Converting existing buildings to data centers: the structural due diligence

Warehouses, big-box stores and old plants are tempting data center shells: large footprints, high roofs, power nearby. The Data Center Handbook warns that their structures often have little reserve. Here is the structural due diligence before you sign.

· updated November 23, 2026 · 5 min read · World Steel USA engineering team

Not every data center starts on raw land. Chapter 22 of the Data Center Handbook edited by Hwaiyu Geng (2nd edition, Wiley, 2021) describes facility searches alongside site searches, and notes that existing buildings and former data centers can be attractive, though often built to outdated standards. Chapter 27, on structural design, is more direct: data centers are often housed in existing buildings constructed under older codes, and many do not meet today's requirements. Converting buildings to data centers can save time and money, but only if the structure is understood before the deal closes. This article sets out the structural due diligence.

Why existing buildings vary so much

The handbook explains that building codes evolve. After every major disaster, engineers learn what worked and what did not, and later code editions become more robust. Some methods once considered safe were later found unsafe. As a result, existing buildings show a much wider range of performance than new ones, and many do not meet the current Risk Category II requirements.

The handbook is careful not to overstate this: not every modern building is low-risk and not every old building is high-risk. Performance depends on the structural type, the quality of design and construction, later modifications and the location. That is exactly why each building needs its own assessment, and why the handbook recommends that natural hazard vulnerability be part of due diligence and budgeting, just as electrical and mechanical capacity are.

The roof: the first thing to check

The handbook singles out the building types most often considered for data centers, industrial warehouses and big-box stores, as the most likely to have:

  • roofs with very little reserve capacity;
  • inadequate consideration of snow drifting;
  • framing flexible enough to create ponding instability.

A data center adds exactly the loads these roofs were not designed for: rooftop chillers and condensers, screens, piping, hung busway, cable trays and containment. The handbook warns that strengthening roof framing can be a very significant cost and is much harder once the building is full of systems, piping, ducts and trays that block access to the framing. New rooftop equipment can also change drainage and create new drift locations; the equipment may need to be moved, raised on platforms or the roof locally strengthened.

Our guide to heavy roof and MEP loads explains what a data center roof carries, and our snow load steel buildings page covers drift and rain-on-snow effects.

Floors and slabs

A warehouse slab on grade may be adequate for storage racks but not for dense IT racks, UPS battery strings and switchgear, which concentrate load. Check the slab thickness, reinforcement, subgrade and joint layout against the planned equipment, and confirm that delivery routes for heavy equipment are on adequate slab. Where a second level is needed, a new steel mezzanine on its own foundations avoids loading the existing structure; see steel mezzanine frames.

Seismic evaluation with ASCE 41

For seismic regions, the handbook points to ASCE 41, Seismic Evaluation and Retrofit of Existing Buildings. Unlike new-building codes, ASCE 41 accepts that an existing building contains elements of varying strength and ductility, many of which would not meet new-building rules, and often requires more detailed analysis. It defines five structural performance levels:

ASCE 41 level Typical association
Immediate Occupancy Comparable to a new Risk Category IV essential facility
Damage Control Between immediate occupancy and life safety
Life Safety Comparable to a typical new building
Limited Safety Below life safety
Collapse Prevention Lowest level before collapse

The handbook's guidance: Life Safety should be the minimum when assessing an existing building for a data center, Immediate Occupancy may be the desired level, and Damage Control an acceptable one. It adds that it will be rare to find an existing building that already meets Damage Control or Immediate Occupancy, so the real choice is usually between accepting life-safety performance with no protection against long downtime, or upgrading the building.

Wind and envelope

For wind, the handbook recommends evaluating existing buildings for the forces a new building would be designed for. Overstressed roof members, framing, cladding or connections should be strengthened. Windows and doors are unlikely to resist windborne debris and may need replacement in hurricane or tornado regions, and rooftop equipment screens may need to be added or upgraded.

Retrofit timing and strategy

The handbook's most practical advice is about timing: if an upgrade is chosen, build it before the building is outfitted as a data center. Retrofitting a vacant structure is significantly cheaper and less risky. If the building is already occupied:

  • consider placing new structural elements outside the building or above the roof to limit work over the servers;
  • where interior work is unavoidable, build temporary protection over the IT equipment;
  • lay out retrofit elements to avoid conflicts with existing mechanical and electrical systems.

For existing nonstructural systems, the handbook notes that data center equipment is usually fairly new but often installed without proper seismic bracing, so anchorage is likely needed. Since existing equipment cannot usually be tested for ruggedness, isolation can be less expensive than replacement when continued function is essential.

Retrofit, replace, insure or accept

For buildings that do not meet the company's standards, the handbook lists four options: retrofit, replace, insure or accept. Retrofit can range from isolated reinforcement and equipment bracing to exterior buttresses, strengthened connections or new interior structural elements. If retrofit approaches the cost of a new building, a new resilient facility, or a second facility elsewhere for redundancy, may be the better business decision. Insurance and acceptance only make sense when retrofit or replacement cannot be justified against the risk.

The steel in a conversion

A typical conversion steel package might include:

  • new roof framing or reinforcement, and dunnage for rooftop equipment;
  • new braced frames or exterior buttress frames for lateral upgrade;
  • connection reinforcement plates and new members;
  • framed openings for louvers, economizer intakes and large doors;
  • mezzanines, equipment platforms, stairs and pipe or cable racks;
  • a new expansion hall attached to the converted building.

Retrofit steel has to fit an existing structure, so field measurement and careful detailing matter. Our seismic retrofit and expansion page explains how we work from survey data.

Where World Steel fits

World Steel designs and fabricates retrofit and expansion steel for conversions, detailed from the US contractor's survey and the Engineer of Record's retrofit design, and fabricated in our own plant in Vietnam with inspection accredited under IAS AC472. Site work, including installation of the new steel, is the US contractor's scope, and their Engineer of Record approves and seals the design. For a new hall next to a converted building, see the data center building package.

Key takeaways

  • Existing buildings vary widely in seismic, wind and snow performance; each needs its own assessment during due diligence.
  • Warehouse and big-box roofs often lack reserve capacity for data center equipment and drift; check them first.
  • ASCE 41 frames the seismic choice; the handbook suggests Life Safety as a minimum and Immediate Occupancy as the goal.
  • Retrofit before fit-out whenever possible, and compare retrofit with replacement, insurance and acceptance on business terms.

Source: H. Geng (ed.), Data Center Handbook, 2nd ed., Wiley, 2021, Chapters 22 and 27; ASCE/SEI 41. Ideas are paraphrased; consult your Engineer of Record for project decisions.

Quick answers

Can any warehouse become a data center?

Many can, but the Data Center Handbook warns that warehouses and big-box buildings often have roofs with little reserve capacity, limited allowance for snow drift, or framing flexible enough to pond. The structure must be evaluated before purchase or lease.

What standard is used to evaluate an existing building for earthquakes?

ASCE 41, Seismic Evaluation and Retrofit of Existing Buildings, with performance levels from Immediate Occupancy to Collapse Prevention.

When is the best time to retrofit?

Before the building is fitted out. Retrofit of a vacant structure is significantly cheaper and less risky than work above live servers.

What steel is typically added?

New roof framing and dunnage for equipment, reinforcement of existing members and connections, new braced frames or exterior buttresses, mezzanines and platforms, and new framed openings for louvers and doors.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

Data center design series

Forty in-depth articles on planning, rating, laying out, cooling, powering, protecting and building a US data center, each read from the structural side: what the frame has to carry, where it sits on the schedule, and how World Steel designs and fabricates the steel for it in Vietnam.

Built on Hwaiyu Geng (ed.), Data Center Handbook, 2nd edition (Wiley, 2021), paraphrased and cited by chapter, with US codes and standards.

Rack AStrategy and planning

Sustainability, energy, data center types, edge sites and the cost picture.

Rack BRisk and resilience

Risk thinking, site search, Risk Category IV, performance-based seismic design and reuse of existing buildings.

Rack CNatural hazards

Wind, roof snow and rain, flood, lessons from Sandy and Tohoku, and post-event inspection.

Rack DStandards and ratings

TIA-942, Tier redundancy, ASHRAE thermal guidance, BICSI 002 and NFPA 75.

Rack EThe white space

Floor loads, ceiling height, column grid, raised floor and the overhead support steel.

Rack FCooling and air

Containment, economizers, liquid cooling, roof plant and the air the steel breathes.

Rack GPower and electrical

Generator yards, UPS and battery rooms, microgrids, grounding and electrical galleries.

Rack HBuild and operate

Project management, modular delivery, fire ratings, reliability and future growth.

Bidding a large US project?

Send the bid documents, or just a footprint and an address. Our engineers check them against US code requirements and confirm what World Steel would supply, from a plant that fabricates 2,500 metric tons of structural steel a month.