Skip to content
Seeking US contractor partners IAS AC472 ACCREDITED ★ METAL BUILDINGS ★ AC472 IAS AC472 accreditedIAS AC472
World Steel USA
Multi-storey structural steel frame with floor beams under construction, steel by World Steel

Project types

Electrical galleries and multi-story data centers: moving plant out of the white space

Modern data centers keep UPS, switchgear and cooling units out of the computer room, either in galleries beside it or on a level above or below. The Data Center Handbook explains why. Here is what each layout asks of the structural frame.

· updated November 23, 2026 · 6 min read · World Steel USA engineering team

In a small data center, the cooling units, power distribution units and even the UPS often sit inside the computer room. In larger facilities the trend runs the other way: everything that is not IT equipment moves out. Chapter 23 of the Data Center Handbook edited by Hwaiyu Geng (2nd edition, Wiley, 2021) describes the two usual ways to do it, galleries beside the computer room and a multi-story building with plant above or below. Both change the structure. Data center electrical galleries add long, heavy zones next to the data hall, and stacked levels turn a single-story shed into a framed multi-story building. This article explains the layouts and what they ask of the steel.

Why plant leaves the computer room

The handbook lists four benefits of locating non-IT systems such as CRAC and CRAH units, PDUs and UPS systems outside the computer room:

  • Fewer non-IT personnel in the IT space, and fewer IT personnel in facility spaces;
  • Heat removed: facility equipment's own heat no longer lands in the computer room;
  • Simpler IT layout: rows of cabinets are no longer interrupted by plant;
  • Cleaner coordination between the IT systems and the building systems.

There is a security and operations logic too. Maintenance on a UPS or a cooling unit no longer requires access to the white space, which matters for colocation operators who must keep tenants' equipment separate from the facility team.

Layout one: galleries

The first method the handbook describes is to place galleries adjacent to the computer room where cooling and power distribution equipment is located. Figures 23.10 and 23.11 show a fan gallery: cooling coils and fans in a long room beside the data hall, pushing air into the computer room and taking it back through return openings.

Chapter 24 adds the mechanical view. CRAC units can be installed in a cooling gallery with a demising wall separating them from the computing space. The mechanical room then becomes an entire return air plenum, so standard front-return units can be used. The handbook notes the costs and gains: fire codes may require very large dampers in the return air path, the gallery takes extra floor area, but it isolates both machine noise and maintenance workers from the IT space.

Electrical galleries follow the same idea for power: switchboards, PDUs, UPS modules and sometimes battery cabinets in a dedicated room alongside the hall, feeding busway or cable trays that cross into the computer room.

What galleries ask of the steel

  • Openings in the demising wall for air, busway and trays, framed in steel and sized for the plant behind them;
  • Heavier floor or slab zones under UPS and switchgear, with equipment loads concentrated along the gallery;
  • Roof framing over the gallery that may carry its own plant, louvers or exhaust;
  • Long, repetitive bays that suit a regular column grid running parallel to the hall;
  • Fire separations with rated walls and dampers that the frame and its fire protection must respect.

Layout two: stacking the levels

The second method is a multistory facility with the computer room above or below the level where cooling and power distribution are located. Figure 23.12 in the handbook shows a common arrangement: the computer room on the upper level, with in-cabinet closed-loop cooling, and the mechanical and electrical utility room on the lower level, holding the UPS and the chilled water piping loop.

Putting water and heavy electrical plant below the IT floor has obvious advantages. Pipes and their leaks are below the servers, not above them. Heavy UPS and switchgear sit on the ground slab or a robust lower floor. Busway and cabling rise vertically through dedicated shafts. The footprint shrinks, which matters on expensive or constrained urban land.

Stacking also brings structural consequences that a single-story data center avoids.

Floor loads on an elevated data hall

Chapter 12 summarizes the TIA-942 floor loading guidance: a minimum of 7.2 kPa (150 lb/ft²) and a recommended 12 kPa (250 lb/ft²) for computer rooms, with suspended loads of at least 1.2 kPa (25 lb/ft²) and 2.4 kPa (50 lb/ft²) recommended. On a slab on grade those numbers are easy. On an elevated floor they drive beam sizes, deck selection and column loads, and high-density racks or liquid-cooled cabinets can exceed them. Our article on data center floor load ratings explains the numbers in depth.

Vibration

Chapter 11 points to ASHRAE's Structural and Vibration Guidelines for Datacom Equipment Centers, which addresses cabinet weights beyond those of ordinary office structures and the effect of vibration on IT equipment. An elevated floor is more sensitive than a slab on grade: walking, carts, generators and rooftop plant can all excite it. Floor framing for a stacked data hall is usually checked for vibration as well as strength. Our tolerance and vibration guide covers the steel side.

Seismic and lateral design

A stacked building has more mass higher up, and equipment on upper floors experiences larger accelerations in an earthquake. Lateral systems, diaphragms and equipment anchorage all have to be designed for that. See our guide to seismic data centers.

Comparing the options

Question Galleries Multi-story
Footprint Larger, single level Smaller, stacked
Heavy plant On grade beside the hall Usually on the lower level
Water above IT Avoided by plan separation Avoided if plant is below
Structural frame Long-span single story, heavy gallery zones Floor beams, composite deck, larger columns, lateral system
Vibration Slab on grade, low concern Elevated floor, check required
Vertical paths Short horizontal crossings Shafts and risers for busway, pipe and cable

Neither is universally better. Land cost, power density, phasing and the owner's operating model decide.

The steel frame for each

For a gallery layout, the frame is a long-span data hall with an attached gallery bay, often framed as a lean-to or a second span on a shared column line. For a multi-story layout, it is a braced or moment-framed building with composite floors. Steel suits both because it is fast to erect, allows long clear spans in the data hall, and can be modified later: new openings, added platforms or strengthened beams are straightforward compared with concrete. Our multi-story data centers guide and the multi-story steel buildings package explain the framing, and our composite floor support steel and metal decking pages cover the floors.

Questions for the brief

  • Which plant goes in galleries or on other levels: UPS, batteries, switchgear, PDUs, cooling units, chilled water?
  • What floor rating does the elevated data hall need, and does liquid cooling raise it?
  • Where are the vertical shafts, and how large are the floor openings for busway and pipe?
  • What vibration criteria apply to the IT floor?
  • How will future plant be added: spare gallery length, knock-out panels, reserve floor capacity?

Where World Steel fits

World Steel designs and fabricates long-span data hall frames, gallery bays and multi-story steel frames with composite floor beams, deck support and framed openings for shafts and risers. Fabrication is done in our own plant in Vietnam with inspection accredited under IAS AC472, and members ship to the US port packed in erection order, level by level. Our customers are US contractors; site work, including erection, is their scope, and their Engineer of Record approves and seals the design. See the data center building package for the shell scope.

Key takeaways

  • The handbook recommends moving cooling and power plant out of the computer room for operations, heat and layout reasons.
  • Galleries keep plant on the same level beside the hall; multi-story buildings put it above or below, often with IT on top.
  • Elevated data halls need floor framing for TIA-942 loads, vibration checks and a lateral system for mass higher up.
  • Steel frames suit both layouts and leave room for later openings, platforms and strengthening.

Source: H. Geng (ed.), Data Center Handbook, 2nd ed., Wiley, 2021, Chapters 11, 12, 23 and 24; ANSI/TIA-942. Ideas are paraphrased; consult your Engineer of Record for project decisions.

Quick answers

Why move electrical and cooling plant out of the computer room?

The Data Center Handbook lists the benefits: fewer facility staff working in the IT space and fewer IT staff in facility spaces, the heat of facility equipment removed from the computer room, and simpler placement of IT equipment.

What does a multi-story data center put on each level?

One common arrangement places the computer room on an upper level and the mechanical and electrical utility room, including UPS and chilled water piping, on the level below.

What floor loading applies to stacked data halls?

TIA-942, as summarized in the handbook, sets a minimum floor loading of 7.2 kPa (150 lb/ft²) with 12 kPa (250 lb/ft²) recommended for computer rooms. Electrical rooms with UPS and batteries are usually heavier and are designed for the actual equipment.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

Data center design series

Forty in-depth articles on planning, rating, laying out, cooling, powering, protecting and building a US data center, each read from the structural side: what the frame has to carry, where it sits on the schedule, and how World Steel designs and fabricates the steel for it in Vietnam.

Built on Hwaiyu Geng (ed.), Data Center Handbook, 2nd edition (Wiley, 2021), paraphrased and cited by chapter, with US codes and standards.

Rack AStrategy and planning

Sustainability, energy, data center types, edge sites and the cost picture.

Rack BRisk and resilience

Risk thinking, site search, Risk Category IV, performance-based seismic design and reuse of existing buildings.

Rack CNatural hazards

Wind, roof snow and rain, flood, lessons from Sandy and Tohoku, and post-event inspection.

Rack DStandards and ratings

TIA-942, Tier redundancy, ASHRAE thermal guidance, BICSI 002 and NFPA 75.

Rack EThe white space

Floor loads, ceiling height, column grid, raised floor and the overhead support steel.

Rack FCooling and air

Containment, economizers, liquid cooling, roof plant and the air the steel breathes.

Rack GPower and electrical

Generator yards, UPS and battery rooms, microgrids, grounding and electrical galleries.

Rack HBuild and operate

Project management, modular delivery, fire ratings, reliability and future growth.

Bidding a large US project?

Send the bid documents, or just a footprint and an address. Our engineers check them against US code requirements and confirm what World Steel would supply, from a plant that fabricates 2,500 metric tons of structural steel a month.