Chapter 11 of the Data Center Handbook edited by Hwaiyu Geng (2nd edition, Wiley, 2021), written by Robert E. McFarlane, explains the work of ASHRAE Technical Committee 9.9 on mission-critical facilities and its influence on data center design. Most readers know TC 9.9 for its Thermal Guidelines, which set the temperature and humidity ranges for IT equipment. Fewer know that the same committee publishes guidance on equipment weights, floors, vibration and seismic restraint. ASHRAE data center guidelines therefore touch the building as well as the cooling plant. This article summarizes the handbook's account and draws out what it means for the structure and envelope.
The thermal envelope that changed the industry
The handbook explains that before TC 9.9, data centers were often kept very cold, out of caution. The Thermal Guidelines gave the industry, for the first time, a validated set of recommended and allowable inlet air ranges, agreed with equipment manufacturers so that their use would not void warranties or shorten equipment life.
Key points from the handbook's summary:
- The top of the recommended range for Class A1 equipment, the servers and storage common in data centers, is 27 °C (80.6 °F).
- That limit was chosen because it is roughly where most servers begin to ramp up internal fan speed. Fan energy follows approximately a cube law, so doubling fan speed can use about eight times the energy. Running warmer than 27 °C can cost more in server fan energy than it saves in cooling.
- Higher allowable ranges exist for Classes A1 to A4. In a partial or full cooling failure, equipment can run reliably at higher inlet temperatures for several days without significant harm.
- Allowable maximums are derated with altitude: for Classes A1 and A2, by 1 °C for every 300 m above 900 m; more steeply for A3 and A4.
- There are limits on the rate of temperature change, as well as on humidity and dew point.
The handbook also warns that delivering 27 °C air at the floor does not mean 27 °C at the top of the rack. Without good containment, the top servers can see inlet air near 38 °C (100 °F).
What the thermal envelope means for the building
Warmer allowable air is the reason economizers and free cooling became practical in so many climates. That has building consequences:
- Economizer openings. Air-side economizers need large intake and relief openings, louvers and dampers. Framed openings, heavy louver supports and fan walls must be planned in the steel from the start.
- Containment. Hot and cold aisle containment is what keeps the thermal envelope under control. Containment systems hang from or brace against the structure, and they interact with sprinklers and lighting.
- Hot aisles and plenums. With hotter return air, more of the building volume runs warm. Clear height above the racks for a hot-air plenum and overhead services is a structural decision.
- Envelope. In a data center, internal heat dwarfs heat through the walls, but solar gain and condensation still matter, especially where economizers bring in humid air. Insulated panels and thermal breaks at girts help. See insulated metal panels and energy code building envelopes.
- Altitude. At high-elevation sites, derated allowable temperatures reduce free-cooling hours, which can push more plant onto the roof or into the yard.
Our PUE and the building shell article covers the energy side of these choices.
The Datacom series: structure is in the book
The handbook summarizes the ASHRAE Datacom series, a set of vendor-neutral books. Several are directly relevant to the structure:
| Datacom book | Why the building team should read it |
|---|---|
| Thermal Guidelines for Data Processing Environments | Sets the temperature ranges that drive cooling, economizers and containment |
| IT Equipment Power Trends | Shows how density keeps rising, and with it heat and weight per cabinet |
| Design Considerations for Datacom Equipment Centers | Turns the guidelines into real design criteria |
| Liquid Cooling Guidelines | Covers direct liquid cooling, rear door heat exchangers and immersion, all of which add weight and piping |
| Structural and Vibration Guidelines | Covers equipment weights, raised floors, structural design of new and existing buildings, vibration and seismic restraint |
The handbook's description of Structural and Vibration Guidelines is worth quoting in substance. As density rises, a fully loaded cabinet can put loads on conventional office structures far beyond their design limits. Spreading half-full cabinets across a floor wastes expensive space. If the structural engineer does not understand cabinet weights, aisle spacings and raised floor specifications, extreme and costly measures may be specified when simpler ones would have worked. The book addresses:
- best practices for cabinet layout and structural design, for new buildings and renovations;
- the extra weight and support considerations of raised access floors;
- shock and vibration, including high-density hard disk drives that vibration can damage or destroy;
- seismic restraint for cabinets and overhead infrastructure.
Every one of these is a steel design topic. Our tolerance and vibration guide covers floor stiffness and vibration, and seismic data centers covers bracing of cabinets and overhead services.
Standard 90.4: energy, with reliability first
The handbook also explains ASHRAE/ANSI Standard 90.4, the Energy Standard for Data Centers, first published in 2016 and updated for the 2019 code cycle. Unlike the prescriptive Standard 90.1, it is performance based. It sets minimum efficiencies for mechanical and electrical systems using two metrics developed for the purpose, the mechanical load component (MLC) and the electrical loss component (ELC), rather than PUE. The handbook emphasizes that the standard was written with reliability and availability as overriding considerations. For envelope items such as exterior walls, it refers back to Standard 90.1.
For the building team, 90.4 matters because it is increasingly adopted into energy codes. Envelope compliance still follows 90.1 or the IECC, while the plant must meet 90.4's efficiency targets, which often favor larger, more efficient equipment with greater weight.
Where World Steel fits
World Steel designs and fabricates steel for data centers with the loads the ASHRAE guidance implies in mind: roof and yard steel for economizer and cooling plant, framed openings for louvers and fan walls, hung-load capacity for containment and overhead services, floor framing stiff enough for vibration-sensitive equipment, and bracing details for seismic regions. Fabrication takes place in our own plant in Vietnam, with inspection accredited under IAS AC472. Our customers are US contractors; site work, including erection, is their scope, and their Engineer of Record approves and seals the design. See the data center building package for the full shell scope.
Key takeaways
- ASHRAE TC 9.9's Thermal Guidelines set 27 °C as the top of the recommended range for Class A1 equipment, with higher allowable ranges and altitude derating.
- Warmer air made economizers and containment mainstream, which means framed openings, louver supports, hung loads and clear height.
- The Datacom series includes a structural and vibration book covering cabinet weights, raised floors, vibration and seismic restraint.
- Standard 90.4 sets performance-based energy targets for data center plant, with reliability as an overriding concern.
Source: H. Geng (ed.), Data Center Handbook, 2nd ed., Wiley, 2021, Chapter 11; ASHRAE TC 9.9 Datacom series; ANSI/ASHRAE Standard 90.4. Ideas are paraphrased; the current ASHRAE documents govern.
Quick answers
What is the ASHRAE recommended temperature for data centers?
For the common Class A1 servers and storage, the top of the recommended inlet air range is 27 °C (80.6 °F), as summarized in the Data Center Handbook. Higher allowable ranges apply for short periods and for other equipment classes.
Why 27 °C and not higher?
Because that is about where most servers start to raise internal fan speed sharply. Fan energy rises roughly with the cube of speed, so going warmer can cost more energy than it saves.
What is ASHRAE Standard 90.4?
The Energy Standard for Data Centers. It is performance based and sets minimum efficiencies for mechanical and electrical systems using its own metrics, the mechanical load component and electrical loss component.
Does ASHRAE address structure?
Yes. One book in the ASHRAE Datacom series, Structural and Vibration Guidelines, covers equipment weights, raised floors, structural design of new and existing buildings, vibration and seismic restraint.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors