Post-disaster inspection plans for data centers: getting back inside fast

After a major earthquake or storm, a data center may be structurally fine and still sit empty for weeks, waiting for someone qualified to say it is safe. The Data Center Handbook describes a simple fix: a post-disaster inspection plan arranged before the disaster.

· updated November 23, 2026 · 5 min read · World Steel USA engineering team

Most disaster planning for data centers focuses on the event itself: keeping power on, moving IT load and protecting staff. Chapter 27 of the Data Center Handbook edited by Hwaiyu Geng (2nd edition, Wiley, 2021), on structural design and natural disaster resilience, adds a step that is easy to overlook. After the shaking or the storm, someone has to decide whether the building is safe to enter. Without a plan, that decision can take weeks. A post-disaster inspection plan, arranged in advance, can cut it to days. This article explains the handbook's guidance and how good steel records support it.

The gap after the event

The handbook is blunt about what happens after a large disaster. The moments afterward are chaotic. Building departments are flooded with requests, and even with volunteer engineers their response times are unpredictable. It can take weeks for a jurisdiction to inspect a particular facility. Hiring a consulting engineer is no easier, because every engineer in the region is suddenly busy.

For a data center, those weeks matter. A building that came through the event with little or no damage still cannot be fully reoccupied until it has been evaluated. The handbook's advice for staff is clear: the default position should be to evacuate and wait for an engineer or building official to confirm the building is safe. That is the right call for life safety, and it is also why the waiting time must be planned away rather than accepted.

The handbook's post-disaster essentials

The handbook names a few concepts every post-disaster plan should contain:

  1. Educate everyone on self-protection during the event. In an earthquake, people often run outside, but the response advocated by FEMA and others is to drop, cover and hold on.
  2. Train on-site staff to spot glaring hazards. They are not a replacement for an engineer, but they can recognize obvious danger and keep people out.
  3. Retain an engineer in advance. A prearranged retainer agreement with an engineer who can inspect one facility or several removes the scramble to find help.
  4. Let that engineer know the building beforehand. Ideally, the retained engineer has already evaluated the facility and knows where damage is most likely. That makes the inspection faster and lets the engineer brief on-site staff on specific things to watch for.

The BORP model

The handbook describes a program from San Francisco that formalizes these ideas. After the 1989 Loma Prieta earthquake, the city and the Structural Engineers Association of Northern California created the Building Occupancy Resumption Program, known as BORP. Under it:

  • the building owner contracts with an evaluating engineer;
  • the engineer prepares a post-earthquake inspection plan and submits it to the jurisdiction;
  • city officials approve the plan and register the engineer;
  • after an event, the engineer must post the building's safety rating within 3 days.

The postings follow a simple scale:

Posting Meaning
Green Safe for reoccupancy
Yellow Safe only for limited reoccupancy by trained personnel
Red Unsafe

The handbook adds that while other cities may not have a formal program, many have been willing to adopt building-specific, BORP-like arrangements when an owner brings a proposal to the building official or planning department. For an owner of a critical data center outside San Francisco, that is an invitation to ask.

What the inspection plan should contain

A useful plan for a steel-framed data center typically covers:

  • Building description. Structural system, lateral force-resisting system, foundations, design code and risk category.
  • Priority locations. Where damage is most likely: braced frame connections, moment connections, column bases, roof diaphragm edges, heavy rooftop equipment supports, equipment yard platforms, and the anchorage of suspended services.
  • Nonstructural checks. Bracing of piping, ductwork, cable trays and busway; anchorage of racks, UPS, batteries and generators; ceilings and cladding.
  • Access routes. How the engineer reaches each priority location, including roofs, ceiling spaces and platforms.
  • Hazard-specific items. For wind, roof edges, corners and rooftop screens; for flood, the water line and anything below it; for snow, drift areas and roof deflection.
  • Documents on hand. A set of current structural drawings and records kept off site and in digital form.

That last item is where the steel package helps directly.

Steel records make inspections faster

An engineer who has the structural drawings, the shop drawings and the fabrication records can inspect a steel frame far more efficiently than one who arrives with nothing. Records tell the engineer which connections are designed to yield, where the braces are, what the column base details look like and what steel grade was used. In a seismic frame, for example, protected zones and demand critical welds are exactly where an engineer should look first after an earthquake; our protected zone fabrication rules article explains why.

World Steel provides a complete set of documents with every project: shop drawings at no extra charge, erection drawings, bolt and weld details, mill certificates, and inspection records from our IAS AC472 accredited plant. Fabrication status is tracked in PEB Studio, so the record of what was built, inspected and shipped is complete. See our pages on project handover documents and quality records. For an owner preparing a post-disaster plan, that package is the starting point for the retained engineer's pre-event evaluation.

Pre-disaster evaluation and the portfolio view

The handbook places the post-disaster plan inside a wider strategy. Before any event, an owner should map the hazards at every site, rank them for earthquake, tornado, hurricane and flood, and set performance standards for each building: life safety only, damage control, or immediate occupancy. Critical data centers belong in the last group. The retained engineer's pre-event review of a building is a natural part of that process, and can identify weaknesses worth fixing before the disaster rather than after. Our articles on data center risk management and Risk Category IV design cover that strategy, and disaster recovery lessons from Sandy and Tohoku shows why it matters.

Where World Steel fits

World Steel designs and fabricates structural steel for data centers, to US codes at the risk category the owner sets, in our own plant in Vietnam. We do not inspect buildings after disasters, and post-event evaluation is the work of the owner's retained engineer and the jurisdiction. What we contribute is a well-documented frame: clear drawings, traceable materials and complete inspection records that make that engineer's job faster. Our customers are US contractors; site work, including erection, is their scope, and their Engineer of Record approves and seals the design. See the data center building package and our seismic data centers guide.

Key takeaways

  • After a major disaster, building inspections can take weeks because officials and engineers are overwhelmed.
  • The handbook recommends staff training, a retained engineer, and pre-event familiarity with the building.
  • San Francisco's BORP has a registered engineer post green, yellow or red within three days; other cities may accept similar arrangements.
  • Complete steel drawings and fabrication records shorten both the pre-event review and the post-event inspection.

Source: H. Geng (ed.), Data Center Handbook, 2nd ed., Wiley, 2021, Chapter 27. Ideas are paraphrased; consult your Engineer of Record and building official for project decisions.

Quick answers

Why can it take weeks to reoccupy a building after a disaster?

Local building departments are overwhelmed, even with volunteer engineers, and consulting engineers are in heavy demand. A building can wait a long time for an inspection even if it is undamaged.

What is BORP?

The Building Occupancy Resumption Program was set up in San Francisco after the 1989 Loma Prieta earthquake. The owner retains an engineer who prepares an inspection plan approved by the city, and that engineer posts the building green, yellow or red within three days of the event.

What do the green, yellow and red postings mean?

Green means safe to reoccupy. Yellow means limited reoccupancy by trained personnel only. Red means unsafe.

How do steel fabrication records help an inspection?

Shop drawings, connection details, material certificates and inspection records tell the engineer how the frame was built and where to look first, which speeds up the evaluation.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

Data center design series

Forty in-depth articles on planning, rating, laying out, cooling, powering, protecting and building a US data center, each read from the structural side: what the frame has to carry, where it sits on the schedule, and how World Steel designs and fabricates the steel for it in Vietnam.

Built on Hwaiyu Geng (ed.), Data Center Handbook, 2nd edition (Wiley, 2021), paraphrased and cited by chapter, with US codes and standards.

Rack AStrategy and planning

Sustainability, energy, data center types, edge sites and the cost picture.

Rack BRisk and resilience

Risk thinking, site search, Risk Category IV, performance-based seismic design and reuse of existing buildings.

Rack CNatural hazards

Wind, roof snow and rain, flood, lessons from Sandy and Tohoku, and post-event inspection.

Rack DStandards and ratings

TIA-942, Tier redundancy, ASHRAE thermal guidance, BICSI 002 and NFPA 75.

Rack EThe white space

Floor loads, ceiling height, column grid, raised floor and the overhead support steel.

Rack FCooling and air

Containment, economizers, liquid cooling, roof plant and the air the steel breathes.

Rack GPower and electrical

Generator yards, UPS and battery rooms, microgrids, grounding and electrical galleries.

Rack HBuild and operate

Project management, modular delivery, fire ratings, reliability and future growth.

Bidding a large US project?

Send the bid documents, or just a footprint and an address. Our engineers check them against US code requirements and confirm what World Steel would supply, from a plant that fabricates 2,500 metric tons of structural steel a month.