Among the standards that shape data centers, ANSI/BICSI 002, Data Center Design and Implementation Best Practices, has a particular character. Chapter 17 of the Data Center Handbook edited by Hwaiyu Geng (2nd edition, Wiley, 2021) describes it as not so much a standard as a data center design and operation guide. It covers planning, construction, commissioning, management and maintenance, cabling, pathways and spaces, gives guidance on modular data centers, and includes its own class structure of availability. Chapter 23, on rack floor plans and facility layout, applies BICSI 002 classes to specific design decisions. This article collects those decisions and explains what they mean for the building and its steel.
A guide with availability classes
BICSI 002 sits alongside TIA-942 and the Uptime Institute tiers as a way of matching a facility's design to its required availability. Chapter 1 of the handbook lists it among the core references for sustainable data center planning, together with ASHRAE guidance, the EU Code of Conduct, FEMA's seismic restraint guides and national standards such as GB 50174. The classes run from lower to higher availability, and the handbook's chapters refer to them both as Classes 1 to 4 and, for facility systems, as F-classes such as F2, F3 and F4.
As with every availability scheme, the classes are mostly expressed through electrical, mechanical and telecommunications requirements. But each requirement has a physical form, and the physical form is where the building comes in. Our articles on TIA-942 ratings and tiers and redundancy cover the other schemes.
Entrance pathways by class
Chapter 23 gives a clear example. The recommended minimum for entrance pathways is four 100 mm (4 in) conduits to support up to three network access providers, with one more conduit for each additional provider. The conduits are recommended to be concrete encased from the maintenance hole to the building, with at least 1.2 m (4 ft) separation from other utilities, and sealed so that water from a flooded maintenance hole cannot migrate into the data center.
The routing then depends on class:
| BICSI class | Entrance pathway, as summarized in the handbook |
|---|---|
| Class 1 | One route with at least four conduits to the entrance room |
| Class 2 | Two diverse routes, each with at least four conduits to the entrance room |
| Classes 3 and 4 | Two diverse routes, each with at least four conduits to each of two entrance rooms, plus conduits between the entrance rooms |
For the building, two diverse routes into two entrance rooms means two separate wall or slab penetrations, usually on different faces of the building, and two rooms that need framing, doors and protection. Planning those points in the steel frame from the start avoids cutting girts, relocating bracing or reworking foundations later. Our flood and tsunami design article explains why entrance points and their rooms should also sit above the flood level.
A and B power down every row
Chapter 23 also describes how class affects power distribution in the computer room. Remote power panels (RPPs) feed the rows of IT equipment. For facilities designed to Class F2 or lower, one RPP at one end of a row can meet the standard. For Classes F3 and F4, each row is fed from both an A RPP and a B RPP, typically one at each end of the row.
That doubling continues upstream: two sets of feeders, two busway or cable routes, and often two overhead distribution systems running the length of the hall. Each route is a hung load on the roof or floor framing, and the routes should be physically separate. A frame with generous hung-load capacity and a regular grid of support points makes A and B routes easy to place. See our data hall frames guide and cable support steel.
Cable trays need space between them
The handbook's cabling chapter notes that TIA and BICSI specify a separation of 300 mm (12 in) between the top of one cable tray and the bottom of the tray above it, so that cables can be installed and removed. Where several tray levels are needed for power, copper and fiber, the stack can become deep, and the depth of the raised floor or the clear height under the structure may limit how many trays fit.
That is a structural input. Clear height to the underside of the roof steel, the depth of the roof members and the position of bracing all determine whether the planned tray stack fits. Steel support frames, trapeze hangers and unistrut grids carry the trays. Our cable tray supports and pipe and cable racks pages show typical arrangements.
Grounding by class
Chapter 23 summarizes BICSI 002 guidance on grounding racks and cabinets. Each rack or cabinet should have a bonding point with direct metal-to-metal contact, without paint or powder coating in the way. The resistance to true earth should be 5, 3 or 1 ohm, measured by the fall-of-potential method, depending on the data center's class. The handbook stresses that these methods exceed building code minimums, because code grounding is about life safety while BICSI 002 and IEEE 1100 also address noise control and protection of sensitive electronics.
Structural steel is often bonded into the grounding system, so the same principle applies to the frame: where a bond is made, the contact surface must be bare metal. Masking bond locations during painting, or providing bare steel lugs, is easier in the shop than grinding coatings off on site. A later article in this series covers grounding and bonding of the steel in more depth.
Seismic restraint and modular guidance
BICSI 002 also gives guidance on modular data centers, and the handbook's Chapter 1 pairs it with FEMA guides for installing seismic restraints on ducts, pipes, electrical and mechanical equipment. In seismic regions, the trays, busway, containment and racks that BICSI layouts call for must all be braced back to the structure. See our seismic data centers guide.
Where World Steel fits
World Steel designs and fabricates steel for data centers to the loads and layouts that follow from the owner's chosen class: framed openings for diverse entrance routes, hung-load capacity for separated A and B distribution, support steel for multi-level tray stacks, and bond points kept free of coating where the grounding design calls for them. Fabrication takes place in our own plant in Vietnam, with inspection accredited under IAS AC472. We design to the codes and standards the project specifies; class compliance is confirmed by the owner's design team. Our customers are US contractors; site work, including erection, is their scope, and their Engineer of Record approves and seals the design. See the data center building package for the full shell scope.
Key takeaways
- BICSI 002 is a broad design and operations guide with its own availability classes.
- Higher classes need two diverse entrance routes and two entrance rooms, which means planned penetrations and framed rooms.
- Classes F3 and F4 feed every row from A and B panels, doubling distribution routes and hung loads.
- Tray spacing of 300 mm and grounding to 5, 3 or 1 ohm with bare-metal bonds both have direct consequences for the steel.
Source: H. Geng (ed.), Data Center Handbook, 2nd ed., Wiley, 2021, Chapters 1, 12, 17 and 23; ANSI/BICSI 002-2019. Ideas are paraphrased; the current edition of the standard governs.
Quick answers
What is BICSI 002?
ANSI/BICSI 002, Data Center Design and Implementation Best Practices, is a design and operations guide covering planning, construction, commissioning, maintenance, cabling, pathways and spaces, with a class structure of availability.
How do BICSI classes affect entrance pathways?
As summarized in the handbook: Class 1 needs one route of at least four conduits, Class 2 needs two diverse routes, and Classes 3 and 4 need two diverse routes to each of two entrance rooms.
How do classes affect power distribution in the hall?
Up to Class F2, one remote power panel per row can meet the standard. For F3 and F4, each row is fed from an A panel and a B panel, usually at opposite ends of the row.
What does BICSI say about grounding?
Racks and cabinets need a bonding point with bare metal-to-metal contact, and the resistance to earth should be 5, 3 or 1 ohm depending on the class.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors