Hold or release
Two stickers, no grey area
A member is either on hold or accepted for delivery. There is no third state where finished is mistaken for accepted.
A missing signature, a punch-list item or a doubt about material puts the member on hold. It does not move until the person responsible for that station clears it.
After every station is signed and the final inspection is accepted, QC applies the acceptance sticker and the member is released to packing.
QC marks any defect on the member, logs it on a punch list with photos, and closes it only when the repair is accepted.
Packing for the Pacific
Bundled the way your crew will erect it
Released members are bundled by erection area and sequence, strapped to timber dunnage and tagged.
Each bundle QR lists its members, so your site team can find a piece without unpacking the yard.
Bundles are loaded into containers, onto flat-racks or as breakbulk in the order the crew will need them.
Every container gets a packing report with seal number, verified gross mass, photos and video.
What ships with your steel
Paperwork that arrives before the containers do
Shipping from Cat Lai or Cai Mep to your US gateway port is covered on our packing and shipping page.
- Packing list
Every member and bundle, matched to the erection drawings
- Container report
Seal number, verified gross mass, photos and video per container
- Manufacturing data record
Mill certificates, weld, dimensional and coating reports for the job
- PEB Studio access
The same records online, by member, bundle and container
Questions
Release and packing questions
What is the process control tag?
A tag that stays on each member through the plant. The worker, foreman and QC inspector sign it at each station, so it always shows which stages are finished and who accepted them.
What happens if a signature is missing?
The member goes on hold and is checked with the person responsible for that station. Manufacturing cannot continue with a missing signature on the tag.
When is a member released for packing?
Only after every station is signed and the final inspection is accepted. QC then applies the acceptance sticker for delivery.
How is steel packed for the US?
Members are bundled by erection area, strapped to timber dunnage, tagged with a QR and loaded in erection order into containers, onto flat-racks or as breakbulk.
What do I receive with each shipment?
A packing list, a container report with seal number, verified gross mass, photos and video, and the manufacturing data record, all also available in PEB Studio.
Built for large jobs
Put your next steel package through this station
QC release & packing is one of eight stations in a plant that fabricates 2,500 metric tons of structural steel a month, accredited under IAS AC472 since 2019 and audited twice a year. Shop drawings are included on every project.
- 5,000 tSunpro Steel Factory
- 2,500 tCPV Food Processing Factory
- 2,000 tLong Son petrochemical complex
- 2,000 tM&D (MD Factory)
Request a quote
Send drawings, a model or a steel list. Our engineers take off the quantities, check the US code basis and price the fabricated steel, delivered to your US port.
Become our partner in the US
You erect and own the customer; we design, fabricate and ship. Engineering support on your bids and OEM supply under your brand.
Watch this station work on your own job. Hold and witness points can be attended live on Zoom or Microsoft Teams, and every record is in PEB Studio.
Book an online audit