Mill building girts and purlins: hot-rolled, cold-formed or joists, and the extra loads

Purlins and girts are the lightest steel in a mill, and the most exposed: to falling ice, dust, forklifts, furnace heat and fumes. AIST TR-13 Section 5.11 lists those loads and the choices for each. Here is how to pick the right system.

· updated November 23, 2026 · 7 min read · World Steel USA engineering team

Girts and purlins carry the cladding and transfer wind and roof loads to the frames. In a warehouse they are an afterthought, usually cold-formed Z and C sections picked from a table. In a mill they face falling ice, layers of dust, forklifts, radiant heat from furnaces and corrosive fumes, and they often support conduits, lights and small pipes as well. AIST Technical Report No. 13 (2021) covers them in Section 5.11, with commentary that compares the options. This article explains how to choose.

Three families of secondary members

Section 5.11 says roof purlins and wall girts can be:

  • hot-rolled steel sections, designed to AISC 360;
  • cold-formed steel sections, designed to AISI S100, the North American specification for cold-formed members;
  • open-web steel joists, designed to the Steel Joist Institute specification.

Each is designed for the loads set by the building code and the project specification, under its own specification. The commentary adds that the choice depends on project requirements and preferences.

How each behaves

The commentary compares the three:

Type Typical behavior Notes from the commentary
Hot-rolled sections Simply supported Doubly symmetric shapes such as W or channel sections are less sensitive to bracing details
Open-web joists Simply supported Long spans with low weight; galvanized after fabrication where needed
Cold-formed C and Z Continuous when lapped over supports Common sections typically limited to about 9 m (30 ft) span; bracing more critical

Cold-formed members gain a lot by being lapped over the frames to act as continuous beams, which cuts the bending moment and deflection. But because C and Z sections are not doubly symmetric, they twist and roll more easily, so their bracing needs more care. The cladding also matters: depending on how it is fastened, the sheeting can brace the outer flange, and that changes the design. All of these effects are covered in the referenced specifications.

Mill frame spacing is often greater than 9 m, especially in crane aisles with heavy columns at 12 to 15 m. In those bays, cold-formed purlins reach their practical limit, and hot-rolled sections, joists or an intermediate secondary frame between columns are used instead.

The loads codes do not list

Section 5.11 goes beyond code loads. It asks that additional loads and conditions be considered where they apply in the project environment:

  • falling ice, from roof edges, monitors or higher roofs onto lower ones;
  • bulk material buildup, such as dust and fines settling on purlins and girt flanges;
  • vehicle impact on wall girts near doors and traffic routes;
  • exposure to excessive heat near furnaces and hot metal paths;
  • corrosion of secondary members where the environment is aggressive.

Dust deserves attention. In a melt shop or raw material building, horizontal flanges of girts and purlins collect dust, and over months the load can approach the design snow load. TR-13 Section 3.10.4 makes the same point for ducts, ventilators and monitors on the roof. Sloped or closed sections, regular cleaning, or a design allowance all help.

Avoiding the exposure

The commentary makes a practical suggestion: rather than designing secondary members to resist every extra load, avoid exposing them to it where possible. Its examples:

  • Vehicle impact: build the lower part of the wall in concrete masonry or concrete (a wainscot), and start the girts above it.
  • Severe corrosion: use a heavier zinc coating and specify a minimum thickness.

The same approach works for heat: keep cold-formed members away from radiant heat sources, or shield them, and use hot-rolled members where heat cannot be avoided. Our article on extreme environments covers heat and corrosion in more depth.

Zinc coatings and thickness

The commentary's galvanizing notes are useful for specifications:

  • cold-formed members are normally formed from pre-galvanized sheet;
  • hot-rolled sections and open-web joists are normally hot-dip galvanized after fabrication, which gives a thicker zinc layer;
  • a specified minimum thickness usually refers to the uncoated base metal, not the coated thickness.

That last point avoids a common misunderstanding. A purlin specified as 2.5 mm minimum is 2.5 mm of steel, with the zinc on top. When comparing products, check whether the stated thickness is base metal or total coated thickness.

TR-13 Section 5.12 excludes purlins and girts from its minimum thickness rules for primary members, but the owner can still specify a minimum for secondary members in corrosive areas, as the commentary suggests.

Bracing and sag rods

Purlins and girts need bracing for stability under both gravity and uplift. For cold-formed members, the usual parts are sag rods or straps at intermediate points, anti-roll clips at the frames and bridging at the ridge and eaves. Under wind uplift the inner flange of a purlin goes into compression and is not braced by the sheeting, so the bracing must work in that direction too.

Girts face a similar issue. Wind pressure and suction alternate, so both flanges take compression in turn. Long girts on tall mill walls usually need sag rods to carry their own weight and the cladding weight back to the eave, as well as bracing for wind.

Why secondary members fail first

Walk through an older mill and the primary steel is often in fair condition while the girts and purlins tell a different story: bent girts beside doors, corroded purlin laps under leaking roof sheets, sagging members in dusty bays and holes where someone drilled a hanger. There are good reasons for this pattern:

  • secondary members are thin, so a given rate of corrosion consumes a larger share of their thickness;
  • they sit right behind the cladding, where condensation forms and leaks first show up;
  • they are the first steel a forklift meets at a wall;
  • they are light and easy to modify, so they collect unplanned attachments.

Replacing purlins and girts on a running plant means working at height over production, often with the cladding removed and the building open to the weather. Choosing the right system at the start, as Section 5.11 asks, costs little against that.

Purlins as part of the roof bracing

In many mill roofs the purlins also act as struts in the roof bracing system, carrying horizontal forces between the bracing bays and the frames. When they do, they are designed for the combined bending from roof loads and the axial strut force, and their connections to the frames must carry that force. Eave struts at the top of the walls play the same role along the eaves. Where crane forces or large wind loads go through the roof bracing, heavier hot-rolled struts are often used at the bracing lines, with lighter purlins between them.

Openings, doors and jambs

Mill walls have large openings for rail cars, trucks and process equipment. The girts stop at the opening, and the door jambs and header carry the wind load from the girts above and beside the opening back to the frames. These members are designed for the full wind load with the door closed, and for the internal pressure case where the door may be open in a storm, as discussed in our wind and snow loads article. Jambs next to forklift routes also need protection from impact.

Things hung from secondary members

Purlins and girts are tempting places to hang lights, conduits, sprinkler pipes and signage. TR-13 Section 5.13 asks that nothing be attached to structural members unless it is added to the drawings and approved by a qualified engineer. For cold-formed members this matters more than for heavy steel: a point load hung from the bottom flange of a Z purlin can twist it, and a hole drilled in the wrong place can cut its capacity. Planned hanger points, or a separate support grid for services, keep the secondary steel working as designed.

Choosing the system: a quick guide

Condition Usual choice
Frame spacing up to about 9 m, clean dry interior Lapped cold-formed Z purlins and girts, pre-galvanized
Frame spacing over 9 m Hot-rolled sections, joists or intermediate secondary frames
Near furnaces or hot metal Hot-rolled sections, shielded where needed
Corrosive fumes Hot-dip galvanized or heavier coated members, minimum base thickness specified
Vehicle routes Concrete wainscot with girts above, plus jamb protection
Dusty areas Members and slopes that shed dust, or a dust allowance

How World Steel applies it

World Steel designs and fabricates secondary framing for US projects, including wall girts, Z purlins, C purlins, sag rods, eave struts and hot-rolled secondary members. On a mill building, we:

  • choose cold-formed, hot-rolled or joist members bay by bay, based on span and exposure;
  • design for the extra loads in TR-13 Section 5.11 where the owner's environment map calls for them;
  • specify base metal thickness and zinc coating separately, and arrange hot-dip galvanizing where the exposure needs it;
  • detail hanger points for services so nothing has to be drilled or welded on site.

Cold-formed design follows AISI S100 and hot-rolled design follows AISC 360. The US Engineer of Record reviews and seals the design. Fabrication is in our plant in Vietnam, accredited under IAS AC472 and audited twice a year. Fitting the secondary framing and cladding on site is the US contractor's scope.

Solutions and the Sunpro Steel project

Our heavy industrial plants solution shows how World Steel handles a full mill or heavy plant, and the crane building system page shows the runway package. For a factory with bridge cranes, start from manufacturing plants with crane bays. The Sunpro Steel mill project, about 5,000 t with 150 t cranes, is where these TR-13 points were applied at full scale.

Source and limits

This article paraphrases AIST Technical Report No. 13 (2021), Sections 3.10.4, 5.11, 5.12 and 5.13 and the commentary to Section 5.11. The selection table is a general guide. Member types and design criteria are set by the Engineer of Record on each project.

Quick answers

How far can cold-formed purlins span in a mill?

AIST TR-13 commentary says common cold-formed sections would typically be limited to spans of about 9 m (30 ft). They can be lapped over supports to act as continuous members.

What extra loads should mill girts and purlins be designed for?

Beyond code loads, AIST TR-13 lists falling ice, bulk material buildup, vehicle impact and excessive heat where they apply, and asks that corrosion be considered.

Does the minimum thickness include the zinc coating?

Usually not. The commentary notes that a specified minimum thickness normally refers to the uncoated base metal, not the coated thickness.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AIST TR-13 mill building series

Thirty in-depth articles on AIST Technical Report No. 13: crane classes and loads, soil and foundations, floors and process loads, frames, runway girders and the shop and service side, each paraphrasing the section it follows, with metric values first.

30 articles · 6 parts

Crane classes and loadsSections 1.4–1.5, 3.7, 3.11

Building class, dynamic crane forces, load combinations and the crane data.

Site, soil and foundationsSections 2, 3.13, 4

Soil investigation, foundations under heavy cranes and the floor slab.

Frame, roof and floorsSections 5.2–5.14

Columns, bracing, trusses, girts, equipment floors and connections.

Runway girders and railsSections 3.7.3, 5.8, 5.15

Fatigue details, stiffness, backup bracing, end stops and the rail system.

Shop, testing and serviceSections 1.6, 5.16–5.17, App. C

Weld testing, tolerances, maintenance access, inspection and upgrades.