Engineering and codes

Mill building seismic design: crane mass, stored material and the nonbuilding route

Tall bays, heavy cranes and bins full of material make a mill behave differently in an earthquake from an office building. AIST TR-13 Section 3.6 explains how ASCE 7 applies, what counts as seismic mass and when to raise the risk category.

· updated November 23, 2026 · 7 min read · World Steel USA engineering team

For a long time, seismic design was something most US mill buildings could treat lightly. That has changed. The commentary to Section 3.6 of AIST Technical Report No. 13 (2021) notes that seismic requirements have changed considerably over the last twenty years and now apply to most buildings in North America. A mill building is also unusual: tall bays, heavy cranes, long spans, big equipment and bins full of material. This article explains what TR-13 asks, how it connects to ASCE 7 and AISC 341, and how it affects the steel structure.

The basic rule

Section 3.6 starts simply: every building and structure is designed to the seismic requirements of the local building code, unless the owner sets stricter ones. In the United States that means the International Building Code and, through it, ASCE 7. A geotechnical investigation should establish the site class for seismic design, which is one reason the soil report matters so much (see our article on the mill building geotechnical investigation).

The commentary then explains the philosophy behind current codes, in two realities:

  • earthquake ground motions and the forces they cause are highly uncertain;
  • designing a building to stay undamaged in a design-level earthquake is usually not economical.

So the codes design for reduced forces and rely on ductility: controlled, stable yielding that absorbs energy and softens the structure, lengthening its period and moving it away from resonance. To get that ductility, the detailing rules for each material must be followed. The stated goal is to prevent collapse and protect life. Damage in a large earthquake is expected.

The nonbuilding structure option

Here TR-13 points to a useful feature of ASCE 7. Industrial buildings often have framing and geometry that do not fit the standard building systems neatly. ASCE 7 allows a building to be classed as a nonbuilding structure similar to a building when its purpose is to enclose equipment or machinery and its occupants are engaged in maintaining or monitoring that equipment or the process.

Many mill buildings fit that description: a melt shop, a rolling mill bay or a scrap bay exists to house the process, and the people inside are operators and maintenance crews. ASCE 7's nonbuilding provisions then offer extra options. A typical trade-off, as TR-13 describes it, is to accept larger design forces (a lower response modification factor R) in return for less demanding ductility detailing.

That trade-off can make sense in a mill:

  • the frames are already heavy for crane loads and stiffness, so higher seismic forces may not change member sizes much;
  • simpler connection and bracing details are faster to fabricate and easier to inspect;
  • fewer special seismic rules mean fewer demand-critical welds and protected zones to manage.

Whether it pays off depends on the site's seismic hazard and the framing. In a high seismic region with a light roof and tall columns, a full ductile system may still be the better answer. The decision belongs to the Engineer of Record, and it should be made early because it drives the connection design.

What counts as seismic mass

Section 3.6 gives specific rules on mass, which matter a great deal in a mill:

  • Stored material. The seismic mass of tanks, bins, silos, hoppers and storage racks includes the weight of the stored material under normal operating conditions. A full bin of alloy additions or a raw material hopper above a furnace adds large mass high in the structure.
  • Cranes. The crane's own weight is part of the seismic mass. The suspended lifted load need not be included, because a load hanging on ropes does not move with the structure in the same way.
  • Rigidly held loads. If the lifted load is rigidly secured to the crane during travel, such as on a stacker crane with a rigid mast or a tong crane gripping a slab, it must be included.

The crane mass rule connects with TR-13's load combinations in Section 3.11, covered in our article on crane runway load combinations. The position of the crane along the runway also matters: parked at one end of a long building, it creates a mass eccentricity that the analysis should cover.

Equipment and structure interaction

Section 3.6 also asks that the interaction between the supporting structure and the equipment be accounted for in the seismic design of both. A large piece of equipment on a platform can have its own natural period close to the platform's, and the two can amplify each other. A heavy furnace shell, a ladle turret or a transformer on a steel deck needs to be modeled with its support, not as a simple dead load, and its anchorage needs to be designed for the forces that result.

Risk category and importance factor

Most mill buildings fall in ASCE 7's ordinary risk category. TR-13 asks for a higher one in two cases:

  • essential structures that must remain operational after an extreme earthquake, such as an emergency power building or a critical control center;
  • buildings whose collapse could cause substantial loss of life because of hazardous material inside, such as gas holders, chemical storage or areas with molten metal.

For these, the risk category and seismic importance factor are set according to ASCE 7 Chapter 1. The commentary explains the effect: a higher importance factor increases the design forces, which reduces the inelastic demand and therefore the damage. For a plant that must restart quickly after an earthquake, that can be a sound investment even where the code does not demand it.

How the seismic system shows up in the steel

Once the system is chosen, it shapes the steel in visible ways:

  • Transverse direction. Mill buildings usually resist lateral loads with rigid frames or cantilever columns across the building (TR-13 Section 5.2). Cantilever column systems have their own seismic rules in AISC 341, covered in our article on cantilever column systems.
  • Longitudinal direction. Vertical braced frames carry wind, seismic, traction and bumper forces along the building (Section 5.5). Their braces and gussets follow AISC 341 if a seismic system is used; see OCBF and SCBF braced frames.
  • Roof diaphragm and bracing. The roof bracing collects the seismic force from the roof mass and the crane girders and delivers it to the frames and braced bays.
  • Connections. Where a ductile system is used, connections are designed for the capacity of the yielding members, and welds may become demand-critical under AWS D1.8.

Seismic design also interacts with drift. TR-13 Section 5.3 limits crane-level drift under crane and wind loads to protect the runway; under the design earthquake, ASCE 7 drift limits apply instead. Both checks belong in the frame design.

A picture of one crane bay

It helps to picture where the seismic force comes from in a typical heavy crane bay. Imagine a bay 30 m wide with crane rails about 20 m above the floor, a 150 t crane and a light metal roof. Most of the seismic mass sits high up: the roof and its bracing, the crane bridge and trolley, the runway girders and rails, and the upper parts of the columns. Very little sits near the floor.

Under a transverse earthquake, that high mass pushes the frame sideways at the crane girder level and at the roof. The stepped crane columns, fixed at their bases, take the force as bending, and the base plates and anchor rods carry it into the foundations. The crane bridge itself, sitting on its wheels, can also slide or lift slightly against the rail stops and guide rollers, which is why runway details such as end stops and rail clips need attention in seismic regions.

Under a longitudinal earthquake, the same mass moves along the building. The crane girders act as struts collecting force from each frame line and delivering it to the braced bays, together with the force from the roof bracing. That is the same load path that carries crane traction and bumper forces, so the braced bays and the girder-to-column connections that feed them are designed for whichever is larger. In a high seismic region, seismic usually governs; in a low one, crane bumper forces often do.

Nonstructural parts and attachments

ASCE 7 also covers the seismic design of nonstructural components: ducts, pipes, cable trays, platforms hung from the frame, and equipment anchorage. In a mill these are numerous and heavy, and many hang from the same steel that carries the cranes. TR-13 Section 5.8.9 already forbids unplanned attachments to crane girders; seismic design adds a reason to plan every attachment to the main frame, because each one adds mass and a connection force that must be carried.

How World Steel applies it

World Steel designs and fabricates seismic steel structures for US projects. On a mill building, our engineers:

  • take the site class and design spectrum from the project's geotechnical report and ASCE 7;
  • compare the building route and the nonbuilding route with the Engineer of Record, and size frames and bracing for the chosen system;
  • include crane weight, stored material and equipment interaction as TR-13 Section 3.6 describes;
  • detail braced frames, gussets and connections to AISC 341 where a seismic system is used, with demand-critical welds made and tested to AWS D1.8.

The US Engineer of Record reviews and seals the design. Our plant in Vietnam is accredited under IAS AC472 and audited twice a year, has AWS D1.8-qualified procedures and welders, and supports protected-zone marking and remote inspector access on request. Our seismic steel structures group explains how we handle seismic force-resisting systems for US projects, and the AISC 341 page covers the provisions themselves. Site work is the US contractor's scope.

Solutions and the Sunpro Steel project

Our heavy industrial plants solution shows how World Steel handles a full mill or heavy plant, and the crane building system page shows the runway package. For a factory with bridge cranes, start from manufacturing plants with crane bays, and see the ASCE 7 page for the load basis. The Sunpro Steel mill project, about 5,000 t with 150 t cranes, is where TR-13's crane and frame guidance was applied at full scale.

Source and limits

This article paraphrases AIST Technical Report No. 13 (2021), Sections 3.6, 5.2, 5.3 and 5.5 and the commentary to Section 3.6. The seismic system, risk category and design forces are set by the Engineer of Record under the local building code on each project.

Quick answers

Does the lifted crane load count as seismic mass?

Not normally. AIST TR-13 says the suspended load need not be included, because it swings free. If the load is rigidly secured to the crane while it travels, it must be included.

Can a mill building be designed as a nonbuilding structure?

ASCE 7 allows industrial buildings that mainly enclose equipment, with occupants who maintain or monitor it, to be classed as nonbuilding structures similar to buildings. That opens options with lower R values and lighter ductility detailing.

When should a mill building use a higher risk category?

When it must stay operational after a major earthquake, or when collapse could cause substantial loss of life because of hazardous material inside. AIST TR-13 refers to ASCE 7 Chapter 1 to set the category and importance factor.

Keep building your steel plan

Go further on USPEB.com

Keep going in the series

AIST TR-13 mill building series

Thirty in-depth articles on AIST Technical Report No. 13: crane classes and loads, soil and foundations, floors and process loads, frames, runway girders and the shop and service side, each paraphrasing the section it follows, with metric values first.

30 articles · 6 parts

Crane classes and loadsSections 1.4–1.5, 3.7, 3.11

Building class, dynamic crane forces, load combinations and the crane data.

Site, soil and foundationsSections 2, 3.13, 4

Soil investigation, foundations under heavy cranes and the floor slab.

Frame, roof and floorsSections 5.2–5.14

Columns, bracing, trusses, girts, equipment floors and connections.

Runway girders and railsSections 3.7.3, 5.8, 5.15

Fatigue details, stiffness, backup bracing, end stops and the rail system.

Shop, testing and serviceSections 1.6, 5.16–5.17, App. C

Weld testing, tolerances, maintenance access, inspection and upgrades.