Redundancy is the vocabulary of data center reliability. The Data Center Handbook edited by Hwaiyu Geng (2nd edition, Wiley, 2021) defines the terms in Chapter 1, explains how they map to tiers in Chapter 4, and examines how they succeed or fail in practice in Chapter 7 on risk. The terms describe electrical and mechanical systems, but data center redundancy has direct consequences for the building: how much plant it carries, where the plant sits, how the two halves of a system are kept apart, and how robust the one thing that cannot be duplicated, the structure, must be. This article explains the language and its structural meaning.
The redundancy vocabulary
The handbook defines the levels this way:
| Term | Meaning |
|---|---|
| N | The base requirement: enough capacity to carry the critical load |
| N+1 | One additional unit, module, path or system beyond the minimum |
| N+2 | Two additional units, modules, paths or systems |
| 2N | Two complete units, modules, paths or systems for every one required |
| 2(N+1) | Two complete N+1 systems |
It then lists the four tier levels in relation to component redundancy: Tier I, a basic system; Tier II, redundant components; Tier III, concurrently maintainable; and Tier IV, fault tolerant. The handbook notes that the Uptime Institute pioneered a tier certification program, that TIA-942 describes four comparable levels, and that other national standards have their own schemes. Our article on TIA-942 ratings covers that standard.
Chapter 4 adds two cautions. First, redundant components alone do not make a facility compliant with a given tier. Second, only a facility certified by the Uptime Institute can claim Uptime certification, even though many providers say their facilities meet the requirements.
Concurrent maintainability and fault tolerance
Two concepts separate the upper tiers.
Concurrent maintainability, explained in Chapter 4, means any system can be bypassed for planned maintenance or repair without affecting the computing equipment. It is a key criterion for Tier III and IV.
Fault tolerance, as described in Chapter 7's table of tiers, means system redundancy with active paths and no single point of failure from any single event: a plant, system, control or power failure, or a flood, fire or explosion. That last part is important. A fault-tolerant design must survive a physical event in one part of the building without losing the other half of the system.
2N is a building layout, not just a diagram
Chapter 7 argues that a 2N system could be considered the minimum needed for an installation free of single points of failure, with separate A and B electrical and mechanical systems. But it adds the condition that makes it work: the systems must be diverse throughout and physically separated, so that any action on one has no effect on the other. The handbook warns that well-meant "improvements" such as interconnecting links or shared storage vessels quietly reintroduce single points of failure, and that a design can look like 2N on paper while being compromised in practice.
Physical separation is a structural and architectural task:
- Separate rooms for A and B switchgear, UPS and batteries, divided by fire-rated walls. See fire-rated assemblies.
- Separate routes for A and B power and cooling distribution, often on different sides of the hall or at different levels, each with its own supports.
- Separate yards for A and B generators and transformers, far enough apart that one event cannot damage both. Our equipment yards and platforms guide shows how steel yards are laid out.
- Separate roof zones for A and B cooling plant, so that one roof failure, fire or wind event does not take out both.
What redundancy adds to the structure
Every step up the redundancy ladder adds equipment, and every piece of equipment needs space and support.
| Design choice | Structural consequence |
|---|---|
| N+1 cooling | One extra chiller or air handler on the roof or in the yard |
| 2N cooling | Twice the cooling plant; roof or yard steel sized for both sets plus maintenance access |
| 2N power | Two switchgear lineups, two UPS systems, two battery rooms with heavy floor loads |
| 2(N+1) | Two complete systems with spares; the largest plant footprint and load |
| Concurrent maintainability | Space and access to isolate and replace any unit while its partner runs |
That is why redundancy decisions belong in the structural criteria early. A roof designed for an N+1 plant cannot simply take a 2N plant later. Our heavy roof and MEP loads guide and mechanical equipment support steel explain how plant loads are carried.
Redundancy also has an energy cost. Chapter 3 of the handbook shows PUE rising at low load, and rising further with fully duplicated power paths, because fixed losses are spread over less IT load. Our PUE and the building shell article explains why phased construction helps.
The one thing that is not duplicated
Here is the structural point that redundancy diagrams leave out. There is one roof, one frame and one foundation. If an earthquake, a windstorm or a snow drift overloads the structure, both the A and B systems inside it are affected. No amount of 2N plant protects against a building that cannot be occupied.
The handbook's structural chapter draws the conclusion: code-minimum design targets life safety, not continued operation, so critical data centers should be designed to a higher performance standard, such as Risk Category IV. The more redundant the systems, the more important it is that the building does not become their common point of failure. See our articles on Risk Category IV design and performance-based seismic design. At campus scale, the only true redundancy for the building is a second building, ideally in a different hazard region.
People are the other weak point
Chapter 7 adds a sobering statistic: according to the Uptime Institute, over 70% of data center failures are caused by human error, mostly management decisions, with the rest due to operators' inexperience and complacency. Complex designs need more training to operate safely. Simple, clearly separated systems, in a building where A and B are physically obvious, are easier to run without mistakes. A clear structure with logical plant zones helps operators as much as it helps the engineers.
Where World Steel fits
World Steel designs and fabricates the steel that redundancy relies on: roof dunnage and platforms sized for N+1, 2N or 2(N+1) plant, separate equipment yards, framing for separated A and B rooms and routes, and frames designed to the risk category the owner sets. Fabrication takes place in our own plant in Vietnam, with inspection accredited under IAS AC472. Our customers are US contractors; site work, including erection, is their scope, and their Engineer of Record approves and seals the design. See the data center building package for the full shell scope.
Key takeaways
- N, N+1, N+2, 2N and 2(N+1) describe how much spare capacity a system has; tiers add concurrent maintainability and fault tolerance.
- Fault tolerance means surviving any single event, including fire and flood, which requires physical separation of A and B systems.
- Each step up in redundancy adds plant, and with it roof, yard and floor load that the structure must be designed for.
- The structure is not duplicated, so it should be designed above code minimum when the systems inside are highly redundant.
Source: H. Geng (ed.), Data Center Handbook, 2nd ed., Wiley, 2021, Chapters 1, 3, 4 and 7. Ideas are paraphrased; consult the handbook and your design team for project decisions.
Quick answers
What do N, N+1 and 2N mean?
N is the capacity needed to carry the critical load. N+1 adds one spare unit, N+2 adds two, 2N provides a complete second set, and 2(N+1) provides two complete sets that each have a spare.
What is concurrent maintainability?
The ability to take any component or path out of service for planned maintenance without affecting the IT load. It is a key requirement for Tier III and IV facilities.
What does fault tolerant mean for the building?
The handbook describes it as having no single point of failure from any single event, including plant failure, flood, fire or explosion. That requires physical separation of the A and B systems, which is a building and structural question.
Is the structure redundant?
No. There is one roof and one frame. That is why it should be designed to a higher performance level than the code minimum when the systems inside are highly redundant.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors