copy of the data book is yours to keep with the building records.
Can the records be split by phase or building?
Yes. Records are filed by piece mark, so the data book can follow your phases, buildings or shipments.
Tell us what your submittal needs
Send your specification and the records your building official expects. We map them to the data book before the first cut, from a plant that fabricates 2,500 metric tons a month.