Most discussion of fire in data centers is about detection and suppression: very early smoke detection, pre-action sprinklers, clean agents. Chapter 28 of the Data Center Handbook edited by Hwaiyu Geng (2nd edition, Wiley, 2021) covers all of that, and an earlier article in this series summarized it. The same chapter also explains passive protection: walls, floors and ceilings with fire-resistance ratings that hold a fire in place long enough for people to leave and for suppression to work. The structural frame that carries those assemblies is part of the picture. Data center fire resistance is therefore a structural steel topic as well as a fire protection one. This article explains where the ratings come from and how rated steel is protected.
Where the ratings come from
The handbook describes several layers of requirements that can overlap on a US data center:
- Model codes. The International Building Code (IBC) and International Fire Code (IFC) apply in most US jurisdictions as the base construction and maintenance codes, with NFPA 101 used in some.
- NFPA 75. The Standard for the Fire Protection of Information Technology Equipment requires, among other provisions, fire separation of IT rooms. The handbook notes that NFPA 75 is not referenced by the IBC or NFPA 101, so it is enforceable only where specifically adopted, but owners and insurers often require it anyway.
- Insurers. FM Global publishes its own Data Sheets; the handbook observes that TIA's Tier III requirements mirror FM Global's requirement for 1-hour rated rooms, whereas the building code does not.
- Rated or tiered systems. TIA-942 and the Uptime Institute set stricter requirements as the tier rises. The handbook notes that Tier I and II facilities typically meet code minimums while Tier III and IV exceed them.
Occupancy classification
Ratings also depend on how the building is classified. The handbook explains that data centers have historically been classified as business occupancies, because they serve a business that employs people. As data centers become larger and more autonomous, it notes, a storage occupancy classification is conceivable, but business occupancy remains the more common choice. Occupancy, building height and area, and sprinkler protection together set the construction type, and the construction type sets the required ratings for the structural frame, floors and roof.
What an hourly rating means
The handbook explains that walls, floors and ceilings are rated for three main reasons: to separate hazards, to protect the means of egress, or to allow the construction of larger buildings. The higher the hourly rating, the higher the thermal resistance.
It also makes an important caution: the hourly rating should not be read as a guarantee that an assembly will resist an adjacent fire for that long. It is the minimum time the assembly resisted a predetermined test fire curve. Real fires in a data center, fed by cable insulation and plastics, differ from the test curve, which is why ratings, detection and suppression work together.
Typical ratings under the model codes are 1 or 2 hours. The handbook adds that some standards go further, citing TIA calling for bearing walls rated as high as 4 hours for the highest tier. Rated assemblies come from sources such as the IBC, the UL Online Certifications Directory and the Gypsum Association's fire resistance design manual.
Openings, penetrations and water
A rated room is only as good as its weakest opening. The handbook points out that:
- Doors and windows in rated walls need their own rating, closers or shutters;
- Penetrations by ducts, pipes and conduit must be protected where the assembly is rated;
- Fire and smoke dampers protect duct penetrations, fire dampers activated by a fusible link and smoke dampers by smoke detection;
- Sprinkler water should be limited from spreading through the building wherever construction allows.
Data centers have unusually many penetrations: busway, cable trays, chilled water, refrigerant, containment exhaust. Every one passes through a rated wall or floor that is framed and supported by steel.
How the ratings reach the steel
When a wall, floor or roof assembly is rated, the steel that supports it usually must be rated too, otherwise the assembly can lose its support before its rating is reached. Depending on construction type, the IBC may also require ratings for columns, beams and bracing in the primary frame. The usual ways to achieve them are:
| Method | Typical use in a data center |
|---|---|
| Sprayed fire-resistive material (SFRM) | Concealed beams, columns and deck above ceilings and in plant rooms |
| Intumescent coating | Exposed steel where appearance and durability matter, or where site trades should be minimized |
| Board encasement | Columns in occupied areas, or where a hard finish is needed |
| Rated enclosure | Steel inside a rated wall or above a rated ceiling assembly |
Each method must follow a tested, listed design that sets the member sizes, protection thickness and details. Our pages on US fire-resistance requirements, intumescent vs SFRM and UL-listed fire protection products explain the choices.
Coordination points for the steel package
Fire resistance touches the steel package in ways that are easy to miss until late:
- Member sizes: listed designs often specify minimum section sizes; a lighter beam may need thicker protection;
- Primer compatibility: the shop primer must be compatible with the SFRM or intumescent product chosen;
- Connections: bolted and welded connections need the same protection as the members, and touch-up after erection;
- Rated wall lines: steel crossing a rated wall needs to be detailed so the wall can be sealed around it;
- Supports for rated ceilings and shafts: framing for rated enclosures around busway, stairs and shafts;
- Inspection: thickness readings and records, as for any other coating.
Shop-applied intumescent moves much of this work into the fabrication plant, where thickness can be controlled and recorded before shipment; see shop-applied intumescent coating and fireproofing inspection and testing. Rated walls and partitions are covered on our fire-rated assemblies page.
Questions for the brief
- What occupancy and construction type has the code consultant set, and what ratings follow for the frame, floors and roof?
- Does the owner or insurer adopt NFPA 75 or FM Global Data Sheets beyond code?
- Which tier or rated level applies, and does it raise wall or floor ratings?
- Which members are exposed and which are concealed, and which protection method suits each?
- Is the fire protection product shop-applied or site-applied, and who touches up connections?
Where World Steel fits
World Steel designs and fabricates the structural frame for data centers to the fire-resistance requirements the project's code consultant and Engineer of Record set, with primers selected for compatibility with the specified fire protection product and shop-applied intumescent available where the project calls for it. The coating products we use carry UL certification. Fabrication and coating are done in our own plant in Vietnam with inspection accredited under IAS AC472, and coating thickness is recorded before the steel ships to the US port. Our customers are US contractors; site work, including erection and site-applied fireproofing, is their scope, and their Engineer of Record approves and seals the design. See the data center building package for the full shell scope.
Key takeaways
- Ratings come from the building code, NFPA 75 where adopted, insurers such as FM Global, and tier standards.
- An hourly rating is a minimum time against a test fire, not a guarantee; 1 and 2 hours are typical, more for the highest tiers.
- Rated assemblies need rated support, so ratings reach beams, columns and deck through listed designs.
- Primer compatibility, connection protection and inspection should be settled before fabrication.
Source: H. Geng (ed.), Data Center Handbook, 2nd ed., Wiley, 2021, Chapter 28; IBC; NFPA 75. Ideas are paraphrased; consult your Engineer of Record for project decisions.
Quick answers
Why do data centers need fire-resistance-rated construction?
The Data Center Handbook explains that building codes require rated walls, floors and ceilings to separate hazards, protect the means of egress or allow larger buildings. NFPA 75, tier standards and insurers add their own separation requirements for IT rooms.
What does a 2-hour rating mean?
It is the minimum time an assembly resisted a standard test fire curve. The handbook stresses that it is not a guarantee that the assembly will survive a real fire next to it for that long.
What ratings are typical in data centers?
The handbook notes that 1-hour and 2-hour assemblies are the most common under the model building codes, while some standards ask for more; it cites TIA calling for bearing walls rated up to 4 hours for the highest tier.
How is structural steel given a fire rating?
By following a tested, listed design that specifies the protection: sprayed fire-resistive material, intumescent coating, board encasement or a rated ceiling or wall enclosure. The listing sets the member sizes and protection thicknesses.
Keep building your steel plan
Go further on USPEB.com
On this topic
Across the US market
- US codes and standardsIBC, AISC, AWS and MBMA, designed to
- Seismic steel structuresSDC D to F framing for West Coast jobs
- Crane building designUS crane standards for mill and bay buildings
- Design ReportWhat our US-code design report contains
- Large projects, 2,500 t a monthCapacity for large US general contractors
- Contractor partnershipLong-term supply for US contractors