Air-side economizers use outside air, directly or indirectly, to cool a data center for much of the year with little or no mechanical refrigeration. Chapter 13 of the Data Center Handbook edited by Hwaiyu Geng (2nd edition, Wiley, 2021) explains how they work and why they became practical. The chapter is about thermodynamics, but the equipment it describes is large, and the air it moves must pass through the building envelope. Air-side economizer design is therefore also a building and structural topic. This article summarizes the handbook and draws out the consequences for the frame and envelope.
Why economizers took off
The handbook traces the change through ASHRAE's guidelines. The recommended range for the main server class was 20 to 25 °C in 2004 and widened to 18 to 27 °C in 2008. In 2012 the allowable range was greatly expanded to give operators room for compressor-less cooling, and in 2015 the recommended range extended to lower humidity. The handbook describes this as a shift in thinking from air conditioning to process cooling.
Climate then decides how many hours a site can be cooled by ambient air. The cooler and drier the climate, the longer the economizer season. The handbook gives the example of Reno, Nevada, where air can be supplied all year at 22 °C (72 °F) using evaporative cooling and no mechanical refrigeration. Our site selection checklist article covers climate alongside other site factors, and ASHRAE data center guidelines explains the ranges.
Direct and indirect
The handbook describes two approaches:
| Type | How it works | Notes from the handbook |
|---|---|---|
| Direct air-side economizer (DASE) | Takes outdoor air, filters and conditions it, delivers it to the space | Often combined with direct evaporative pads that cool air to near wet-bulb; arguably the most efficient and least costly technique, but humidity control is the biggest drawback |
| Indirect air-side economizer (IASE) | Outdoor "scavenger" air cools the recirculating air through an air-to-air heat exchanger | Outside air never enters the hall; heat exchanger effectiveness typically chosen around 65 to 75%; evaporative precooling of scavenger air extends the season |
In almost all climates except the coldest, the handbook notes, some mechanical cooling is still needed, and in most cases it is sized for the full load. So economizer buildings often carry both the economizer equipment and a full mechanical plant.
The trouble with outdoor air
For direct systems, the handbook lists costs of bringing large amounts of outdoor air into the building: more frequent filter changes, less control of humidity, and gaseous contaminants that standard high-efficiency filters do not capture. It also warns that systems must be designed to prevent freezing at evaporative pads and condensation in ductwork. Gaseous contamination is a serious topic for electronics, covered in the handbook's corrosion chapter, and the same air also reaches the building's steel and cladding inside the hall.
What economizers need from the building
An economizer is mostly about moving air, and air volumes for a data hall are very large. The building consequences:
- Large framed openings. Intake and relief openings, often along a full wall or in a penthouse, interrupt girts and bracing. Wall bracing must be relocated around them and openings framed with jambs and headers designed for wind on the louvers.
- Louvers, dampers and filter banks. These are heavy and must be supported by the frame or by independent steel. Damper actuators and filter walls need access platforms.
- Air handling units. Economizer units, with evaporative sections and fans, are often very large. They sit on the roof, on grade beside the building, or in galleries alongside the hall. Roof units need dunnage and platforms; ground units need pads or raised steel platforms. See HVAC platforms and equipment platforms.
- Indirect heat exchangers. Air-to-air heat exchangers for indirect systems are bulky modules, frequently stacked beside or on top of the building, with large scavenger air paths.
- Galleries and plenums. Chapter 24 describes cooling galleries separated from the hall by a demising wall, with the mechanical room acting as a return plenum. Fire codes may require large dampers in that return path. The gallery wall and its openings are framed into the structure.
- Separation of intake and exhaust. Intake openings should be placed away from relief openings, generator exhausts and cooling tower plumes. Openings fixed in the frame early are hard to move later.
- Envelope and condensation. With humid outdoor air in the system, the envelope's vapor control and the thermal breaks at girts and purlins matter. See insulated metal panels.
Wind and economizer openings
Large openings change the wind design of the building. A wall that is mostly louvers is a porous wall; a wall with large openings can raise internal pressure on the roof in a storm. In hurricane regions, louvers and their framing must be designed for wind and, where required, windborne debris. Our article on wind design for data centers covers the envelope.
Questions for the structural brief
Before the frame is laid out, the mechanical and structural teams should agree:
- Which walls or roof areas carry intake and relief openings, and how large they are;
- The weight, footprint and support points of each economizer unit, heat exchanger and filter bank;
- Whether units sit on the roof, on grade, in galleries or on raised platforms, and how they are maintained;
- Where generator exhausts and other contaminant sources are, so intakes can be kept away from them;
- Whether future expansion will add more economizer capacity, and where it would go.
Answering these early lets the bracing, girts and roof framing be arranged around the openings and equipment, rather than cut and reinforced later. It also lets the frame be designed once for the full economizer plant, even if it is installed in phases.
Where World Steel fits
World Steel designs and fabricates the steel that economizer systems need: framed intake and relief openings with relocated bracing, louver and damper support framing, roof dunnage and platforms for large air handlers and heat exchangers, gallery walls and access platforms. Fabrication takes place in our own plant in Vietnam, with inspection accredited under IAS AC472, and exposed steel can be galvanized or coated for the site's exposure. Our customers are US contractors; site work, including erection, is their scope, and their Engineer of Record approves and seals the design. See the data center building package and our heavy roof and MEP loads guide.
Key takeaways
- Wider ASHRAE ranges made outside air a mainstream cooling source; climate sets how many hours an economizer can run.
- Direct economizers bring outdoor air in and depend on filtration and humidity control; indirect economizers use heat exchangers and keep outdoor air out.
- Most sites still need full mechanical backup, so economizer buildings carry both systems.
- Economizers need large framed openings, louver and damper supports, and platforms for big air handlers and heat exchangers, all planned in the steel from the start.
Source: H. Geng (ed.), Data Center Handbook, 2nd ed., Wiley, 2021, Chapters 13, 15 and 24. Ideas are paraphrased; consult your design team for project decisions.
Quick answers
What is the difference between direct and indirect air-side economizers?
A direct economizer filters outside air and delivers it into the data hall. An indirect economizer uses outside air to cool the recirculating air through a heat exchanger, so outside air never enters the hall.
Why are economizers more common now?
Because ASHRAE widened the recommended and allowable temperature ranges for IT equipment, so outside air, sometimes with evaporative cooling, can carry the load for much more of the year.
What are the drawbacks of direct outside air?
Higher filter changes, less humidity control and the risk of gaseous contaminants that standard filters do not capture.
What does an economizer need from the structure?
Large framed openings for intake and relief, support for louvers, dampers and filter banks, and often roof or ground platforms for large air handling units or heat exchangers.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors